| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/13/2023 | $950K | — | — → — | $255/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| XC ENGINEERING PC | 3 | 06/09/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| G DESIGN DRAFTING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DVE CONSTRUCTION INC | General Contractor | 3 | 03/21/2026 |
| SS CONSTRUCTION EXPERTS L | General Contractor | 1 | 08/13/2026 |
| RRP PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| XC ENGINEERING PC | 9405 | 1 | 06/09/2026 |
| XC ENGINEERING PC | 6692 | 2 | 01/09/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | SS CONSTRUCTION EXPERTS L | 08/12/2026 |
| DOB NOW | Plumbing | Signed-off | RRP PLUMBING CORP | 01/12/2024 |
| DOB NOW | General Construction | Signed-off | DVE CONSTRUCTION INC | 01/12/2024 |
| BIS | — | ISSUED | SIGNS CAD CORP | 11/20/2003 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/15/2024 | Complete | R & T ELECTRICAL CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/25/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 08/07/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 07/29/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/02/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/30/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/08/2024 | Duct leakage testing, insulation and design | XIU CHEN | energy_progress |
| 01/08/2024 | Tenant Protection Plan Compliance | XIU CHEN | special |
| 01/08/2024 | Insulation placement and R values | XIU CHEN | energy_progress |
| 01/08/2024 | Fire-Resistant Penetrations and Joints | XIU CHEN | special |
| 01/08/2024 | Fire-Resistant Penetrations and Joints | XIU CHEN | special |
| 01/08/2024 | Tenant Protection Plan Compliance | XIU CHEN | special |
| 01/08/2024 | Energy Code Compliance Inspections | XIU CHEN | progress |
| 01/08/2024 | Interior lighting power | XIU CHEN | energy_progress |
| 01/08/2024 | Maintenance information | XIU CHEN | energy_progress |
| 01/08/2024 | Lighting controls | XIU CHEN | energy_progress |
| 01/08/2024 | Shutoff dampers | XIU CHEN | energy_progress |
| 01/05/2024 | Mechanical Systems | XIU CHEN | special |
| 01/05/2024 | Final | XIU CHEN | progress |