← Back
Multi-story retail building (2+)
3550 BROADWAY
MANHATTAN · BIN 1061957
💬 Discuss this project
1930Year Built
2Stories
K2Building Class
R8Zoning
13,740 sfGross Floor Area
2Units
2 Open Violations 1 unresolved · 1 paperwork only ▸
Multi-story retail building (2+) · Owner of record: R.C.J.R. REALTY LLC · 7,500 sf lot · 1.83 FAR built · Flood zone X
Locations of Work
ArchitectureOther
Floor 29p · 2 filings · 19 docs
Floor 15p · 1 filing · 16 docs
Cellar6p · 1 filing · 16 docs
1 job · most recent 05/08/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
05/08/2026——Heating and Air Conditioning Systems
Heat / Cool
York AH15S3DP2A1AAA11A3 150,000 BTU · Rooftop Unit ×1
1 job · most recent 05/08/2026
Gas
FiledStatusContractorScope
05/08/2026——Gas
2 jobs · most recent 01/09/2025
General Wiring
FiledStatusContractorScope
01/09/2025Permit IssuedCLAIRMONT ELEC'L CONTR'GGeneral Wiring
10/23/2020CompleteMARTINEZ ELECTRICAL CONT—
Building Lifecycle
All (38)Filed (5)Permit Issued (1)Violation (8)Inspection (2)Objection (16)Special Inspection (6)
05/27/2026
Objection resolved — Resolved
05/27/2026
Objection resolved — Resolved
05/26/2026
Objection raised — Cost
05/26/2026
Objection raised — Energy
05/08/2026
Filed — Alteration
Replacing rooftop air conditioning (no modification of ductwork or disturbance of building)- gas [piping only. no change in egress, use or occupancy
M01361995-S1
05/08/2026
Filed — Alteration
Replacing rooftop air conditioning (no modification of ductwork or disturbance of building)- gas [piping only. no change in egress, use or occupancy
M01361995-I1
02/19/2026
Special inspection requirement — Mechanical Systems
02/19/2026
Special inspection requirement — Final
04/08/2024
Filed — Alteration CO
HEREWITH FILE PLANS TO AMEND CERTIFICATE OF OCCUPANCY FOR 2ND FLOOR. EXISTING CO#23671. NEW HOUSE OF WORSHIP FOR 2ND FLOOR.
M00730919-P1
04/02/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
03/04/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
INHWAN CHANG
03/04/2024
Special inspection requirement — Energy Code Compliance Inspections
JAEJUN RYU
03/04/2024
Special inspection requirement — Maintenance information
JAEJUN RYU
02/21/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
11/13/2023
Permit issued — General Construction
M00730919-I1-GC
08/03/2023
Objection resolved — Addressed
07/28/2023
Objection raised — Scope
07/24/2023
Filed — No Work
M00904986-I1
07/17/2023
Special inspection requirement — Public Assembly Emergency Lighting
JAEJUN RYU
05/24/2022
Objection raised — Scope
05/24/2022
Objection resolved — Addressed
05/24/2022
Objection raised — Zoning
05/24/2022
Objection resolved — Addressed
05/24/2022
Objection raised — Structural
05/24/2022
Objection resolved — Addressed
05/24/2022
Objection raised — Zoning
05/24/2022
Objection resolved — Addressed
05/24/2022
Objection raised — Fire_Protection
05/24/2022
Objection resolved — Addressed
05/17/2022
Filed — Alteration CO
HEREWITH FILE PLANS TO AMEND CERTIFICATE OF OCCUPANCY FOR 2ND FLOOR. EXISTING CO#23671. NEW HOUSE OF WORSHIP FOR 2ND FLOOR.
M00730919-I1
02/11/2020
Violation issued (ECB, open)
Elevators
04/05/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/08/2010
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/21/2003
Violation issued (ECB, closed)
Signs
03/16/1999
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/04/1998
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/10/1997
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/02/1993
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
RCJR REALTY403/22/2026
GTTG BDWAY CORP103/22/2026
LUNA BROTHERS REALTY203/21/2026
LUNA REALTY403/21/2026
LUNA BRO REALTY103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
INSIGHT STUDIO ARCHITECTURE PC205/08/2026
H ARCHITECTURE304/08/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MJ EXPEDITNG SERVICE603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
UNIVERSAL CONSTRUCTION INGeneral Contractor203/21/2026
CLAIRMONT ELEC'L CONTR'GElectrical103/22/2026
CLAIRMONT LONDONElectrical103/21/2026
JOE MIDDLETONElectrical103/21/2026
TOP DOG PLBG & HTG CORPPlumbing103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SEAD ENGINEERING PC2665204/08/2024
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedUNIVERSAL CONSTRUCTION IN11/13/2023
BISOTISSUEDUNIVERSAL CONSTRUCTION IN04/30/2019
BISPLISSUEDTOP DOG PLBG & HTG CORP04/18/2019
BISOTISSUEDUNIVERSAL CONSTRUCTION IN03/26/2019
BISOTISSUEDC.S.D. DESIGN LLC06/19/2013
BISEQISSUEDROCKLEDGE SCAFFOLD CORP01/09/2008
BISMHISSUEDLEE DESIGN & MANANGEMENT GROUP11/09/2007
BISEQISSUEDROCKLEDGE SCAFFOLD CORP08/22/2007
BIS—ISSUEDINTERBORO SIGN & MAINTENANCE05/12/1997
BIS—ISSUEDJOHN CAPPELLI ERECTORS INC08/08/1994
BISPLISSUEDMISA PLUMBING, LLC04/11/1994
BIS—ISSUEDF.W. WOOLWORTH CO02/25/1994
BISOTISSUEDF.W.WOOLWORTH CO.02/01/1994
BISOTISSUEDF.W.WOOLWORTH CO.10/19/1993
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
04/02/2024Pass-Final CND-Occupancy InspectionPassView ↗
02/21/2024Pass-Final CND-Occupancy InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
02/19/2026Mechanical Systems—special
02/19/2026Final—progress
03/04/2024Fire-Resistant Penetrations and JointsINHWAN CHANGspecial
03/04/2024Energy Code Compliance InspectionsJAEJUN RYUprogress
03/04/2024Maintenance informationJAEJUN RYUenergy_progress
07/17/2023Public Assembly Emergency LightingJAEJUN RYUprogress
▾Documents — 94 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch4
08/27/2026M00730919-P1Request digital key ↗
08/17/2026M01361995-S1Request digital key ↗
08/15/2026M01361995-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly1
08/29/2026M00904986-I1Request digital key ↗
▸Applications & Permits19
▸BISPLAN / WORK APPROVAL APPLICATION12
09/20/2019123733237Open ↗
09/19/2019123733237Open ↗
08/02/2019123733237Open ↗
Showing 3 of 12 on file for this type
▸BISWORK PERMIT APPLICATION7
05/01/2019123733237Open ↗
05/01/2019123733237Open ↗
04/19/2019123733237Open ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications24
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION7
12/10/2019123733237Open ↗
12/10/2019123733237Open ↗
03/26/2019123733237Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/27/2026M00730919-P1Open ↗
08/27/2026M00730919-I1Open ↗
08/17/2026M01361995-I1Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
03/26/2019123733237Open ↗
06/21/2013121685970Open ↗
01/07/2008110018409Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
09/01/2026M00730919-P1Open ↗
09/01/2026M00730919-P1Open ↗
08/24/2026M00904986-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
06/21/2013121685970Open ↗
11/08/2007110018409Open ↗
▸BISPC FULL REPORT1
11/08/2007110018409Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
03/26/2019123733237Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/01/2026M00730919-P1Open ↗
▸Trade Schedules & Equipment10
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE7
09/20/2019123733237Open ↗
09/19/2019123733237Open ↗
08/01/2019123733237Open ↗
Showing 3 of 7 on file for this type
▸BISEQUIPMENT USE PERMITS1
12/10/2019123733237Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT1
12/10/2019123733237Open ↗
▸BISSCHEDULE B - PLUMBING1
06/21/2013121685970Open ↗
▸Safety & Tenant Protection4
▸DOB NOWStreet Tree Checklist2
08/13/2026M00730919-I1Open ↗
08/13/2026M00730919-P1Open ↗
▸BISTenant Protection Plan and Notes1
03/26/2019123733237Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026M00730919-I1Open ↗
▸Environmental & Asbestos5
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
03/26/2019123733237Open ↗
06/25/2013121685970Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/27/2026M00730919-P1Open ↗
08/15/2026M00730919-I1Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
11/08/2007110018409Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
12/10/2019123733237Open ↗
03/26/2019123733237Open ↗
06/21/2013121685970Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
12/10/2019123733237Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026M00730919-I1Open ↗
▸Approvals, Objections & Sign-offs4
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
12/10/2019123733237Open ↗
07/30/2008110018409Open ↗
▸BISADMINISTRATIVE OBJECTIONS2
06/21/2013121685970Open ↗
11/08/2007110018409Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT4
12/10/2019123733237Open ↗
03/26/2019123733237Open ↗
06/21/2013121685970Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms11
▸BISBOROUGH INTAKE FORM6
12/10/2019123733237Open ↗
09/19/2019123733237Open ↗
08/01/2019123733237Open ↗
Showing 3 of 6 on file for this type
▸BISADDITIONAL INFORMATION3
09/20/2019123733237Open ↗
06/10/2019123733237Open ↗
06/05/2019123733237Open ↗
▸BISEFILING COVER SHEET2
03/26/2019123733237Open ↗
06/21/2013121685970Open ↗
▸Other Documents3
▸DOB NOWProperty Ownership Certification2
08/27/2026M00730919-P1Open ↗
08/15/2026M00730919-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026M00730919-I1Open ↗