| Owner | Filings | Most Recent |
|---|---|---|
| OWNER OF 3610 HOLLAND AVE | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/05/2022 | $470K | — | Private party → Private party | $208/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| A&A CONSULTING ENGINEERS PC | 5 | 09/20/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BADINI CONSTRUCTION CORP | General Contractor | 8 | 07/08/2026 |
| M & M PIPING AND HEATING | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A&B ENGINEERING AND LAND | 2470 | 5 | 09/20/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | M & M PIPING AND HEATING | 11/27/2024 |
| DOB NOW | General Construction | Permit Issued | BADINI CONSTRUCTION CORP | 08/02/2024 |
| DOB NOW | General Construction | Permit Issued | BADINI CONSTRUCTION CORP | 10/23/2023 |
| DOB NOW | General Construction | Permit Issued | BADINI CONSTRUCTION CORP | 07/10/2023 |
| DOB NOW | Plumbing | Signed-off | M & M PIPING AND HEATING | 06/09/2023 |
| DOB NOW | General Construction | Permit Issued | BADINI CONSTRUCTION CORP | 04/27/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/05/2023 | Complete | V&B ELECTRICAL CONTNG INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/25/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/16/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/16/2023 | Certified Sprinkler (PL)-SP-Fixtures (PL)-Finish | Certified | View ↗ |
| 10/16/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/16/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/11/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/03/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/03/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/03/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/11/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/27/2024 | Fire-Resistant Penetrations and Joints | David Arabi | special |
| 09/27/2024 | Energy Code Compliance Inspections | SAEED AINECHI | progress |
| 09/27/2024 | Permanent certificate | SAEED AINECHI | energy_progress |
| 09/27/2024 | Maintenance information | SAEED AINECHI | energy_progress |
| 01/17/2024 | Fire-Resistant Penetrations and Joints | David Arabi | special |
| 01/17/2024 | Energy Code Compliance Inspections | SAEED AINECHI | progress |
| 01/17/2024 | Fire-Resistance Rated Construction | David Arabi | progress |
| 01/17/2024 | Lighting in dwelling units | David Arabi | energy_progress |
| 01/17/2024 | Fenestration and door U-factor and product ratings | SAEED AINECHI | energy_progress |
| 01/17/2024 | Fenestration air leakage | David Arabi | energy_progress |
| 01/17/2024 | Air barrier - visual inspection | David Arabi | energy_progress |
| 01/17/2024 | Fenestration areas | David Arabi | energy_progress |