RoofUnder Construction2p · 3 filings
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
TEMPORARY MULTIPOINT SUSPENDED SCAFFOLDING DURING NB CONST. FILED SEP. SUSPENDED SCAFFOLD SHALL COMPLY WITH CH 33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
5 documents · 1 drawing sheet
Installation of 4 point suspended scaffold during facade inspection/repair.
On file for this project
14 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
BulkheadUnder Construction1p · 1 filing · 10 docs
Civil
Pl: Civil plumbing for sanitary and storm drainage and backflow preventer and internal water main piping. All main plumbing work is covered under NB Job# 210182069 and Plumbing application # X00432072-I1.
On file for this project
10 documents · 1 drawing sheet
Floor 29Under Construction1 filing
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
INSTALLATION OF EMERGENCY GAS GENERATOR IN CONJUNCTION WITH NEW BUILDING APPLICATION 210182069. ALL GAS WORK COVERED UNDER NB PLUMBING APPLICATION X00432072
On file for this project
4 documents
Floor 28Under Construction1p · 1 filing
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
INSTALLATION OF EMERGENCY GAS GENERATOR IN CONJUNCTION WITH NEW BUILDING APPLICATION 210182069. ALL GAS WORK COVERED UNDER NB PLUMBING APPLICATION X00432072
On file for this project
4 documents · 1 drawing sheet
Floor 27
Floor 26
Floor 25
Floor 24
Floor 23
Floor 22
Floor 21
Floor 20
Floor 19
Floor 18
Floor 17
Floor 16Under Construction1p · 1 filing
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural
Installation of 4 point suspended scaffold during facade inspection/repair.
On file for this project
14 documents · 1 drawing sheet
Floor 15
Floor 14
Floor 13
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6Under Construction1p · 2 filings
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
Installation of 4 point suspended scaffold during facade inspection/repair.
On file for this project
14 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Floor 51 filing
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Floor 41 filing
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Floor 31 filing
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Floor 21 filing
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Floor 1Under Construction9 filings · 5 docs
ArchitectureCivilEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Boiler Equipment · Curb Cut · Foundation · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sign · Sprinklers · Standpipe · Structural · Supported Scaffold
Boiler filing as per plans filed
On file for this project
3 documents
APPLICATION FILED IS FOR A NEW CURB CUT ACCESSING THE FIRE ACCESS APPARATUS ROAD (PRIVATE ROAD).
On file for this project
2 documents
APPLICATION FILED IS FOR A NEW CURB CUT ACCESSING A FIRE ACCESS APPARATUS ROAD (PRIVATE ROAD AND PRIVATE ON-SITE DRIVEWAY)
On file for this project
2 documents
Latest 3 of 9 filings on this floor.
Cellar1 filing
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
FILING UDERGROUND PLUMBING IN CONJUNCTION WITH NEW BUILDING APPLICATION 210182069 AS SHOWN PER PLAN.
On file for this project
2 documents
Site & exteriorUnder Construction11 filings · 20 docs
ArchitectureCivilElectricalEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Plumbing · Protection and Mechanical Methods · Sidewalk Shed · Supported Scaffold · Support of Excavation
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
7 documents · 10 drawing sheets
INSTALLATION OF TEMPORARY OVERHEAD PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 12 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents · 5 drawing sheets
Latest 3 of 11 filings on this floor.
Filed — no permit issued1 filing · 2 docs
MechanicalPlumbing
INSTALLATION OF NEW BOILERS IN CONJUNCTION WITH NEW BUILDING APPLICATION 210182069
On file for this project
2 documents · 2 drawing sheets