LL97 CoveredRent Stabilized15 Open Violations 14 unresolved · 1 paperwork only ▸FDNY Report ↗
Over six families without stores · Owner of record: BUSHWICK GARDENS 1 LLC · 113,900 sf lot · 0.62 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction15p · 2 filings · 20 docs
Floor 3Under Construction13p · 1 filing · 20 docs
Floor 2Under Construction13p · 1 filing · 20 docs
Floor 1Under Construction13p · 1 filing · 20 docs
CellarUnder Construction15p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
PENNROSE2808/28/2026
PROCIDA CONSTRUCTION CORP.503/22/2026
N.Y.C. HOUSING AUTHORITY403/22/2026
ZAMAN CONSTRUCTION203/21/2026
NEW YORK CITY HOUSING AUTHORITY203/21/2026
BUSHWICK GARDENS403/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CAMERON ENGINEERING508/12/2026
IMEG Consulting Corp.101/18/2024
CHRISTOPHER COMPTON309/19/2022
KNF SERVICES CROP108/05/2021
PAUL PERDEK, PROF. ENG. PLLC108/06/2020
DOOLING & COMPANY ARCHITECTS111/06/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ECC603/21/2026
DANICO SERVICES203/21/2026
A1 EXPEDITING SERVICE203/21/2026
AE DESIGN SOLUTION203/21/2026
JM ZONING, LLC.1003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
J-J PLUMBING CORPPlumbing1207/08/2026
PROCIDA CONSTRUCTION CORP.General Contractor704/09/2026
VAYA RESTORATION INCGeneral Contractor407/08/2026
INTERSTATE RESTORATION LLGeneral Contractor207/08/2026
DERRICK RAMDEENElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TECTONIC ENGINEERING CONS106608/12/2026
ENVIRONMENTAL CODE CONSUL5516111/16/2021
Building Lifecycle
All (108)Filed (12)Permit Issued (11)Signed Off (2)Violation (46)Inspection (7)Special Inspection (30)
08/12/2026
Filed — Alteration
DECOMMISSION AND ABANDON IN PLACE EXISTING INDIRECT DOMESTIC WATER HEATERS, RECIRCULATION PUMP, AND ASSOCIATED PIPING WITH VALVES; PROVIDE NEW DOMESTIC WATER AND GAS PIPING FROM THE CEL TO A NEW BOILER POD AT ROOF. NO CHANGES TO USE, EGRESS, OR OCCUPANCY.
B00965492-P2
07/20/2026
Special inspection requirement — Sprinkler Systems
GEORGE GHEBRYAL
07/20/2026
Special inspection requirement — Tenant Protection Plan Compliance
07/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
GEORGE GHEBRYAL
07/10/2026
Inspection — Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)
Certified
View inspection ↗
06/26/2026
Permit issued — Plumbing
B00965492-S1-PL
03/21/2026
Violation issued (HPD, closed)
C
03/03/2026
Permit issued — General Construction
B00965475-I1-GC-CX
02/24/2026
Violation issued (HPD, closed)
C
12/22/2025
Violation issued (HPD, closed)
B
12/22/2025
Violation issued (HPD, closed)
B
12/12/2025
Filed — Alteration
DECOMMISSION AND ABANDON IN PLACE EXISTING INDIRECT DOMESTIC WATER HEATERS, RECIRCULATION PUMP, AND ASSOCIATED PIPING WITH VALVES; PROVIDE NEW DOMESTIC WATER AND GAS PIPING FROM THE CEL TO A NEW BOILER POD AT ROOF. NO CHANGES TO USE, EGRESS, OR OCCUPANCY.
B00965492-P1
12/12/2025
Special inspection requirement — Sprinkler Systems
GEORGE GHEBRYAL
12/12/2025
Special inspection requirement — Post-installed Anchors
GEORGE GHEBRYAL
12/12/2025
Special inspection requirement — Tenant Protection Plan Compliance
12/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
GEORGE GHEBRYAL
12/10/2025
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
12/10/2025
Special inspection requirement — Tenant Protection Plan Compliance
12/10/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
GEORGE GHEBRYAL
12/10/2025
Special inspection requirement — Post-installed Anchors
GEORGE GHEBRYAL
12/10/2025
Special inspection requirement — Sprinkler Systems
GEORGE GHEBRYAL
11/25/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
11/25/2025
Inspection — Certified Sprinkler (PL)-SP-Fixtures (PL)-Finish
Certified
View inspection ↗
11/25/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/20/2025
Permit issued — Mechanical Systems
B00965492-I1-MS
10/02/2025
Violation issued (HPD, closed)
I
09/24/2025
Violation issued (HPD, closed)
B
09/24/2025
Violation issued (HPD, closed)
B
09/24/2025
Violation issued (HPD, closed)
B
09/17/2025
Violation issued (HPD, closed)
C
09/17/2025
Violation issued (HPD, closed)
B
06/13/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
06/13/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/25/2025
Permit issued — Boiler Equipment
B00965492-S2-BE
03/17/2025
Permit issued — General Construction
B00965475-I1-GC-CX
03/03/2025
Permit issued — Plumbing
B00965492-S1-PL
02/26/2025
Filed — Alteration
DECOMMISSION AND ABANDON IN PLACE EXISTING INDIRECT DOMESTIC WATER HEATERS, RECIRCULATION PUMP, AND ASSOCIATED PIPING WITH VALVES; PROVIDE NEW DOMESTIC WATER AND GAS PIPING FROM THE CEL TO A NEW BOILER POD AT ROOF. NO CHANGES TO USE, EGRESS, OR OCCUPANCY.
B00965492-S2
02/07/2025
Special inspection requirement — Maintenance information
GEORGE GHEBRYAL
02/07/2025
Special inspection requirement — HVAC-R and service water heating equipment
GEORGE GHEBRYAL
02/07/2025
Special inspection requirement — Heating Systems
GEORGE GHEBRYAL
02/07/2025
Special inspection requirement — Tenant Protection Plan Compliance
GEORGE GHEBRYAL
02/07/2025
Special inspection requirement — HVAC-R and service water heating system controls
GEORGE GHEBRYAL
02/07/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
GEORGE GHEBRYAL
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/18/2024
Filed — Alteration
RENOVATION OF 3-STORY NYCHA MULTIPLE DWELLING AS PART OF THE NYCHA PACT RENOVATION: PROVIDE ROOF DUNNAGE FOR MEP EQUIPMENTS; NO CHANGES TO USE, EGRESS OR OCCUPANCY.
B00965475-I1
01/15/2024
Filed — Alteration
DECOMMISSION AND ABANDON IN PLACE EXISTING INDIRECT DOMESTIC WATER HEATERS, RECIRCULATION PUMP, AND ASSOCIATED PIPING WITH VALVES; PROVIDE NEW DOMESTIC WATER AND GAS PIPING FROM THE CEL TO A NEW BOILER POD AT ROOF. NO CHANGES TO USE, EGRESS, OR OCCUPANCY.
B00965492-S1
01/11/2024
Filed — Alteration
DECOMMISSION AND ABANDON IN PLACE EXISTING INDIRECT DOMESTIC WATER HEATERS, RECIRCULATION PUMP, AND ASSOCIATED PIPING WITH VALVES; PROVIDE NEW DOMESTIC WATER AND GAS PIPING FROM THE CEL TO A NEW BOILER POD AT ROOF. NO CHANGES TO USE, EGRESS, OR OCCUPANCY.
B00965492-I1
12/18/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
GEORGE GHEBRYAL
12/18/2023
Special inspection requirement — Maintenance information
GEORGE GHEBRYAL
12/18/2023
Special inspection requirement — Post-installed Anchors
GEORGE GHEBRYAL
12/18/2023
Special inspection requirement — Metering
GEORGE GHEBRYAL
12/18/2023
Special inspection requirement — Tenant Protection Plan Compliance
GEORGE GHEBRYAL
11/20/2023
Special inspection requirement — Final
GEORGE GHEBRYAL
11/20/2023
Special inspection requirement — Tenant Protection Plan Compliance
GEORGE GHEBRYAL
11/20/2023
Special inspection requirement — Mechanical Systems
GEORGE GHEBRYAL
11/20/2023
Special inspection requirement — Heating Systems
GEORGE GHEBRYAL
11/20/2023
Special inspection requirement — Final
GEORGE GHEBRYAL
11/20/2023
Special inspection requirement — Energy Code Compliance Inspections
GEORGE GHEBRYAL
11/20/2023
Special inspection requirement — HVAC-R and service water heating system controls
GEORGE GHEBRYAL
Latest 60 of 108 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedJ-J PLUMBING CORP06/26/2026
DOB NOWGeneral ConstructionPermit IssuedPROCIDA CONSTRUCTION CORP.03/03/2026
DOB NOWMechanical SystemsPermit IssuedPROCIDA CONSTRUCTION CORP.10/20/2025
DOB NOWBoiler EquipmentSigned-offJ-J PLUMBING CORP03/25/2025
DOB NOWGeneral ConstructionPermit IssuedPROCIDA CONSTRUCTION CORP.03/17/2025
DOB NOWPlumbingPermit IssuedJ-J PLUMBING CORP03/03/2025
DOB NOWGeneral ConstructionSigned-offINTERSTATE RESTORATION LL02/14/2022
DOB NOWGeneral ConstructionSigned-offINTERSTATE RESTORATION LL01/22/2022
DOB NOWSidewalk ShedPermit IssuedVAYA RESTORATION INC07/15/2021
DOB NOWSidewalk ShedPermit IssuedVAYA RESTORATION INC08/09/2020
DOB NOWConstruction FencePermit IssuedPROCIDA CONSTRUCTION CORP.11/07/2019
BISMHISSUEDPROCIDA CONSTRUCTION CORP.06/03/2022
BISOTISSUEDPROCIDA CONSTRUCTION CORP.05/26/2022
BISBLISSUEDPLUMB-IT MECHANICAL INC11/23/2021
BISBLISSUEDPLUMB-IT MECHANICAL INC12/09/2020
BISPLISSUEDPLUMB-IT MECHANICAL INC12/09/2020
BISOTISSUEDPROCIDA CONSTRUCTION CORP.11/27/2020
BISMHISSUEDPROCIDA CONSTRUCTION CORP.11/27/2020
1 project · most recent 08/12/2026
Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
08/12/2026Permit IssuedPROCIDA CONSTRUCTION CORPHeating Systems
Heating
Raypak H7-1000B 1,000,000 BTU · Boiler ×3
1 project · most recent 08/12/2026
FiledStatusContractorScope
08/12/2026——10 heads
1 project · most recent 08/12/2026
Gas Plumbing-Sprinkler Storm Water/Sanitary
FiledStatusContractorScope
08/12/2026Permit IssuedJ-J PLUMBING CORPGas, Plumbing-Sprinkler, Storm, Water/Sanitary
2 projects · most recent 04/08/2025
General Wiring
FiledStatusContractorScope
04/08/2025Permit IssuedSNB ELECTRICAL CONTNG CORGeneral Wiring
08/03/2020Permit IssuedGREEN POWER ELECTRIC CORP—
1 project · most recent 01/18/2024
Steel
FiledStatusContractorScope
01/18/2024Permit IssuedPROCIDA CONSTRUCTION CORPSteel
1 project · most recent 01/18/2024
Tenant Protection Plan 72 Hour
FiledStatusContractorScope
01/18/2024Permit IssuedPROCIDA CONSTRUCTION CORPTenant Protection Plan 72 Hour
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
07/10/2026Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
12/10/2025Pass-Final Boiler Equipment InspectionPassView ↗
11/25/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
11/25/2025Certified Sprinkler (PL)-SP-Fixtures (PL)-FinishCertifiedView ↗
11/25/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/13/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/13/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 40
DateRequirementInspectorRole
07/20/2026Sprinkler SystemsGEORGE GHEBRYALspecial
07/20/2026Tenant Protection Plan Compliance—special
07/20/2026Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
12/12/2025Sprinkler SystemsGEORGE GHEBRYALspecial
12/12/2025Post-installed AnchorsGEORGE GHEBRYALspecial
12/12/2025Tenant Protection Plan Compliance—special
12/12/2025Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
12/10/2025Tenant Protection Plan Compliance—special
12/10/2025Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
12/10/2025Post-installed AnchorsGEORGE GHEBRYALspecial
12/10/2025Sprinkler SystemsGEORGE GHEBRYALspecial
02/07/2025Maintenance informationGEORGE GHEBRYALenergy_progress
02/07/2025HVAC-R and service water heating equipmentGEORGE GHEBRYALenergy_progress
02/07/2025Heating SystemsGEORGE GHEBRYALspecial
02/07/2025Tenant Protection Plan ComplianceGEORGE GHEBRYALspecial
02/07/2025HVAC-R and service water heating system controlsGEORGE GHEBRYALenergy_progress
02/07/2025HVAC-R and service water piping design and insulationGEORGE GHEBRYALenergy_progress
12/18/2023Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
12/18/2023Maintenance informationGEORGE GHEBRYALenergy_progress
12/18/2023Post-installed AnchorsGEORGE GHEBRYALspecial
12/18/2023MeteringGEORGE GHEBRYALenergy_progress
12/18/2023Tenant Protection Plan ComplianceGEORGE GHEBRYALspecial
11/20/2023FinalGEORGE GHEBRYALprogress
11/20/2023Tenant Protection Plan ComplianceGEORGE GHEBRYALspecial
11/20/2023Mechanical SystemsGEORGE GHEBRYALspecial
Latest 25 of 40.
▾Documents — 151 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch10
09/01/2026B00552503-I1Request digital key ↗
08/31/2026B00599920-I1Request digital key ↗
08/31/2026B00643280-P1Request digital key ↗
Showing 3 of 10 on file for this type
▸DOB NOWPlans/Sketch - Construction Fence1
09/02/2026B00248935-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/02/2026B00378382-I1Request digital key ↗
▸Applications & Permits25
▸BISWORK PERMIT APPLICATION15
06/14/2022322060112Open ↗
06/08/2022322060112Open ↗
06/07/2022322060112Open ↗
Showing 3 of 15 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION9
03/02/2022322060112Open ↗
02/28/2022322060112Open ↗
02/22/2022322060112Open ↗
Showing 3 of 9 on file for this type
▸BISTEMPORARY FENCE APPLICATION & PERMIT1
11/20/2020322060112Open ↗
▸Seals & Professional Certifications32
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/31/2026B00599920-I1Open ↗
08/31/2026B00643280-P1Open ↗
08/31/2026B00643280-I1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
08/24/2026B00599920-I1Open ↗
08/24/2026B00599920-I1Open ↗
08/23/2026B00643280-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/01/2026B00965492-P2Open ↗
08/24/2026B00599920-I1Open ↗
08/22/2026B00965475-I1Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
09/27/2019322060112Open ↗
06/28/2019322060112Open ↗
06/28/2019322060112Open ↗
Showing 3 of 5 on file for this type
▸Trade Schedules & Equipment10
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT2
02/22/2022322060112Open ↗
02/01/2022322060112Open ↗
▸BISSCHEDULE B - PLUMBING2
02/28/2022322060112Open ↗
02/22/2022322060112Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
12/26/2018322060112Open ↗
12/26/2018322060112Open ↗
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT1
07/20/2022322060112Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
07/20/2022322060112Open ↗
▸BISSPRINKLER SYSTEMS1
07/20/2022322060112Open ↗
▸BISHEATING SYSTEMS1
07/20/2022322060112Open ↗
▸Safety & Tenant Protection2
▸DOB NOWTenant Protection Plan2
08/13/2026B00378382-I1Open ↗
08/13/2026B00248935-I1Open ↗
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/31/2026B00599920-I1Open ↗
08/31/2026B00643280-I1Open ↗
08/31/2026B00643280-P1Open ↗
Showing 3 of 9 on file for this type
▸BISDEP ASBESTOS PROJECT CONDITIONAL COMPLETION FORM1
11/20/2020322060112Open ↗
▸Energy Compliance19
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS6
09/27/2019322060112Open ↗
09/27/2019322060112Open ↗
06/28/2019322060112Open ↗
Showing 3 of 6 on file for this type
▸BISINTERIOR LIGHTING POWER1
07/20/2022322060112Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
07/20/2022322060112Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
07/20/2022322060112Open ↗
▸BISLIGHTING IN DWELLING UNITS1
07/20/2022322060112Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
07/20/2022322060112Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
07/20/2022322060112Open ↗
▸BISLIGHTING CONTROLS1
07/20/2022322060112Open ↗
▸BIS* HVAC INSULATION AND SEALING1
07/20/2022322060112Open ↗
▸BISELECTRIC MOTORS1
07/20/2022322060112Open ↗
▸BISELECTRICAL ENERGY CONSUMPTION1
07/20/2022322060112Open ↗
▸BISEXTERIOR LIGHTING POWER1
07/20/2022322060112Open ↗
▸BISFENESTRATION AIR LEAKAGE1
07/20/2022322060112Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
07/20/2022322060112Open ↗
▸Inspections & Test Reports10
▸BISTECHNICAL REPORT: RESPONSIBILITY2
08/22/2022322060112Open ↗
08/22/2022322060112Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
07/20/2022322060112Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
07/20/2022322060112Open ↗
▸BISMASONRY1
07/20/2022322060112Open ↗
▸BISSTRUCTURAL STEEL - HIGH STRENGTH BOLTING1
07/20/2022322060112Open ↗
▸BISMECHANICAL SYSTEMS1
07/20/2022322060112Open ↗
▸BISHIGH TEMPERATURE HOT WATER PIPING (WELDING)1
07/20/2022322060112Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
07/20/2022322060112Open ↗
▸BISSTRUCTURAL STEEL - DETAILS1
07/20/2022322060112Open ↗
▸Approvals, Objections & Sign-offs16
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter12
08/31/2026B00599920-I1Open ↗
08/31/2026B00643280-P1Open ↗
08/31/2026B00643280-I1Open ↗
Showing 3 of 12 on file for this type
▸BISFINAL1
07/20/2022322060112Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
08/23/2022322060112Open ↗
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)1
08/13/2026B00248935-I1Open ↗
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)1
08/13/2026B00248935-I1Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT2
12/26/2018322060112Open ↗
12/26/2018322060112Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
08/18/2022322060112Open ↗
▸Filing & Intake Forms9
▸BISBOROUGH INTAKE FORM4
02/05/2022322060112Open ↗
11/23/2021322060112Open ↗
11/17/2021322060112Open ↗
Showing 3 of 4 on file for this type
▸BISADDITIONAL INFORMATION3
08/11/2022322060112Open ↗
06/28/2019322060112Open ↗
06/28/2019322060112Open ↗
▸BISEFILING COVER SHEET2
12/26/2018322060112Open ↗
12/26/2018322060112Open ↗
▸Other Documents3
▸BISSHUTOFF DAMPERS1
07/20/2022322060112Open ↗
▸BISSTRUCTURAL COLD-FORMED STEEL1
07/20/2022322060112Open ↗
▸BISMAINTENANCE INFORMATION1
07/20/2022322060112Open ↗