← Back
Elevator cooperative
3626 KINGS HIGHWAY
BROOKLYN · Flatlands · BIN 3209903
💬 Discuss this project
1939Year Built
6Stories
D4Building Class
R5Zoning
94,128 sfGross Floor Area
72Units
LL97 CoveredRent Stabilized85 Open Violations 76 unresolved · 9 paperwork only ▸FISP: SAFEFDNY Report ↗
Elevator cooperative · Owner of record: 3626 KINGS HIGHWAY OWNERS CORP · 21,000 sf lot · 4.48 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Roof5p · 2 filings · 11 docs
Basement2p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
FIRSTSERVICE RESIDENTIAL907/08/2026
T-MOBILE907/08/2026
3626 KINGS HIGHWAY OWNERS CORP2603/22/2026
3625 KINGS HIGHWAY OWNERS103/22/2026
CELL TOWER LEASE ACQUISITION203/21/2026
3626 KINGS HWY OWNERS303/21/2026
CELL TOWER LEASE303/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ROGER DE ELECTRIC CO.208/08/2023
PAUL PERDEK, PROF. ENG. PLLC303/21/2022
KMB DESIGN GROUP, LLC103/04/2022
CSANAD BODNAR ARCHITECT107/13/2021
JOHN M BANKS ARCHITECT108/07/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AE DESIGN SOLUTION603/21/2026
CONSTRUCTION PERMIT SERVICES203/21/2026
CODECOMPLINACE203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SQUAN CONSTRUCTION SERVICGeneral Contractor507/08/2026
INTER RENOVATION INCGeneral Contractor407/08/2026
POWERS BRIDGING & SCAFFOLDINGGeneral Contractor207/08/2026
BEKKERMAN, MIKHAILElectrical103/21/2026
MP & L METAL INCElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SALAMON ENGINEERING PLLC1264208/08/2023
KMB DESIGN GROUP, LLC513103/04/2022
Building Lifecycle
All (97)Filed (8)Permit Issued (7)Signed Off (2)Facade (FISP) (18)Violation (60)Special Inspection (2)
06/24/2026
Violation issued (ECB, open)
Elevators
06/20/2026
Violation issued (HPD, open)
A
05/22/2026
Violation issued (ECB, open)
Elevators
04/27/2026
Violation issued (ECB, open)
Elevators
04/21/2025
Violation issued (HPD, open)
B
04/21/2025
Violation issued (HPD, open)
B
04/21/2025
Violation issued (HPD, open)
B
04/21/2025
Violation issued (HPD, open)
B
04/20/2025
Violation issued (HPD, open)
C
04/20/2025
Violation issued (HPD, open)
B
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/06/2024
Signed off — Alteration
DECOMMISSION OF EXISTING SPRINT/CW TELECOM SITE. REMOVE EQUIPMENT ROOM FROM BASEMENT. REMOVE 12 ANTENNAS, 7 RRH AND 1 GPS FROM THE ROOF. REMOVE CABLES FROM BASEMENT AND ROOF. NO CHANGE IN USE, EGRESS OR OCCUPANCY. ORIGINAL APP# 300554442
B00685093-I1
03/06/2024
Permit issued — Antenna
B00685093-I1-AN
10/04/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/04/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
08/21/2023
Special inspection requirement — Masonry
David Salamon
08/21/2023
Special inspection requirement — Final
David Salamon
08/08/2023
Filed — Alteration
B00520285-P1
04/24/2023
Violation issued (ECB, open)
Elevators
04/24/2023
Violation issued (ECB, open)
Elevators
03/06/2023
Permit issued — Antenna
B00685093-I1-AN
12/22/2022
Cycle 9 facade report signed — SAFE
12/13/2022
Cycle 9 facade report submitted
11/28/2022
Cycle 9 facade inspection completed
11/05/2022
Signed off — Alteration
B00687709-I1
08/17/2022
Permit issued — Sidewalk Shed
B00532158-I1-SH
03/31/2022
Permit issued — Supported Scaffold
B00687709-I1-SF
03/23/2022
Permit issued — Antenna
B00685093-I1-AN
03/21/2022
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00532158-P1
03/16/2022
Filed — Alteration
B00687709-I1
03/04/2022
Filed — Alteration
DECOMMISSION OF EXISTING SPRINT/CW TELECOM SITE. REMOVE EQUIPMENT ROOM FROM BASEMENT. REMOVE 12 ANTENNAS, 7 RRH AND 1 GPS FROM THE ROOF. REMOVE CABLES FROM BASEMENT AND ROOF. NO CHANGE IN USE, EGRESS OR OCCUPANCY. ORIGINAL APP# 300554442
B00685093-I1
02/18/2022
Cycle 9 facade report submitted
02/18/2022
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/18/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/10/2022
Violation issued (ECB, closed)
Construction
02/10/2022
Violation issued (ECB, closed)
Construction
02/10/2022
Violation issued (ECB, closed)
Construction
02/09/2022
Cycle 9 facade report signed — UNSAFE
02/07/2022
Cycle 9 facade inspection completed
02/07/2022
Violation issued (HPD, open)
A
02/07/2022
Violation issued (HPD, open)
B
12/09/2021
Violation issued (HPD, open)
B
10/23/2021
Violation issued (HPD, open)
B
10/23/2021
Violation issued (HPD, open)
B
10/23/2021
Violation issued (HPD, open)
B
09/14/2021
Violation issued (HPD, open)
A
09/14/2021
Violation issued (HPD, open)
A
09/14/2021
Violation issued (HPD, open)
B
09/14/2021
Violation issued (HPD, open)
B
09/14/2021
Violation issued (HPD, open)
B
09/14/2021
Violation issued (HPD, open)
A
09/14/2021
Violation issued (HPD, open)
B
09/14/2021
Violation issued (HPD, open)
B
08/20/2021
Permit issued — Sidewalk Shed
B00532158-I1-SH
08/07/2021
Violation issued (HPD, open)
B
07/28/2021
Permit issued — General Construction
B00520285-I1-GC
07/13/2021
Filed — Alteration
Install new gas clothing dryers and 2 new sprinkler heads off domestic water supply. No change in use egress or occupancy
B00518871-I1
06/23/2021
Violation issued (HPD, closed)
C
06/15/2021
Violation issued (HPD, closed)
C
06/15/2021
Violation issued (HPD, open)
A
Latest 60 of 97 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWAntennaSigned-offSQUAN CONSTRUCTION SERVIC03/06/2024
DOB NOWAntennaSigned-offSQUAN CONSTRUCTION SERVIC03/06/2023
DOB NOWSidewalk ShedPermit IssuedPOWERS BRIDGING & SCAFFOL08/17/2022
DOB NOWSupported ScaffoldSigned-offINTER RENOVATION INC03/31/2022
DOB NOWAntennaSigned-offSQUAN CONSTRUCTION SERVIC03/23/2022
DOB NOWSidewalk ShedPermit IssuedPOWERS BRIDGING & SCAFFOL08/20/2021
DOB NOWGeneral ConstructionPermit IssuedINTER RENOVATION INC07/28/2021
BISOTISSUEDTELCOM ENGINEERING GP INC10/05/2020
BISEQISSUEDPREMIERONE RESTORATION IN01/19/2017
BISOTISSUEDPREMIERONE RESTORATION IN11/03/2016
BISOTISSUEDHPC WIRELESS SERVICES LLC04/22/2016
BISOTISSUEDJ.A. LEE ELECTRIC INC09/15/2015
BISOTISSUEDVERTICAL SOLUTIONS INC03/21/2014
BISOTISSUEDSPIROS CONSTRUCTION SGC I01/15/2013
BISOTISSUEDNEXLINK GLOBAL SERVICES I07/18/2012
BISOTISSUEDTRINITY TECHNOLOGIES LLC10/04/2010
BISOTISSUEDBCI COMMUNICATIONS INC01/22/2009
BISOTISSUEDTELCOM ENGINEERING GP INC09/19/2008
BISOTISSUEDBCI COMMUNICATIONS INC.02/01/2008
BISOTISSUEDSQUAN CONSTRUCTION SERVIC01/29/2008
BISOTISSUEDTRI-STATE TELECOMM.11/22/2005
BISOTISSUEDBERLINER COMMUNICATION INC12/18/1998
BISOTISSUEDBERLINER COMMUNICATION INC11/30/1998
BISMHISSUEDGJF CONSTRUCTION CORP D/B/A NYC11/22/1996
BISOTISSUEDGJF CONSTRUCTION CORP D/B/A NYC11/20/1996
BISPLISSUEDBALTER LEHIGH PLUMBING AND HEATI02/05/1996
BISFSISSUEDBORO FUEL OIL02/05/1996
1 project · most recent 07/13/2021
Gas
FiledStatusContractorScope
07/13/2021——Gas
4 projects · most recent 03/14/2024
General Wiring
FiledStatusContractorScope
03/14/2024CompleteMECHANICAL ELECTR'L CORP.—
10/07/2022Permit IssuedSTAR ELEC'L CONTRACTORS C—
06/06/2021CompleteOPTIMAL ELECTRIC, INC—
03/10/2020CompleteALL CITY ELECTRICAL INCGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 2
DateRequirementInspectorRole
08/21/2023MasonryDavid Salamonspecial
08/21/2023FinalDavid Salamonprogress
▾Documents — 190 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch7
09/01/2026B00518871-I1Request digital key ↗
08/31/2026B00685093-I1Request digital key ↗
08/30/2026B00687709-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Antenna1
09/02/2026B00185582-I1Request digital key ↗
▸Applications & Permits37
▸BISPLAN / WORK APPROVAL APPLICATION18
08/12/2020340751859Open ↗
01/31/2020310013641Open ↗
01/31/2020321207626Open ↗
Showing 3 of 18 on file for this type
▸BISWORK PERMIT APPLICATION16
10/23/2020340751859Open ↗
10/23/2020340751859Open ↗
09/30/2020340751859Open ↗
Showing 3 of 16 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION3
08/25/2020340751859Open ↗
01/23/2020310013641Open ↗
01/23/2020321207626Open ↗
▸Seals & Professional Certifications40
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION21
07/18/2017321114003Open ↗
01/19/2017321511645Open ↗
12/05/2015320962295Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
09/01/2026B00518871-I1Open ↗
08/31/2026B00685093-I1Open ↗
08/30/2026B00687709-I1Open ↗
Showing 3 of 8 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
01/19/2017321511645Open ↗
01/16/2013320588529Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
08/12/2020340751859Open ↗
10/14/2016340430448Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
01/16/2013320588529Open ↗
▸BISProfessional and Owner Certification (POC3)1
01/19/2017321511645Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
10/14/2016340430448Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
10/14/2016340430448Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
08/12/2020340751859Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/26/2026B00520285-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/26/2026B00520285-I1Open ↗
▸Safety & Tenant Protection5
▸BISTenant Protection Plan and Notes3
08/12/2020340751859Open ↗
01/19/2017321511645Open ↗
10/14/2016340430448Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
02/12/2020321207626Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026B00185582-I1Open ↗
▸Environmental & Asbestos15
▸BISASBESTOS: CERTIFICATION (DEP ACP5)8
08/12/2020340751859Open ↗
10/14/2016340430448Open ↗
09/08/2015321207626Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/31/2026B00685093-I1Open ↗
08/27/2026B00520285-P1Open ↗
08/27/2026B00520285-I1Open ↗
Showing 3 of 4 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'3
01/24/2008310083110Open ↗
08/27/2007310013641Open ↗
06/28/2012320490811Open ↗
▸Energy Compliance23
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS9
07/18/2017321114003Open ↗
12/05/2015320962295Open ↗
09/08/2015321207626Open ↗
Showing 3 of 9 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS6
12/22/2020310013641Open ↗
11/24/2020340751859Open ↗
11/19/2020340751859Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
11/24/2020340751859Open ↗
11/19/2020340751859Open ↗
08/12/2020340751859Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
08/12/2020340751859Open ↗
10/14/2016340430448Open ↗
▸BISTR8: Energy Code Progress Inspections1
06/28/2012320490811Open ↗
▸BISNYCECC ANALYSIS1
10/14/2016340430448Open ↗
▸Inspections & Test Reports10
▸BISTECHNICAL REPORT: RESPONSIBILITY10
12/22/2020310013641Open ↗
12/22/2020310013641Open ↗
12/09/2020321207626Open ↗
Showing 3 of 10 on file for this type
▸Approvals, Objections & Sign-offs18
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST8
01/14/2021340751859Open ↗
11/24/2020340751859Open ↗
11/19/2020340751859Open ↗
Showing 3 of 8 on file for this type
▸BISADMINISTRATIVE OBJECTIONS7
07/21/2015321163076Open ↗
04/27/2015321114003Open ↗
05/31/2014320962295Open ↗
Showing 3 of 7 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
09/30/2020340751859Open ↗
10/14/2016340430448Open ↗
10/21/2013320588529Open ↗
▸Cost, Insurance & Ownership21
▸BISCOST AFFIDAVIT21
11/24/2020340751859Open ↗
11/19/2020340751859Open ↗
08/12/2020340751859Open ↗
Showing 3 of 21 on file for this type
▸Filing & Intake Forms12
▸BISEFILING COVER SHEET7
01/20/2017321511645Open ↗
09/08/2015321207626Open ↗
07/21/2015321163076Open ↗
Showing 3 of 7 on file for this type
▸BISADDITIONAL INFORMATION3
12/09/2020321207626Open ↗
12/08/2020310013641Open ↗
07/22/2013320588529Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
08/12/2020340751859Open ↗
10/14/2016340430448Open ↗
▸Other Documents1
▸DOB NOWDHCR Document1
09/01/2026B00518871-I1Open ↗