| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/05/2026 | Permit Issued | WINSON CONSTRUCTION INC | Heating and Air Conditioning Systems | Heat / Cool Lg model # LCN098HV4 12,000 BTU · Vrf Indoor ×6 model # LCN128HV4 12,000 BTU · Vrf Indoor ×6 LG-LMU480HHV 5 tons · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/05/2026 | Signed-off | CROWN PLUMBING INC | Storm |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/02/2025 | Complete | VMA ELECTRICAL CORP. | General Wiring |
| 08/29/2023 | Complete | A ELECTRICAL MAIN SVC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/05/2026 | Signed-off | CROWN PLUMBING INC | Steel, Masonry |
| Owner | Filings | Most Recent |
|---|---|---|
| OSSA PROPERTIES | 50 | 07/08/2026 |
| 360 TEN EYCK | 23 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| RIP CONSTRUCTION CONSULTANTS | 1 | 08/07/2026 |
| W.D.ROSS, R.A., P.C | 17 | 06/05/2026 |
| KRIS KOZLOWSKI ARCHITECT | 4 | 03/18/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| VMARCHDESIGN | 15 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CARPEX INC | General Contractor | 3 | 03/21/2026 |
| WINSON CONSTRUCTION INC | General Contractor | 3 | 07/08/2026 |
| BLAZE PLUMBING & HEATING | Plumbing | 1 | 07/08/2026 |
| CROWN PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| PASQUALE QUARATINO INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| S&S CONCRETE & SOIL TESTI | 1008 | 10 | 06/05/2026 |
| KRIS KOZLOWSKI ARCHITECT | 3955 | 4 | 03/18/2025 |
| W.D.ROSS, R.A., P.C | 3758 | 5 | 06/08/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | CROWN PLUMBING INC | 08/20/2025 |
| DOB NOW | General Construction | Signed-off | CARPEX INC | 03/04/2025 |
| DOB NOW | Plumbing | Signed-off | BLAZE PLUMBING & HEATING | 02/18/2025 |
| DOB NOW | General Construction | Permit Issued | WINSON CONSTRUCTION INC | 07/01/2023 |
| DOB NOW | General Construction | Permit Issued | WINSON CONSTRUCTION INC | 03/22/2023 |
| DOB NOW | Plumbing | Signed-off | PASQUALE QUARATINO INC | 06/17/2021 |
| BIS | PL | ISSUED | ORBIT PLBG & HTG INC | 11/09/2015 |
| BIS | FP | ISSUED | NY FIRE LLC | 07/15/2015 |
| BIS | PL | ISSUED | ORBIT PLBG & HTG INC | 11/06/2014 |
| BIS | — | ISSUED | RICHFIELD CONSTRUCTION IN | 05/16/2014 |
| BIS | OT | ISSUED | RICHFIELD CONSTRUCTION IN | 02/12/2014 |
| BIS | PL | ISSUED | ORBIT PLBG & HTG INC | 09/11/2012 |
| BIS | — | ISSUED | RICHFIELD DESIGN & CONSTR | 08/30/2012 |
| BIS | EQ | ISSUED | RICHFIELD DESIGN & CONSTR | 08/30/2012 |
| BIS | PL | ISSUED | ENTERPRISE PLBG & HTG INC | 10/01/2010 |
| BIS | — | ISSUED | D'LUIS CONSTRUCTION CORP | 07/28/2010 |
| BIS | — | ISSUED | MEDICI CONTRACTING CORP | 04/07/2009 |
| BIS | — | ISSUED | MEDICI CONTRACTING CORP. | 04/25/2008 |
| BIS | PL | ISSUED | ENTERPRISE PLUMBING & HTG. INC. | 04/16/2008 |
| BIS | — | ISSUED | MEDICI CONTRACTING CORP. | 09/14/2007 |
| BIS | — | ISSUED | MEDICI CONTRACTING CORP. | 09/20/2006 |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/02/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/06/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 09/05/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 04/23/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/31/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/20/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/27/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/26/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/28/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/20/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/27/2025 | Fire-Resistant Penetrations and Joints | Kris Kozlowski | special |
| 12/13/2024 | Public Assembly Emergency Lighting | WILLIAM ROSS | progress |
| 10/10/2023 | Energy Code Compliance Inspections | GLEN LANGER | progress |
| 10/10/2023 | Fire-Resistant Penetrations and Joints | GLEN LANGER | special |
| 10/10/2023 | Maintenance information | GLEN LANGER | energy_progress |
| 10/06/2023 | Fenestration air leakage | GLEN LANGER | energy_progress |
| 10/06/2023 | Fenestration and door U-factor and product ratings | GLEN LANGER | energy_progress |
| 10/06/2023 | Permanent certificate | GLEN LANGER | energy_progress |
| 10/06/2023 | Lighting controls | GLEN LANGER | energy_progress |
| 10/06/2023 | Insulation placement and R values | GLEN LANGER | energy_progress |
| 10/06/2023 | HVAC-R and service water heating equipment | GLEN LANGER | energy_progress |
| 10/06/2023 | Exterior lighting power | GLEN LANGER | energy_progress |
| 10/06/2023 | Fire-Resistance Rated Construction | GLEN LANGER | progress |
| 10/06/2023 | Energy Code Compliance Inspections | GLEN LANGER | progress |
| 10/06/2023 | Final | GLEN LANGER | progress |
| 10/06/2023 | Fire-Resistant Penetrations and Joints | GLEN LANGER | special |
| 10/06/2023 | Structural Cold-Formed Steel | GLEN LANGER | special |
| 10/06/2023 | Mechanical Systems | GLEN LANGER | special |
| 10/06/2023 | Structural Steel - High Strength Bolting | GLEN LANGER | special |
| 10/06/2023 | Masonry | GLEN LANGER | special |
| 10/06/2023 | Structural Stability – Alterations of existing buildings | GLEN LANGER | special |
| 10/06/2023 | Structural Steel - Welding | GLEN LANGER | special |
| 10/06/2023 | Structural Steel - Details | GLEN LANGER | special |
| 10/06/2023 | HVAC-R and service water heating system controls | GLEN LANGER | energy_progress |
| 10/06/2023 | HVAC-R and service water piping design and insulation | GLEN LANGER | energy_progress |