| Firm | Filings | Most Recent |
|---|---|---|
| James V Morri | 2 | 03/07/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| James V Morri, RA | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Paul Lopa Designs | General Contractor | 9 | 03/21/2026 |
| Rite-Flo P.H. & Cooling | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| James V Morri, RA | 1042 | 1 | 06/19/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | DJ Plumbing & Heating | 11/14/2025 |
| DOB NOW | Plumbing | Permit Issued | DJ Plumbing & Heating | 03/12/2025 |
| DOB NOW | General Construction | Permit Issued | Paul Lopa Designs | 02/26/2025 |
| DOB NOW | General Construction | Permit Issued | Paul Lopa Designs | 01/27/2025 |
| DOB NOW | Structural | Permit Issued | Paul Lopa Designs | 12/19/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/07/2025 | Permit Issued | DJ Plumbing & Heating | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/14/2025 | Complete | Live Wire Electric 1 | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/07/2025 | Permit Issued | DJ Plumbing & Heating | Steel, Concrete, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/25/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/04/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/04/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/20/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/15/2024 | Concrete - Cast-In-Place | James Morri | special |
| 05/15/2024 | Fire-Resistant Penetrations and Joints | James Morri | special |
| 05/15/2024 | Structural Stability – Alterations of existing buildings | James Morri | special |
| 05/15/2024 | Subgrade Inspections | James Morri | special |
| 05/15/2024 | Structural Steel - Details | James Morri | special |
| 05/15/2024 | Energy Code Compliance Inspections | James Morri | progress |
| 05/15/2024 | Fire-Resistance Rated Construction | James Morri | progress |
| 05/15/2024 | Preliminary | James Morri | progress |
| 05/15/2024 | Structural Wood Frame | James Morri | progress |
| 05/15/2024 | Final | James Morri | progress |
| 05/15/2024 | Footing and Foundation | James Morri | progress |
| 05/15/2024 | Air barrier — testing | anthony santoro | energy_progress |
| 05/15/2024 | HVAC-R and service water heating system controls | James Morri | energy_progress |
| 05/15/2024 | HVAC-R and service water piping design and insulation | James Morri | energy_progress |
| 05/15/2024 | Air barrier - visual inspection | James Morri | energy_progress |
| 05/15/2024 | Insulation placement and R values | James Morri | energy_progress |
| 05/15/2024 | Fenestration and door U-factor and product ratings | James Morri | energy_progress |
| 05/15/2024 | Fenestration air leakage | James Morri | energy_progress |
| 05/15/2024 | Fenestration areas | James Morri | energy_progress |
| 05/15/2024 | Lighting in dwelling units | James Morri | energy_progress |
| 05/15/2024 | Maintenance information | James Morri | energy_progress |
| 05/15/2024 | Permanent certificate | James Morri | energy_progress |
| 05/15/2024 | HVAC-R and service water heating equipment | James Morri | energy_progress |