Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofMechanical systems installation in cellar, floors, penthouse7p · 1 filing · 13 docs
Mechanical
Issued Permit Scope
Mechanical Systems
INSTALLATION OF MECHANICAL SYSTEMS IN CELLAR, FLOORS 001-004, PENTHOUSE, AND ROOF IN CONJUNCTION WITH ALT 1 FILING JOB NUMBER 220723867. NO CHANGE OF EGRESS, USE, OR OCCUPANCY.
On file for this project
13 documents
PenthouseMechanical systems installation in cellar, floors, penthouse34p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Structural
INSTALLATION OF MECHANICAL SYSTEMS IN CELLAR, FLOORS 001-004, PENTHOUSE, AND ROOF IN CONJUNCTION WITH ALT 1 FILING JOB NUMBER 220723867. NO CHANGE OF EGRESS, USE, OR OCCUPANCY.
On file for this project
13 documents
INSTALLATION OF NEW SPRINKLER SYSTEM AS PER PLANS
On file for this project
12 documents
INSTALLATION OF PLUMBING FIXTURES IN CONJUNCTION TO ALT 1 FILING JOB NUMBER 220723867. NO CHANGE OF EGRESS, USE, OR OCCUPANCY.
On file for this project
24 documents
Latest 3 of 4 filings on this floor.
Floor 4Mechanical systems installation in cellar, floors, penthouse38p · 6 filings · 20 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Structural · Supported Scaffold
INSTALLATION OF MECHANICAL SYSTEMS IN CELLAR, FLOORS 001-004, PENTHOUSE, AND ROOF IN CONJUNCTION WITH ALT 1 FILING JOB NUMBER 220723867. NO CHANGE OF EGRESS, USE, OR OCCUPANCY.
On file for this project
13 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Latest 3 of 6 filings on this floor.
Floor 3Mechanical systems installation in cellar, floors, penthouse37p · 6 filings · 20 docs
EquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Structural · Supported Scaffold
INSTALLATION OF MECHANICAL SYSTEMS IN CELLAR, FLOORS 001-004, PENTHOUSE, AND ROOF IN CONJUNCTION WITH ALT 1 FILING JOB NUMBER 220723867. NO CHANGE OF EGRESS, USE, OR OCCUPANCY.
On file for this project
13 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Latest 3 of 6 filings on this floor.
Floor 2Mechanical systems installation in cellar, floors, penthouse37p · 6 filings · 20 docs
EquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Structural · Supported Scaffold
INSTALLATION OF MECHANICAL SYSTEMS IN CELLAR, FLOORS 001-004, PENTHOUSE, AND ROOF IN CONJUNCTION WITH ALT 1 FILING JOB NUMBER 220723867. NO CHANGE OF EGRESS, USE, OR OCCUPANCY.
On file for this project
13 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Latest 3 of 6 filings on this floor.
Floor 1Mechanical systems installation in cellar, floors, penthouse37p · 6 filings · 20 docs
EquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Structural · Supported Scaffold
INSTALLATION OF MECHANICAL SYSTEMS IN CELLAR, FLOORS 001-004, PENTHOUSE, AND ROOF IN CONJUNCTION WITH ALT 1 FILING JOB NUMBER 220723867. NO CHANGE OF EGRESS, USE, OR OCCUPANCY.
On file for this project
13 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Latest 3 of 6 filings on this floor.
CellarMechanical systems installation in cellar, floors, penthouse34p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Structural
INSTALLATION OF MECHANICAL SYSTEMS IN CELLAR, FLOORS 001-004, PENTHOUSE, AND ROOF IN CONJUNCTION WITH ALT 1 FILING JOB NUMBER 220723867. NO CHANGE OF EGRESS, USE, OR OCCUPANCY.
On file for this project
13 documents
INSTALLATION OF NEW SPRINKLER SYSTEM AS PER PLANS
On file for this project
12 documents · 1 drawing sheet
INSTALLATION OF PLUMBING FIXTURES IN CONJUNCTION TO ALT 1 FILING JOB NUMBER 220723867. NO CHANGE OF EGRESS, USE, OR OCCUPANCY.
On file for this project
24 documents
Latest 3 of 4 filings on this floor.
Site & exteriorSupport of Excavation Work21p · 5 filings · 20 docs
CivilElectricalEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Sidewalk Shed · Supported Scaffold · Support of Excavation
SUPPORT OF EXCAVATION FILING IN CONJUNCTION WITH ALT 1 220723867. THIS APPLICATION IS FOR SOE WORK ONLY.
On file for this project
12 documents · 3 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 4 drawing sheets
Latest 3 of 5 filings on this floor.