← Back
Two family converted from one family
358 GATES AVENUE
BROOKLYN · BIN 3051067
💬 Discuss this project
1899Year Built
3Stories
B3Building Class
R6BZoning
3,040 sfGross Floor Area
2Units
Rent Stabilized2 Open Violations ▸FDNY Report ↗
Two family converted from one family · 1,900 sf lot · 1.6 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Roof3p · 1 filing · 20 docs
Floor 31p · 1 filing · 20 docs
Floor 2
Floor 1
Cellar3p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/15/2026$2.6M—— → —$845/sf building
10/20/2014$1.8M—EVEN CAPITAL LLC → Private party$605/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NTD ENGINEERING CONSULTANT LLC107/22/2025
ALL CITY ENGINEERING PC305/16/2025
CHI F. LAU ARCHITECT, P.C.103/04/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BMB BUILDING CONSULTING1003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
W & M ELECTRIC CORPElectrical103/21/2026
Building Lifecycle
All (118)Filed (5)Violation (9)Objection (76)Special Inspection (28)
08/11/2025
Objection resolved — Addressed
08/04/2025
Objection resolved — Addressed
07/22/2025
Filed — Alteration CO
SUBSEQUENT FILING FOR STRUCTURAL WORK TYPE.
B01007968-S4
07/22/2025
Objection raised — Other
07/22/2025
Objection raised — Other
07/22/2025
Special inspection requirement — Structural Steel - Details
07/14/2025
Special inspection requirement — Structural Cold-Formed Steel
07/14/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
07/14/2025
Special inspection requirement — Structural Wood Frame
07/14/2025
Special inspection requirement — Final
06/23/2025
Objection resolved — Addressed
06/23/2025
Objection resolved — Addressed
06/18/2025
Objection resolved — Addressed
06/17/2025
Objection raised — Structural
06/17/2025
Objection raised — Energy
06/12/2025
Objection raised — Energy
05/30/2025
Objection resolved — Addressed
05/27/2025
Objection resolved — Addressed
05/27/2025
Objection resolved — Addressed
05/27/2025
Objection resolved — Addressed
05/27/2025
Objection resolved — Addressed
05/27/2025
Objection resolved — Addressed
05/27/2025
Objection resolved — Addressed
05/19/2025
Objection raised — Cost
05/19/2025
Objection raised — Structural
05/19/2025
Objection raised — Cost
05/19/2025
Objection raised — Mechanical
05/19/2025
Objection raised — Structural
05/19/2025
Objection raised — Cost
05/19/2025
Objection raised — Structural
05/16/2025
Filed — Alteration CO
SUBSEQUENT FILING FOR STRUCTURAL WORK TYPE.
B01007968-S3
05/16/2025
Filed — Alteration CO
SUBSEQUENT FILING FOR STRUCTURAL WORK TYPE.
B01007968-S2
05/16/2025
Filed — Alteration CO
SUBSEQUENT FILING FOR STRUCTURAL WORK TYPE.
B01007968-S1
05/12/2025
Special inspection requirement — Maintenance information
05/12/2025
Special inspection requirement — Energy Code Compliance Inspections
05/12/2025
Special inspection requirement — Permanent certificate
05/12/2025
Special inspection requirement — Ventilation and air distribution system
05/08/2025
Special inspection requirement — HVAC-R and service water heating equipment
05/08/2025
Special inspection requirement — Mechanical Systems
05/08/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
05/08/2025
Special inspection requirement — Final
05/08/2025
Special inspection requirement — HVAC-R and service water heating system controls
05/01/2025
Objection resolved — Addressed
04/15/2025
Objection raised — Energy
04/14/2025
Objection raised — Other
04/14/2025
Objection resolved — Addressed
04/14/2025
Objection raised — Other
04/14/2025
Objection resolved — Addressed
04/14/2025
Objection resolved — Addressed
04/11/2025
Objection raised — Other
03/28/2025
Objection resolved — Addressed
03/25/2025
Objection resolved — Addressed
03/25/2025
Objection resolved — Addressed
03/24/2025
Objection resolved — Addressed
10/01/2024
Objection resolved — Addressed
09/25/2024
Objection raised — Other
09/14/2024
Objection resolved — Addressed
09/14/2024
Objection resolved — Addressed
09/14/2024
Objection resolved — Addressed
09/14/2024
Objection resolved — Addressed
Latest 60 of 118 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISOTISSUEDBROOKLYN SOLARWORKS LLC05/23/2018
1 project · most recent 07/22/2025
Air Conditioning Systems Heating and Air Conditioning Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
07/22/2025——Air Conditioning Systems, Heating and Air Conditioning Systems, Heating Systems
Cooling
Guardian FC43B3XC1A 76,800 BTU · Fan Coil Indoor ×3
FC35B3XC1A 58,700 BTU · Fan Coil Indoor ×1
Heat / Cool
Mitsubishi Electric MXZ-3C24NA 25,000 BTU · Heat Pump Outdoor ×1
Heating
Luxaire TG9S080B12MP11B 76,000 BTU · Furnace ×2
TG8S080B12MP11B 64,000 BTU · Furnace ×1
1 project · most recent 07/22/2025
Sprinkler System
FiledStatusContractorScope
07/22/2025——Sprinkler System
1 project · most recent 07/22/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
07/22/2025——Gas, Storm, Water/Sanitary
1 project · most recent 08/02/2018
FiledStatusContractorScope
08/02/2018CompleteBROOKYLN SOLARWORKS, LLC—
1 project · most recent 07/22/2025
Steel Wood
FiledStatusContractorScope
07/22/2025——Steel, Wood
▾Special Inspection Requirements (DOB NOW) — 28
DateRequirementInspectorRole
07/22/2025Structural Steel - Details—special
07/14/2025Structural Cold-Formed Steel—special
07/14/2025Structural Stability – Alterations of existing buildings—special
07/14/2025Structural Wood Frame—progress
07/14/2025Final—progress
05/12/2025Maintenance information—energy_progress
05/12/2025Energy Code Compliance Inspections—progress
05/12/2025Permanent certificate—energy_progress
05/12/2025Ventilation and air distribution system—energy_progress
05/08/2025HVAC-R and service water heating equipment—energy_progress
05/08/2025Mechanical Systems—special
05/08/2025HVAC-R and service water piping design and insulation—energy_progress
05/08/2025Final—progress
05/08/2025HVAC-R and service water heating system controls—energy_progress
05/21/2024Fire-Resistance Rated Construction—progress
05/21/2024Fire-Resistant Penetrations and Joints—special
04/26/2024Fenestration and door U-factor and product ratings—energy_progress
04/23/2024Fenestration areas—energy_progress
04/23/2024Air barrier - visual inspection—energy_progress
04/23/2024Insulation placement and R values—energy_progress
04/23/2024Fenestration air leakage—energy_progress
04/23/2024Lighting in dwelling units—energy_progress
04/23/2024Energy Code Compliance Inspections—progress
04/23/2024Interior lighting power—energy_progress
03/19/2024Post-installed Anchors—special
Latest 25 of 28.
▾Documents — 44 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/15/2026B01007968-S3Request digital key ↗
08/15/2026B01007968-I1Request digital key ↗
08/15/2026B01007968-S1Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION3
05/14/2018340599748Open ↗
05/07/2018340599748Open ↗
04/25/2018340599748Open ↗
▸BISWORK PERMIT APPLICATION1
05/23/2018340599748Open ↗
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B01007968-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B01007968-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026B01007968-I1Open ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/21/2026B01007968-S4Open ↗
08/21/2026B01007968-S3Open ↗
08/21/2026B01007968-S1Open ↗
Showing 3 of 5 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
04/25/2018340599748Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026B01007968-I1Open ↗
▸Safety & Tenant Protection2
▸BISTenant Protection Plan and Notes1
04/25/2018340599748Open ↗
▸DOB NOWStreet Tree Checklist1
08/15/2026B01007968-I1Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/15/2026B01007968-S3Open ↗
08/15/2026B01007968-I1Open ↗
08/15/2026B01007968-S1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
04/25/2018340599748Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
10/11/2018340599748Open ↗
04/25/2018340599748Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
10/11/2018340599748Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
10/11/2018340599748Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
04/25/2018340599748Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
10/11/2018340599748Open ↗
04/25/2018340599748Open ↗
▸Approvals, Objections & Sign-offs2
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
10/11/2018340599748Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
10/11/2018340599748Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
10/11/2018340599748Open ↗
04/25/2018340599748Open ↗
▸Filing & Intake Forms2
▸BISADDITIONAL INFORMATION1
05/18/2018340599748Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
04/25/2018340599748Open ↗
▸Other Documents4
▸DOB NOWPlot Diagram1
08/13/2026B01007968-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/15/2026B01007968-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026B01007968-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1