← Back
Two family frame
36 CLINTON PLACE
STATEN ISLAND · Port Richmond · BIN 5024759
💬 Discuss this project
1910Year Built
2.5Stories
B2Building Class
R3AZoning
2,252 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family frame · 2,800 sf lot · 0.8 FAR built · Flood zone X
Locations of Work
Electrical
Roof4p · 1 filing · 12 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC204/04/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN SOLAR ELECTL CORPElectrical203/22/2026
SUNRUN INSTALLATION SVCGeneral Contractor203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272204/04/2025
Building Lifecycle
All (12)Filed (2)Permit Issued (1)Signed Off (1)Violation (3)Special Inspection (5)
08/01/2025
Signed off — Alteration
S01193276-I1
04/07/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
04/07/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
04/07/2025
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
04/07/2025
Special inspection requirement — Final
Walid Abdulla
04/07/2025
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
04/04/2025
Filed — Alteration
S01193276-P1
03/25/2025
Permit issued — Solar
S01193276-I1-SL
03/18/2025
Filed — Alteration
S01193276-I1
02/24/2010
Violation issued (ECB, closed)
Construction
01/13/2010
Violation issued (ECB, closed)
Unknown
01/13/2010
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC03/25/2025
1 project · most recent 04/28/2025
General Wiring
FiledStatusContractorScope
04/28/2025CompleteSUNRUN SOLAR ELECTL CORPGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
04/07/2025Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
04/07/2025Fire-Resistant Penetrations and JointsWalid Abdullaspecial
04/07/2025Energy Code Compliance InspectionsWalid Abdullaprogress
04/07/2025FinalWalid Abdullaprogress
04/07/2025Air barrier - visual inspectionWalid Abdullaenergy_progress
▾Documents — 12 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/20/2026S01193276-I1Request digital key ↗
08/20/2026S01193276-P1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWProgress Inspector Seal & Signature3
08/24/2026S01193276-I1Open ↗
08/24/2026S01193276-I1Open ↗
08/24/2026S01193276-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/20/2026S01193276-I1Open ↗
08/20/2026S01193276-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/24/2026S01193276-I1Open ↗
08/24/2026S01193276-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/20/2026S01193276-P1Open ↗
08/20/2026S01193276-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01193276-I1Open ↗