| Owner | Filings | Most Recent |
|---|---|---|
| V V DEVELOPMENT | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ROGERS CALVANICO GROUP PLLC | 5 | 10/30/2025 |
| TOM PETERSEN ARCHITECT, LLC | 1 | 09/08/2025 |
| A TECH ENGINEERING NYC, PLLC. | 2 | 11/22/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| ROGERS CALVANICO GROUP | 4 | 03/21/2026 |
| A TECH ENGINEERING NYC | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| V&V DEVELOPMENT CORP | General Contractor | 6 | 07/03/2026 |
| THE GREEN PLUG LLC | General Contractor | 1 | 04/09/2026 |
| FLOW-RIGHT PLBG & HTG COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A TECH ENGINEERING NYC, P | 6738 | 2 | 10/30/2025 |
| C&P DESIGN CONSULTANT | 8472 | 4 | 10/30/2025 |
| THOMAS PETERSEN ARCHITECT | 7854 | 1 | 09/08/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Foundation | Permit Issued | V&V DEVELOPMENT CORP | 07/01/2026 |
| DOB NOW | Solar | Signed-off | THE GREEN PLUG LLC | 09/11/2025 |
| DOB NOW | Plumbing | Permit Issued | FLOW-RIGHT PLBG & HTG COR | 02/18/2025 |
| DOB NOW | Foundation | Permit Issued | V&V DEVELOPMENT CORP | 12/10/2024 |
| DOB NOW | Foundation | Permit Issued | V&V DEVELOPMENT CORP | 12/03/2024 |
| DOB NOW | Construction Fence | Signed-off | V&V DEVELOPMENT CORP | 10/23/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/30/2025 | Permit Issued | FLOW-RIGHT PLBG & HTG COR | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/04/2025 | Complete | L.D.M. ELECTL CONTRS INC | — |
| 05/29/2025 | Permit Issued | KWONG MING ELECTRIC INC | General Wiring |
| 05/28/2025 | Permit Issued | KWONG MING ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/30/2025 | Permit Issued | V&V DEVELOPMENT CORP | Wood |
| 11/22/2024 | Permit Issued | V&V DEVELOPMENT CORP | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/08/2025 | Signed-off | THE GREEN PLUG LLC | 36 panels, 15.3 kw, 2,020.81 roof_area_sqft |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/30/2025 | Permit Issued | V&V DEVELOPMENT CORP | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/26/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/26/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 11/18/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/20/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/04/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 02/28/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 02/26/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/26/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/14/2025 | Fenestration areas | Stanislav Pilipenko | energy_progress |
| 11/14/2025 | Insulation placement and R values | Stanislav Pilipenko | energy_progress |
| 11/14/2025 | Permanent certificate | Stanislav Pilipenko | energy_progress |
| 11/14/2025 | Maintenance information | Stanislav Pilipenko | energy_progress |
| 11/14/2025 | Fireplaces | Stanislav Pilipenko | energy_progress |
| 11/14/2025 | Fenestration and door U-factor and product ratings | Stanislav Pilipenko | energy_progress |
| 11/14/2025 | Subgrade Inspections | Stanislav Pilipenko | special |
| 11/14/2025 | Mechanical Systems | Stanislav Pilipenko | special |
| 11/14/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Stanislav Pilipenko | special |
| 11/14/2025 | Subsurface Investigations (Borings/Test Pits) | WILLIAM MONTAGUE | special |
| 11/14/2025 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Stanislav Pilipenko | special |
| 11/14/2025 | Concrete - Cast-In-Place | Stanislav Pilipenko | special |
| 11/14/2025 | Fire-Resistant Penetrations and Joints | Stanislav Pilipenko | special |
| 11/14/2025 | Footing and Foundation | Stanislav Pilipenko | progress |
| 11/14/2025 | Structural Wood Frame | Stanislav Pilipenko | progress |
| 11/14/2025 | Fire-Resistance Rated Construction | Stanislav Pilipenko | progress |
| 11/14/2025 | Lowest Floor Elevation | Stanislav Pilipenko | progress |
| 11/14/2025 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |
| 11/14/2025 | Final | Stanislav Pilipenko | progress |
| 11/14/2025 | Ventilation and air distribution system | Stanislav Pilipenko | energy_progress |
| 11/14/2025 | HVAC-R and service water piping design and insulation | Stanislav Pilipenko | energy_progress |
| 11/14/2025 | HVAC-R and service water heating equipment | Stanislav Pilipenko | energy_progress |
| 11/14/2025 | Fenestration air leakage | Stanislav Pilipenko | energy_progress |
| 11/14/2025 | Protection of exposed foundation insulation | Stanislav Pilipenko | energy_progress |
| 11/14/2025 | Metering | Stanislav Pilipenko | energy_progress |