← Back
Three families
3553 CARLISLE PLACE
BRONX · BIN 2057751
💬 Discuss this project
1915Year Built
2Stories
C0Building Class
R6AZoning
2,420 sfGross Floor Area
3Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Three families · Owner of record: 3553 CARLISLE LLC · 2,500 sf lot · 0.97 FAR built · Flood zone X
Locations of Work
ArchitectureFire ProtectionGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction11p · 1 filing · 20 docs
Floor 3Under Construction9p · 1 filing · 20 docs
Floor 2Under Construction11p · 1 filing · 20 docs
Floor 1Under Construction11p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
3553 CARLISLE LLC203/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/10/2019$500K—Private party → 1210 COLL LLC$207/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LESTER KATZ, NCARB412/09/2024
VASILIOS ARTEMIOU PE105/26/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
XPDITE GROUP LLC (104)503/21/2026
XPDITE GROUP LLC 104103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JHZ CONSULTING SERVICES *General Contractor204/09/2026
FRIED ELECTRIC CO.Electrical103/22/2026
DYNAMIC PLBNG & SPRKR CORFire Protection107/08/2026
INFINITI ESC PLUMBING CORPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616512/09/2024
Building Lifecycle
All (144)Filed (5)Permit Issued (4)Signed Off (3)Violation (60)Inspection (12)Objection (30)Special Inspection (30)
01/17/2025
Signed off — Alteration CO
APPLICATION FILED HEREWITH TO CONVERT AN EXISTING THREE STORY THREE FAMILY BUILDING INTO AN EIGHT FAMILY BUILDING
X01012362-S1
01/13/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/20/2024
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
12/20/2024
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
12/20/2024
Special inspection requirement — Maintenance information
FAHAD FATEH
12/20/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
12/20/2024
Special inspection requirement — Permanent certificate
FAHAD FATEH
12/20/2024
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
12/20/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAHAD FATEH
12/20/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
12/20/2024
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
12/20/2024
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
12/20/2024
Special inspection requirement — Metering
FAHAD FATEH
12/20/2024
Special inspection requirement — Fenestration areas
FAHAD FATEH
12/20/2024
Special inspection requirement — Interior lighting power
FAHAD FATEH
12/18/2024
Objection raised — C/O of existing property requi
12/18/2024
Objection resolved — Addressed
12/09/2024
Filed — Alteration CO
APPLICATION FILED HEREWITH TO CONVERT AN EXISTING THREE STORY THREE FAMILY BUILDING INTO AN EIGHT FAMILY BUILDING
X01012362-P2
12/09/2024
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
12/09/2024
Special inspection requirement — Fenestration areas
FAHAD FATEH
12/09/2024
Special inspection requirement — Interior lighting power
FAHAD FATEH
12/09/2024
Special inspection requirement — Metering
FAHAD FATEH
12/09/2024
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
12/09/2024
Special inspection requirement — Permanent certificate
FAHAD FATEH
12/09/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
12/09/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAHAD FATEH
12/09/2024
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
12/09/2024
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
12/09/2024
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
12/09/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
12/09/2024
Special inspection requirement — Maintenance information
FAHAD FATEH
12/05/2024
Signed off — Alteration CO
APPLICATION FILED HEREWITH TO CONVERT AN EXISTING THREE STORY THREE FAMILY BUILDING INTO AN EIGHT FAMILY BUILDING
X01012362-S3
11/25/2024
Violation issued (HPD, closed)
I
11/15/2024
Inspection — Pass-Final SP - Up to 3 Requested Floors
Pass
View inspection ↗
10/18/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
10/10/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/08/2024
Signed off — Alteration CO
APPLICATION FILED HEREWITH TO CONVERT AN EXISTING THREE STORY THREE FAMILY BUILDING INTO AN EIGHT FAMILY BUILDING
X01012362-S2
10/01/2024
Inspection — Pass-Final SP - Up to 3 Requested Floors
Pass
View inspection ↗
09/27/2024
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
09/24/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
09/19/2024
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
08/01/2024
Permit issued — Sprinklers
X01012362-S3-EW-SP
07/19/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/19/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
07/17/2024
Objection raised — C/O of existing property requi
07/17/2024
Objection resolved — Addressed
07/17/2024
Objection raised — Cost
07/17/2024
Objection resolved — Addressed
07/16/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
07/11/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/03/2024
Permit issued — Plumbing
X01012362-S1-PL
06/26/2024
Permit issued — Mechanical Systems
X01012362-S2-MS
06/06/2024
Permit issued — General Construction
X01012362-I1-GC
06/06/2024
Objection resolved — Addressed
06/03/2024
Objection resolved — Addressed
06/03/2024
Special inspection requirement — Maintenance information
FAHAD FATEH
06/03/2024
Special inspection requirement — Ventilation and air distribution system
FAHAD FATEH
06/03/2024
Special inspection requirement — Duct leakage testing, insulation and design
FAHAD FATEH
06/03/2024
Special inspection requirement — Permanent certificate
FAHAD FATEH
05/26/2024
Filed — Alteration CO
APPLICATION FILED HEREWITH TO CONVERT AN EXISTING THREE STORY THREE FAMILY BUILDING INTO AN EIGHT FAMILY BUILDING
X01012362-S3
Latest 60 of 144 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersSigned-offCITYWIDE PLBG, HTG &SPRKL08/01/2024
DOB NOWPlumbingSigned-offINFINITI ESC PLUMBING COR07/03/2024
DOB NOWMechanical SystemsSigned-offJHZ CONSULTING SERVICES *06/26/2024
DOB NOWGeneral ConstructionPermit IssuedJHZ CONSULTING SERVICES *06/06/2024
1 project · most recent 12/09/2024
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
12/09/2024Signed-offJHZ CONSULTING SERVICES *Heating and Air Conditioning Systems
Heat / Cool
Daikin 2MXS18WMVJU9 18,900 BTU · Split System ×4
RX18BXVJU 21,600 BTU · Split System ×3
4MXS36WMVJU9 36,000 BTU · Split System ×1
1 project · most recent 12/09/2024
Sprinkler System
FiledStatusContractorScope
12/09/2024Signed-offDYNAMIC PLBNG & SPRKR CORSprinkler System
1 project · most recent 12/09/2024
Water/Sanitary
FiledStatusContractorScope
12/09/2024Signed-offINFINITI ESC PLUMBING CORWater/Sanitary
1 project · most recent 06/21/2024
General Wiring
FiledStatusContractorScope
06/21/2024CompleteFRIED ELECTRIC CO.General Wiring
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
01/13/2025Pass-Final CND-Occupancy InspectionPassView ↗
11/15/2024Pass-Final SP - Up to 3 Requested FloorsPassView ↗
10/18/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/10/2024Pass-Final CND-Occupancy InspectionPassView ↗
10/01/2024Pass-Final SP - Up to 3 Requested FloorsPassView ↗
09/27/2024Fail-Final CND-Occupancy InspectionFailView ↗
09/24/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/19/2024Fail-Final CND-Occupancy InspectionFailView ↗
07/19/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/19/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
07/16/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/11/2024Pass-Final CND-Occupancy InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 44
DateRequirementInspectorRole
12/20/2024Insulation placement and R valuesFAHAD FATEHenergy_progress
12/20/2024Fenestration air leakageFAHAD FATEHenergy_progress
12/20/2024Maintenance informationFAHAD FATEHenergy_progress
12/20/2024Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
12/20/2024Permanent certificateFAHAD FATEHenergy_progress
12/20/2024Air barrier - visual inspectionFAHAD FATEHenergy_progress
12/20/2024Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
12/20/2024Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
12/20/2024Fire-Resistance Rated ConstructionFAHAD FATEHprogress
12/20/2024Energy Code Compliance InspectionsFAHAD FATEHprogress
12/20/2024MeteringFAHAD FATEHenergy_progress
12/20/2024Fenestration areasFAHAD FATEHenergy_progress
12/20/2024Interior lighting powerFAHAD FATEHenergy_progress
12/09/2024Insulation placement and R valuesFAHAD FATEHenergy_progress
12/09/2024Fenestration areasFAHAD FATEHenergy_progress
12/09/2024Interior lighting powerFAHAD FATEHenergy_progress
12/09/2024MeteringFAHAD FATEHenergy_progress
12/09/2024Fenestration air leakageFAHAD FATEHenergy_progress
12/09/2024Permanent certificateFAHAD FATEHenergy_progress
12/09/2024Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
12/09/2024Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
12/09/2024Energy Code Compliance InspectionsFAHAD FATEHprogress
12/09/2024Fire-Resistance Rated ConstructionFAHAD FATEHprogress
12/09/2024Air barrier - visual inspectionFAHAD FATEHenergy_progress
12/09/2024Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
Latest 25 of 44.
▾Documents — 33 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/15/2026X01012362-I1Request digital key ↗
08/15/2026X01012362-S3Request digital key ↗
08/15/2026X01012362-P2Request digital key ↗
Showing 3 of 5 on file for this type
▸Zoning, Tax Lot & Property Records1
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026X01012362-I1Open ↗
▸Seals & Professional Certifications18
▸DOB NOWProgress Inspector Seal & Signature8
09/02/2026X01012362-I1Open ↗
09/02/2026X01012362-I1Open ↗
08/31/2026X01012362-P2Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/02/2026X01012362-I1Open ↗
08/31/2026X01012362-S3Open ↗
08/31/2026X01012362-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/21/2026X01012362-S3Open ↗
08/21/2026X01012362-P2Open ↗
08/21/2026X01012362-S2Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection2
▸DOB NOWStreet Tree Checklist2
08/15/2026X01012362-I1Open ↗
08/15/2026X01012362-P2Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/15/2026X01012362-I1Open ↗
08/15/2026X01012362-S3Open ↗
08/15/2026X01012362-P2Open ↗
Showing 3 of 5 on file for this type
▸Other Documents2
▸DOB NOWProperty Ownership Certification2
08/15/2026X01012362-I1Open ↗
08/15/2026X01012362-P2Open ↗