12 Open Violations ▸FDNY Report ↗
Over six families without stores · Owner of record: 360 EAST 184 STREET LLC · 2,504 sf lot · 2.8 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingGeneral
Roof33p · 2 filings · 20 docs
Bulkhead2p · 1 filing · 10 docs
Penthouse28p · 1 filing · 20 docs
Floor 429p · 1 filing · 20 docs
Floor 328p · 1 filing · 20 docs
Floor 228p · 1 filing · 20 docs
Floor 132p · 2 filings · 20 docs
Cellar28p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
360 EAST 184 STREET LLC503/22/2026
LOD CONSTRUCTION303/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NODE ARCHITECTURE,ENGINEERING, CONS1811/06/2023
PAUL PERDEK, PROF. ENG. PLLC205/23/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NODE ARCHITECTURE ENGINEERING CON1403/21/2026
AE DESIGN SOLUTION403/21/2026
NODE ARCH ENGIN CONSULT603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
LOD CONSTRUCTION LLCGeneral Contractor2607/08/2026
CENTRAL SCAFFOLD & HOISTGeneral Contractor407/08/2026
DENNISON ELECTRIC CORPElectrical103/22/2026
LLOYD G DRUMMOND PLBG&GENFire Protection107/08/2026
LLOYD G DRUMMOND PLBG&GENPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NODE ARCHITECTURE,ENGINEE67991411/06/2023
INTERNATIONAL GEOTEHCNICA1795906/27/2023
Building Lifecycle
All (103)Filed (19)Permit Issued (18)Signed Off (10)Violation (18)Inspection (6)Objection (2)Special Inspection (30)
05/11/2026
Violation issued (HPD, open)
A
11/25/2025
Violation issued (HPD, open)
A
11/25/2025
Violation issued (HPD, open)
A
11/25/2025
Violation issued (HPD, open)
A
11/25/2025
Violation issued (HPD, open)
A
11/25/2025
Violation issued (HPD, open)
A
11/25/2025
Violation issued (HPD, open)
A
11/25/2025
Violation issued (HPD, open)
A
11/25/2025
Violation issued (HPD, open)
A
11/25/2025
Violation issued (HPD, open)
C
11/17/2025
Violation issued (HPD, closed)
I
09/18/2025
Violation issued (HPD, closed)
A
09/18/2025
Violation issued (HPD, closed)
A
06/16/2025
Violation issued (HPD, open)
A
11/22/2024
Violation issued (HPD, closed)
I
11/30/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
Radomir Delic
11/30/2023
Special inspection requirement — Protection of exposed foundation insulation
Radomir Delic
11/30/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Radomir Delic
11/30/2023
Special inspection requirement — Lighting controls
Radomir Delic
11/30/2023
Special inspection requirement — Exterior lighting power
Radomir Delic
11/30/2023
Special inspection requirement — Insulation placement and R values
Radomir Delic
11/30/2023
Special inspection requirement — Fire-Resistance Rated Construction
Radomir Delic
11/30/2023
Special inspection requirement — Fenestration air leakage
Radomir Delic
11/30/2023
Special inspection requirement — Metering
Radomir Delic
11/30/2023
Special inspection requirement — Fenestration areas
Radomir Delic
11/30/2023
Special inspection requirement — Lighting in dwelling units
Radomir Delic
11/30/2023
Special inspection requirement — Interior lighting power
Radomir Delic
11/30/2023
Special inspection requirement — Air barrier - visual inspection
Radomir Delic
11/30/2023
Special inspection requirement — Maintenance information
Radomir Delic
11/29/2023
Objection resolved — Addressed
11/13/2023
Objection raised — Scope
11/06/2023
Filed — New Building
Filing of Roof Protection plans in conjunction with NB Application # X00542666-I1
X00542666-A1
11/03/2023
Special inspection requirement — Insulation placement and R values
Radomir Delic
11/03/2023
Special inspection requirement — Metering
Radomir Delic
11/03/2023
Special inspection requirement — Lighting in dwelling units
Radomir Delic
11/03/2023
Special inspection requirement — Lighting controls
Radomir Delic
11/03/2023
Special inspection requirement — Fenestration air leakage
Radomir Delic
11/03/2023
Special inspection requirement — Air barrier - visual inspection
Radomir Delic
11/03/2023
Special inspection requirement — Maintenance information
Radomir Delic
11/03/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
Radomir Delic
11/03/2023
Special inspection requirement — Protection of exposed foundation insulation
Radomir Delic
11/03/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Radomir Delic
11/03/2023
Special inspection requirement — Exterior lighting power
Radomir Delic
11/03/2023
Special inspection requirement — Fenestration areas
Radomir Delic
11/03/2023
Special inspection requirement — Fire-Resistance Rated Construction
Radomir Delic
11/03/2023
Special inspection requirement — Interior lighting power
Radomir Delic
08/21/2023
Signed off — New Building
Filing of Roof Protection plans in conjunction with NB Application # X00542666-I1
X00542666-S4
08/15/2023
Signed off — New Building
Filing of Roof Protection plans in conjunction with NB Application # X00542666-I1
X00542666-S3
08/14/2023
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
08/09/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
07/28/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
06/29/2023
Signed off — New Building
Filing of Roof Protection plans in conjunction with NB Application # X00542666-I1
X00542666-S2
06/27/2023
Filed — New Building
Filing of Roof Protection plans in conjunction with NB Application # X00542666-I1
X00542666-P5
06/07/2023
Signed off — Alteration
Construction Fence filed in conjunction with NB Application #X00542666-I1
X00529142-I1
06/07/2023
Signed off — Alteration
X00742141-I1
06/07/2023
Signed off — Alteration
X00742139-I1
06/07/2023
Special inspection requirement — HVAC-R and service water heating system controls
MICHAEL KARANTINIDIS, P.E.
06/07/2023
Special inspection requirement — Maintenance information
MICHAEL KARANTINIDIS, P.E.
05/11/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/10/2023
Permit issued — General Construction
X00542666-I1-GC
Latest 60 of 103 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedLOD CONSTRUCTION LLC02/10/2023
DOB NOWMechanical SystemsSigned-offLOD CONSTRUCTION LLC02/09/2023
DOB NOWConstruction FenceSigned-offLOD CONSTRUCTION LLC02/09/2023
DOB NOWGeneral ConstructionPermit IssuedLOD CONSTRUCTION LLC01/04/2023
DOB NOWGeneral ConstructionPermit IssuedLOD CONSTRUCTION LLC01/04/2023
DOB NOWGeneral ConstructionPermit IssuedLOD CONSTRUCTION LLC01/04/2023
DOB NOWMechanical SystemsSigned-offLOD CONSTRUCTION LLC10/28/2022
DOB NOWGeneral ConstructionPermit IssuedLOD CONSTRUCTION LLC09/02/2022
DOB NOWConstruction FenceSigned-offLOD CONSTRUCTION LLC06/22/2022
DOB NOWPlumbingSigned-offLLOYD G DRUMMOND PLBG&GEN05/25/2022
DOB NOWProtection and Mechanical MethodsSigned-offCENTRAL SCAFFOLD & HOIST05/24/2022
DOB NOWSidewalk ShedSigned-offCENTRAL SCAFFOLD & HOIST05/24/2022
DOB NOWProtection and Mechanical MethodsSigned-offLOD CONSTRUCTION LLC05/17/2022
DOB NOWSprinklersSigned-offLLOYD G. DRUMMOND05/13/2022
DOB NOWStructuralSigned-offLOD CONSTRUCTION LLC04/21/2022
DOB NOWSupport of ExcavationSigned-offLOD CONSTRUCTION LLC03/07/2022
DOB NOWEarth WorkSigned-offLOD CONSTRUCTION LLC02/01/2022
DOB NOWConstruction FenceSigned-offLOD CONSTRUCTION LLC07/01/2021
BIS—ISSUEDLOD CONSTRUCTION LLC11/16/2021
1 project · most recent 11/06/2023
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
11/06/2023Permit IssuedLOD CONSTRUCTION LLCHeating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric MXZ-3C24NAHZ 28,400 BTU · Split System ×14
MXZ-2C20NAHZ 18,000 BTU · Split System ×12
MUZ-FS09NAH 9,000 BTU · Split System ×7
1 project · most recent 11/06/2023
Sprinkler System
FiledStatusContractorScope
11/06/2023Signed-offLLOYD G DRUMMOND PLBG&GENSprinkler System
1 project · most recent 11/06/2023
Storm Water/Sanitary
FiledStatusContractorScope
11/06/2023Signed-offLLOYD G DRUMMOND PLBG&GENStorm, Water/Sanitary
2 projects · most recent 10/11/2022
General Wiring
FiledStatusContractorScope
10/11/2022CompleteDENNISON ELECTRIC CORPGeneral Wiring
06/02/2022CompleteV. VASS ELECTRIC CORP—
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
08/14/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/09/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/28/2023Pass-Final CND-Occupancy InspectionPassView ↗
05/11/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/03/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
08/03/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 71
DateRequirementInspectorRole
11/30/2023Fenestration areasRadomir Delicenergy_progress
11/30/2023Exterior lighting powerRadomir Delicenergy_progress
11/30/2023Air barrier - visual inspectionRadomir Delicenergy_progress
11/30/2023Maintenance informationRadomir Delicenergy_progress
11/30/2023Insulation placement and R valuesRadomir Delicenergy_progress
11/30/2023Protection of exposed foundation insulationRadomir Delicenergy_progress
11/30/2023Fire-Resistant Penetrations and JointsRadomir Delicspecial
11/30/2023Fire-Resistance Rated ConstructionRadomir Delicprogress
11/30/2023Fenestration air leakageRadomir Delicenergy_progress
11/30/2023Interior lighting powerRadomir Delicenergy_progress
11/30/2023Lighting in dwelling unitsRadomir Delicenergy_progress
11/30/2023Lighting controlsRadomir Delicenergy_progress
11/30/2023Fenestration and door U-factor and product ratingsRadomir Delicenergy_progress
11/30/2023MeteringRadomir Delicenergy_progress
11/03/2023Air barrier - visual inspectionRadomir Delicenergy_progress
11/03/2023Fire-Resistant Penetrations and JointsRadomir Delicspecial
11/03/2023Fire-Resistance Rated ConstructionRadomir Delicprogress
11/03/2023Fenestration air leakageRadomir Delicenergy_progress
11/03/2023Fenestration and door U-factor and product ratingsRadomir Delicenergy_progress
11/03/2023Protection of exposed foundation insulationRadomir Delicenergy_progress
11/03/2023Exterior lighting powerRadomir Delicenergy_progress
11/03/2023Interior lighting powerRadomir Delicenergy_progress
11/03/2023Fenestration areasRadomir Delicenergy_progress
11/03/2023Lighting controlsRadomir Delicenergy_progress
11/03/2023Maintenance informationRadomir Delicenergy_progress
Latest 25 of 71.
▾Documents — 185 on file (BIS + DOB NOW)
▸Plans & Drawings19
▸DOB NOWPlans/Sketch19
08/25/2026X00529142-I1Request digital key ↗
08/25/2026X00529142-P1Request digital key ↗
08/24/2026X00557628-I1Request digital key ↗
Showing 3 of 19 on file for this type
▸Applications & Permits8
▸BISPLAN / WORK APPROVAL APPLICATION4
01/19/2022240308387Open ↗
01/18/2022240308387Open ↗
10/01/2021240308387Open ↗
Showing 3 of 4 on file for this type
▸BISWORK PERMIT APPLICATION2
11/18/2021220737040Open ↗
11/16/2021220737040Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation2
01/18/2022240308387Open ↗
10/01/2021240308387Open ↗
▸Zoning, Tax Lot & Property Records7
▸DOB NOWZoning Exhibit form (1-5)3
08/13/2026X00542666-P9Open ↗
08/13/2026X00542666-A1Open ↗
08/13/2026X00542666-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram3
08/13/2026X00542666-A1Open ↗
08/13/2026X00542666-I1Open ↗
08/13/2026X00542666-P9Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026X00542666-I1Open ↗
▸Seals & Professional Certifications92
▸DOB NOWProgress Inspector Seal & Signature51
09/27/2026X00542666-A1Open ↗
09/27/2026X00542666-A1Open ↗
09/27/2026X00542666-A1Open ↗
Showing 3 of 51 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature20
09/27/2026X00542666-A1Open ↗
09/01/2026X00557628-I1Open ↗
09/01/2026X00557628-I1Open ↗
Showing 3 of 20 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature19
08/25/2026X00529142-I1Open ↗
08/25/2026X00529142-P1Open ↗
08/24/2026X00557628-I1Open ↗
Showing 3 of 19 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
10/01/2021240308387Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
10/01/2021240308387Open ↗
▸Trade Schedules & Equipment5
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)3
08/13/2026X00542666-I1Open ↗
08/13/2026X00542666-P9Open ↗
08/13/2026X00542666-A1Open ↗
▸BISELECTRIC CUT-OFF2
11/18/2021220737040Open ↗
11/10/2021220737040Open ↗
▸Safety & Tenant Protection12
▸DOB NOWStreet Tree Checklist3
08/24/2026X00542666-P9Open ↗
08/24/2026X00542666-I1Open ↗
08/15/2026X00542666-A1Open ↗
▸BISSTREET TREE CHECKLIST2
01/18/2022240308387Open ↗
10/01/2021240308387Open ↗
▸BISSRO MD ANTI-HARASSMENT CHECKLIST1
11/18/2021220737040Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
11/18/2021220737040Open ↗
▸BISBPP: STREET TREES SITE PLAN1
10/01/2021240308387Open ↗
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
11/10/2021220737040Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026X00542666-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026X00542666-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026X00542666-I1Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
11/18/2021220737040Open ↗
▸BISRODENT CONTROL1
11/18/2021220737040Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026X00542666-I1Open ↗
▸Approvals, Objections & Sign-offs9
▸BISLETTERS - SUPPORTING DOCUMENTATION8
11/22/2021220737040Open ↗
11/18/2021220737040Open ↗
11/18/2021220737040Open ↗
Showing 3 of 8 on file for this type
▸BISTAP LETTER - DOM SVC : DEP-DOM1
11/18/2021220737040Open ↗
▸Cost, Insurance & Ownership4
▸BISPROJECT-SPECIFIC GL INSURANCE2
11/18/2021220737040Open ↗
11/10/2021220737040Open ↗
▸DOB NOWCertification by Insurance Broker or Agency1
08/13/2026X00542666-I1Open ↗
▸DOB NOWCertificate of Insurance1
08/13/2026X00542666-I1Open ↗
▸Filing & Intake Forms7
▸BISBOROUGH INTAKE FORM3
11/18/2021220737040Open ↗
11/10/2021220737040Open ↗
03/19/2021220737040Open ↗
▸BISADDITIONAL INFORMATION2
11/18/2021220737040Open ↗
10/01/2021240308387Open ↗
▸BISEFILING COVER SHEET1
03/19/2021220737040Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
10/01/2021240308387Open ↗
▸Other Documents19
▸BISBPP - SUPPORTING DOCUMENTATION5
01/18/2022240308387Open ↗
01/18/2022240308387Open ↗
10/01/2021240308387Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/13/2026X00542666-I1Open ↗
08/13/2026X00542666-P9Open ↗
08/13/2026X00542666-A1Open ↗
▸DOB NOWProperty Ownership Certification3
08/24/2026X00542666-P4Open ↗
08/24/2026X00542666-P2Open ↗
08/24/2026X00542666-P1Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION2
11/18/2021220737040Open ↗
11/10/2021220737040Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026X00542666-I1Open ↗
08/13/2026X00542666-A1Open ↗
▸DOB NOWAdjoining Owners Notification2
08/13/2026X00684965-I1Open ↗
08/13/2026X00557628-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026X00542666-I1Open ↗
▸DOB NOWAdditional Insured Authorizations1
08/13/2026X00542666-I1Open ↗