| Owner | Filings | Most Recent |
|---|---|---|
| 354 FLATBUSH LLC | 2 | 03/22/2026 |
| M T BANK | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| STRUCTURAL ENGINEERING TECHNOLOGIES | 3 | 07/21/2026 |
| A&D ENGINEERING, PLLC | 4 | 06/24/2026 |
| KAO HWA LEE ARCHITECTS PC | 1 | 05/20/2026 |
| ENTHINK ENGINEERS LLC | 2 | 07/28/2025 |
| URBAN INTEGRATIONS | 1 | 05/10/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| UNITED SAFETY CONSULTANTS | 1 | 03/21/2026 |
| AVALON DESIGNS | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SPRING SCAFFOLDING LLC | General Contractor | 3 | 03/21/2026 |
| CROWBAR INDUSTRIES | General Contractor | 1 | 08/26/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ENTHINK ENGINEERS LLC | 6247 | 1 | 07/28/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | CROWBAR INDUSTRIES INC | 08/05/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 05/11/2021 |
| BIS | — | ISSUED | NORTH SHORE NEON SIGN CO INC | 05/12/2004 |
| BIS | — | ISSUED | UNIVERSAL ELECTRIC SIGN CO., INC | 10/28/1992 |
| BIS | — | ISSUED | UNIVERSAL ELECTRIC SIGN CO., INC | 10/28/1992 |
| BIS | — | ISSUED | UNIVERSAL ELECTRIC SIGN CO., INC | 10/28/1992 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/21/2026 | — | — | Heating and Air Conditioning Systems, Heating Systems | Heat / Cool Mitsubishi Electric RXTA24AAVJU 34,200 BTU · Vrf Outdoor ×36 RXTA36AAVJU 34,200 BTU · Heat Pump Outdoor ×20 RXTA48AAVJU 45,500 BTU · Vrf Outdoor ×3 Daikin RXTA24AAVJU 23,000 BTU · Vrf Outdoor ×16 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/21/2026 | — | — | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/12/2021 | Complete | TOP SHELF ELECTRIC CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/21/2026 | — | — | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/28/2025 | Permit Issued | CROWBAR INDUSTRIES INC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/18/2026 | Fire-Resistance Rated Construction | — | progress |
| 06/18/2026 | Duct leakage testing, insulation and design | — | energy_progress |
| 06/18/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 06/18/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 06/18/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 06/18/2026 | Maintenance information | — | energy_progress |
| 06/18/2026 | Shutoff dampers | — | energy_progress |
| 06/18/2026 | Energy Code Compliance Inspections | — | progress |
| 06/18/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/18/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 06/18/2026 | Energy Code Compliance Inspections | — | progress |
| 06/18/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 06/18/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 06/18/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 06/18/2026 | Maintenance information | — | energy_progress |
| 06/18/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/18/2026 | Heating Systems | — | special |
| 05/21/2026 | Concrete - Cast-In-Place | — | special |
| 05/21/2026 | Post-installed Anchors | — | special |
| 05/20/2026 | Footing and Foundation | — | progress |
| 05/20/2026 | Final | — | progress |
| 05/20/2026 | Sprinkler Systems | — | special |
| 05/20/2026 | Standpipe Systems | — | special |
| 05/20/2026 | Mechanical Systems | — | special |
| 05/20/2026 | Final | — | progress |