| Owner | Filings | Most Recent |
|---|---|---|
| BOSTON PROPERTIES | 252 | 09/30/2026 |
| ENTERPRISE ASSET MANAGEMENT | 70 | 07/08/2026 |
| 360 PAS OWNER LLC | 1 | 03/22/2026 |
| 360 PARK SOUTH DELAWARE A | 14 | 03/22/2026 |
| REIDY CONTRACTING GROUP | 4 | 03/22/2026 |
| ENTERPRISE DEVELOPMENT | 1 | 03/22/2026 |
| 360 PARK SOUTH ASSOCIATES, LLC | 156 | 03/22/2026 |
| 360 PARK SO DELAWARE ASSOC | 108 | 03/21/2026 |
| 360 PARK AVE SO DELAWARE ASSOC | 102 | 03/21/2026 |
| 360 PARK AVE. SOUTH ASSO'S, LLC | 5 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/14/2021 | $300.0M | — | 360 PARK SOUTH DELAWARE ASSOCIATES, LLC → 360 PAS OWNER LLC | $666/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| 5TH FLOOR DESIGN | 1 | 08/24/2026 |
| ALWAYS FAST SERVICES CORP | 1 | 08/19/2026 |
| WB ENGINEERS & CONSULTANTS PLLC | 33 | 08/18/2026 |
| AMA CONSULTING ENGINEERS, PC | 7 | 08/17/2026 |
| VOCON | 1 | 08/13/2026 |
| SSM DESIGN LLP D/B/A SPECTOR GROUP | 11 | 06/01/2026 |
| ARCHITECTURE PLUS INFORMATION | 15 | 04/29/2025 |
| LEON SKVIRSKY PE | 2 | 03/07/2025 |
| GENSLER | 3 | 12/18/2024 |
| MN ARCHITECTURE DPC | 3 | 08/29/2024 |
| WSP | 53 | 07/12/2024 |
| GILSANZ MURRAY STEFICEK LLP | 9 | 06/26/2024 |
| AMM ENGINEERING PC | 4 | 06/17/2024 |
| PATUXENT ENGINEERING LLC | 1 | 05/22/2024 |
| KZ ENGINEERING, P.C | 4 | 11/10/2023 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 08/18/2021 |
| DIAZ ARCHITECTS INC.,PA | 2 | 03/09/2021 |
| ASHRAF CORP | 1 | 03/11/2020 |
| GREEN DESIGN | 2 | 02/05/2020 |
| BEST PROFESSIONALS NY CORP | 2 | 02/05/2020 |
| NARINDER CHHABRA | 1 | 01/14/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| GILLMAN CONSULTING | 220 | 03/21/2026 |
| BUILDING BROTHERS | 4 | 03/21/2026 |
| PATUXENT ENGINEERING | 2 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 4 | 03/21/2026 |
| RIZZO GROUP | 6 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| REIDY CONTRACTING GROUP | General Contractor | 48 | 07/08/2026 |
| ARSENAL SCAFFOLD INC | General Contractor | 12 | 07/08/2026 |
| SEAN COAKLEY P & H INC | Fire Protection | 11 | 07/08/2026 |
| CONNELLY & SONS PLUMBING | Plumbing | 10 | 07/08/2026 |
| STRUCTURE TONE, LLC | General Contractor | 9 | 07/08/2026 |
| CLUNE CONSTRUCTION CO LP | General Contractor | 7 | 08/27/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 6 | 07/08/2026 |
| SCHNELLBACHER-SENDON GRO* | General Contractor | 5 | 07/08/2026 |
| CONCEPT CONSTRUCTION SERV | General Contractor | 4 | 07/08/2026 |
| BEDROCK MECHANICAL INC | Fire Protection | 4 | 09/16/2026 |
| ARCHSTONE BUILDERS LLC | General Contractor | 4 | 07/08/2026 |
| ANDAMIO SCAFFOLDING LLC | General Contractor | 4 | 08/20/2026 |
| P & D MECHANICAL CORP | Fire Protection | 4 | 07/08/2026 |
| ALLSTATE ELEC'L CONT INC | Electrical | 3 | 03/22/2026 |
| SHAWMUT WOODWORKING & SUPPLY | General Contractor | 3 | 07/08/2026 |
| URBAN INTELLIGENCE, INC | General Contractor | 3 | 03/21/2026 |
| SEAN COAKLEY P & H INC | Plumbing | 3 | 07/08/2026 |
| SHAW MECHANICAL INC | Plumbing | 3 | 07/08/2026 |
| ACTIVE SIGNS | Scaffold | 2 | 07/08/2026 |
| A&A PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| BEDROCK PLBG. & HTG., INC | Plumbing | 2 | 07/08/2026 |
| BYPASS MECHANICAL CORP | Plumbing | 2 | 08/21/2026 |
| PHASE 3 INTERIORS LLC | General Contractor | 2 | 03/21/2026 |
| CROSSWIRE ELECTRICAL INC | Electrical | 2 | 03/22/2026 |
| DONATO PLUMBING, INC | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| WB ENGINEERING | 533 | 32 | 08/18/2026 |
| CODEGREEN | 510 | 4 | 08/17/2026 |
| ATLAS ATC ENGINEERING INC | 8011 | 39 | 09/26/2025 |
| SOCOTEC ENGINEERING | 4983 | 7 | 05/16/2025 |
| ATLANTIC ENGINEERINGLABOR | 1381 | 33 | 04/04/2024 |
| ALAN MARGOLIN & ASSOC | 423 | 2 | 03/09/2021 |
| SAG ENGINEERING & CONSULT | 608 | 3 | 01/14/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | FLOW-RIGHT PLBG & HTG COR | 10/01/2026 |
| DOB NOW | Plumbing | Permit Issued | CITY/SUBURBAN PLBG CORP | 10/01/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | STRUCTUAL PRESV SYSTEM | 09/29/2026 |
| DOB NOW | Structural | Permit Issued | JT MAGEN & COMPANY INC | 09/22/2026 |
| DOB NOW | Sprinklers | Permit Issued | BEDROCK MECHANICAL INC | 09/15/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | CLUNE CONSTRUCTION CO LP | 08/26/2026 |
| DOB NOW | Plumbing | Permit Issued | BYPASS MECHANICAL CORP | 08/20/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | TRI-STAR CONSTRUCTION CORP | 08/20/2026 |
| DOB NOW | General Construction | Permit Issued | TRI-STAR CONSTRUCTION CORP | 08/20/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | ANDAMIO SCAFFOLDING LLC | 08/19/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | CLUNE CONSTRUCTION CO LP | 08/11/2026 |
| DOB NOW | General Construction | Permit Issued | CLUNE CONSTRUCTION CO LP | 08/11/2026 |
| DOB NOW | General Construction | Permit Issued | CLUNE CONSTRUCTION CO LP | 08/11/2026 |
| DOB NOW | Plumbing | Permit Issued | BEDROCK PLBG. & HTG., INC | 06/30/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | CONCEPT CONSTRUCTION SERV | 06/24/2026 |
| DOB NOW | Sprinklers | Permit Issued | DENKO MECHANICAL INC | 06/23/2026 |
| DOB NOW | Sprinklers | Permit Issued | FULL CAPACITY FIRE CORP | 06/08/2026 |
| DOB NOW | General Construction | Permit Issued | CONCEPT CONSTRUCTION SERV | 06/05/2026 |
| DOB NOW | Plumbing | Permit Issued | A&A PLUMBING CORP | 06/04/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | CONCEPT CONSTRUCTION SERV | 06/02/2026 |
| DOB NOW | Plumbing | Permit Issued | BYPASS MECHANICAL CORP | 05/11/2026 |
| DOB NOW | General Construction | Permit Issued | CONCEPT CONSTRUCTION SERV | 05/11/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | CLUNE CONSTRUCTION CO LP | 05/01/2026 |
| DOB NOW | Sprinklers | Permit Issued | BEDROCK MECHANICAL INC | 04/30/2026 |
| DOB NOW | Sprinklers | Permit Issued | BEDROCK MECHANICAL INC | 04/29/2026 |
| DOB NOW | General Construction | Permit Issued | CLUNE CONSTRUCTION CO LP | 04/17/2026 |
| DOB NOW | General Construction | Permit Issued | CLUNE CONSTRUCTION CO LP | 04/17/2026 |
| DOB NOW | Sprinklers | Permit Issued | SEAN COAKLEY P & H INC | 02/26/2026 |
| DOB NOW | Sprinklers | Permit Issued | SEAN COAKLEY P & H INC | 02/26/2026 |
| DOB NOW | Sprinklers | Signed-off | CAPITOL FIRE SPRINKLER CO | 01/20/2026 |
| DOB NOW | Plumbing | Signed-off | A&A PLUMBING CORP | 01/08/2026 |
| DOB NOW | General Construction | Signed-off | STRUCTURE TONE, LLC | 12/03/2025 |
| DOB NOW | Mechanical Systems | Signed-off | STRUCTURE TONE, LLC | 12/03/2025 |
| DOB NOW | Sprinklers | Signed-off | CAPITOL FIRE SPRINKLER CO | 12/02/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | ARSENAL SCAFFOLD INC | 09/09/2025 |
| DOB NOW | Sprinklers | Signed-off | H M SPRINKLER INC | 08/18/2025 |
| DOB NOW | Mechanical Systems | Signed-off | STRUCTURE TONE, LLC | 08/08/2025 |
| DOB NOW | General Construction | Signed-off | STRUCTURE TONE, LLC | 08/05/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | ARSENAL SCAFFOLD INC | 06/04/2025 |
| DOB NOW | Sprinklers | Signed-off | H M SPRINKLER INC | 06/03/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/17/2026 | Permit Issued | TRI-STAR CONSTRUCTION COR | Air Conditioning Systems | Cooling Above Air MCW-004B 1 tons · Crac Unit ×2 |
| 06/18/2026 | Permit Issued | CONCEPT CONSTRUCTION SERV | Air Conditioning Systems | Cooling Water Furnace V7AH024 22,000 BTU · Wshp ×1 |
| 05/18/2026 | Signed-off | STRUCTURE TONE, LLC | Air Conditioning Systems | Cooling Vertiv MMD20G 600 CFM · Crac Unit ×1 |
| 04/30/2026 | Permit Issued | CLUNE CONSTRUCTION CO LP | Air Conditioning Systems | Cooling Water Furnace V7AH024 22,000 BTU · Wshp ×1 |
| 07/12/2024 | Signed-off | SHAWMUT WOODWORKING & SUP | Heating and Air Conditioning Systems | Heat / Cool |
| 11/13/2019 | — | — | Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/18/2026 | Permit Issued | BEDROCK MECHANICAL INC | Sprinkler System |
| 08/17/2026 | Permit Issued | BEDROCK MECHANICAL INC | Sprinkler System |
| 06/18/2026 | Permit Issued | DENKO MECHANICAL INC | Sprinkler System |
| 05/28/2026 | Permit Issued | FULL CAPACITY FIRE CORP | Sprinkler System |
| 05/18/2026 | Signed-off | CAPITOL FIRE SPRINKLER CO | Sprinkler System |
| 04/30/2026 | Permit Issued | BEDROCK MECHANICAL INC | Sprinkler System |
| 11/13/2019 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/18/2026 | Permit Issued | PLUMBING WORKS CORP | Water/Sanitary |
| 08/17/2026 | Permit Issued | CITY/SUBURBAN PLBG CORP | Water/Sanitary |
| 06/18/2026 | Permit Issued | BEDROCK PLUMBING & HEATING INC | Water/Sanitary |
| 05/18/2026 | Signed-off | A&A PLUMBING CORP | Water/Sanitary |
| 04/30/2026 | Permit Issued | PLUMBING WORKS CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/23/2026 | Permit Issued | MATROS AUTOMATED ELEC'L C | — |
| 08/26/2026 | Permit Issued | RONAN ELECTRICAL LLC | General Wiring |
| 08/26/2026 | Permit Issued | RONAN ELECTRICAL LLC | General Wiring |
| 08/26/2026 | Permit Issued | RONAN ELECTRICAL LLC | General Wiring |
| 08/26/2026 | Permit Issued | RONAN ELECTRICAL LLC | General Wiring |
| 12/30/2025 | Complete | ENCORE ELECTRICAL SERVICE | General Wiring |
| 08/05/2025 | Complete | RX ELECTRIC INC | — |
| 08/05/2025 | Complete | RX ELECTRIC INC | General Wiring |
| 06/06/2025 | Complete | RONAN ELECTRICAL LLC | General Wiring |
| 05/22/2025 | Complete | RX ELECTRIC INC | — |
| 05/13/2025 | Complete | ALLSTATE ELEC'L CONT INC | General Wiring |
| 05/13/2025 | Complete | ALLSTATE ELEC'L CONT INC | General Wiring |
| 05/09/2025 | Complete | RX ELECTRIC INC | General Wiring |
| 02/05/2025 | Complete | CROSSWIRE ELECTRICAL INC | General Wiring |
| 02/05/2025 | Complete | CROSSWIRE ELECTRICAL INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/17/2026 | Permit Issued | CITY/SUBURBAN PLBG CORP | Steel |
| 01/14/2020 | — | — | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/17/2024 | Permit Issued | ARSENAL SCAFFOLD INC | Sidewalk Shed |
| 08/18/2021 | Permit Issued | SCHNELLBACHER-SENDON GRO* | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/27/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 03/24/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/20/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/20/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/26/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/24/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/03/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/24/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/03/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/31/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/29/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/28/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/14/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 08/25/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/31/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/29/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/25/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/18/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 04/08/2025 | Pass-Final PL - Underground | Pass | View ↗ |
| 02/28/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/26/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/03/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/10/2025 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 12/26/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/19/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/24/2026 | Fire-Resistant Penetrations and Joints | James Sullivan Jr | special |
| 07/24/2026 | Sprinkler Systems | James Sullivan Jr | special |
| 07/24/2026 | Post-installed Anchors | James Sullivan Jr | special |
| 07/24/2026 | Post-installed Anchors | James Sullivan Jr | special |
| 07/24/2026 | Fire-Resistant Penetrations and Joints | James Sullivan Jr | special |
| 07/21/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/21/2026 | Fire-Resistance Rated Construction | — | progress |
| 07/15/2026 | Final | Wyett Baker | progress |
| 07/15/2026 | Sprayed fire-resistant materials | James Sullivan Jr | special |
| 07/15/2026 | Fire-Resistant Penetrations and Joints | James Sullivan Jr | special |
| 06/03/2026 | Electrical motors and elevators | David Bonifacic | energy_progress |
| 06/03/2026 | Interior lighting power | David Bonifacic | energy_progress |
| 06/03/2026 | HVAC-R and service water heating system controls | David Bonifacic | energy_progress |
| 06/03/2026 | HVAC-R and service water heating equipment | David Bonifacic | energy_progress |
| 06/03/2026 | Exterior lighting power | David Bonifacic | energy_progress |
| 06/03/2026 | HVAC-R and service water piping design and insulation | David Bonifacic | energy_progress |
| 06/03/2026 | Lighting controls | David Bonifacic | energy_progress |
| 06/03/2026 | Metering | David Bonifacic | energy_progress |
| 06/03/2026 | HVAC-R and service water piping design and insulation | David Bonifacic | energy_progress |
| 06/03/2026 | Maintenance information | David Bonifacic | energy_progress |
| 05/28/2026 | HVAC-R and service water piping design and insulation | David Bonifacic | energy_progress |
| 05/19/2026 | Energy Code Compliance Inspections | David Bonifacic | progress |
| 05/19/2026 | Final | David Bonifacic | progress |
| 05/19/2026 | Electrical motors and elevators | David Bonifacic | energy_progress |
| 05/19/2026 | Fire-Resistant Penetrations and Joints | David Bonifacic | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Hunter Point Capital | Office | Floors 15, 16 | Project M01431511 |
| Vercel AI | Office | Floor 9 | Project M01404632 |
| Betches | Office | Floor 6 | Project M01387830 |
| Trexquant | Office | Floor 10 | Project M01374907 |
| Grammarly | Office | Floor 11 | Project M01310481 |
| ICONIQ Capital | Office | Floors 17–20 | Project M01010924 Project M00989779 |