| 07/13/2026 | Permit Issued | WATTS UP ELECTRIC NY LLC | — |
| 05/27/2026 | Complete | WATTS UP ELECTRIC NY LLC | — |
| 12/09/2024 | Complete | RICHARD NEU | — |
| 12/25/2021 | Complete | AP ELECTL SER & MAIN INC | General Wiring |
| 04/29/2020 | Complete | OM ELECTRIC, INC | General Wiring |
| 01/13/2020 | Complete | STAR ELEC'L CONTRACTORS C | — |
| 10/17/2019 | Complete | WCK ELECTRIC CORP. | — |
| 10/02/2019 | Complete | RICHARD NEU | — |
| 09/26/2019 | Complete | OM ELECTRIC, INC | 89 meters, 89 new_meters |
| 02/02/2019 | Complete | RICHARD NEU | — |
| Owner | Filings | Most Recent |
|---|---|---|
| STEEL CITY GROUP | 5 | 07/08/2026 |
| RELIABLE ENTERPRISES | 12 | 07/08/2026 |
| MANAGEMENT OFFICE | 15 | 07/08/2026 |
| HKS CONSTRUCTION | 15 | 07/08/2026 |
| SAFELINE GROUP INC. | 5 | 03/22/2026 |
| 3660 WALDO | 56 | 03/22/2026 |
| M RUBIN & CO LLC | 40 | 03/22/2026 |
| BUILDWELL GROUP | 1 | 03/22/2026 |
| 3660 WALDO LLC LEASING | 6 | 03/22/2026 |
| RK CONTRACTING | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/30/2013 | $17.6M | — | — → — | $244/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| RISE ARCHITECTURE NJ LLC | 1 | 12/09/2024 |
| RICHARD KOENIGSBERG | 1 | 10/23/2024 |
| ENTHINK ENGINEERS LLC | 5 | 06/07/2021 |
| MOORE ASSOCIATES, LLC | 3 | 04/05/2021 |
| GUTH DECONZO CONSULTING ENGINEERS, | 1 | 07/20/2020 |
| SYED ENGINEERING, P.C. | 1 | 10/03/2019 |
| HAIDER ENGINEERING, P.E. | 2 | 07/02/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| ADVANCED BUILDERS SERVICES | 1 | 03/21/2026 |
| HAIDER ENGINEERING, P.E. | 2 | 03/21/2026 |
| SNR EXPEDITING DESIGN | 2 | 03/21/2026 |
| METROPOLIS GROUP INC | 2 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 1 | 03/21/2026 |
| HAIDER ENGINEERING P E | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HKS CONSTRUCTION CORP | General Contractor | 7 | 07/08/2026 |
| SAFELINE GROUP INC | General Contractor | 3 | 03/21/2026 |
| HUDSON PLMBING & MCH, LLC | Plumbing | 2 | 07/08/2026 |
| RICHARD NEU | Electrical | 1 | 03/21/2026 |
| TORRES IVAN | Electrical | 1 | 03/21/2026 |
| BUILDWELL GROUP INC | General Contractor | 1 | 07/08/2026 |
| OM ELECTRIC, INC | Electrical | 1 | 03/22/2026 |
| RELIABLE ENTERPRISES INC | General Contractor | 1 | 07/08/2026 |
| MORALES, RICHARD | Electrical | 1 | 03/21/2026 |
| TOPLINE GC INC | General Contractor | 1 | 07/08/2026 |
| HOD PIPING & HEATING CORP | Plumbing | 1 | 07/08/2026 |
| AP ELECTL SER & MAIN INC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MCHENERY TESTING LAB | 9181 | 1 | 11/20/2024 |
| KOENIGSBERG ENGINEERING, | 2247 | 1 | 10/23/2024 |
| MOORE ASSOCIATES, LLC | 3408 | 3 | 04/05/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Suspended Scaffold | Permit Issued | HARMEL SINGH | 12/24/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | SAFELINE GROUP INC | 12/09/2024 |
| DOB NOW | Plumbing | Signed-off | HUDSON PLMBING & MCH, LLC | 03/16/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | RELIABLE ENTERPRISES INC | 03/12/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | TOPLINE GC INC | 10/26/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | HKS CONSTRUCTION CORP | 10/02/2020 |
| DOB NOW | Supported Scaffold | Signed-off | HKS CONSTRUCTION CORP | 10/02/2020 |
| DOB NOW | Plumbing | Signed-off | HUDSON PLMBING & MCH, LLC | 10/01/2020 |
| DOB NOW | Plumbing | Signed-off | HOD PIPING & HEATING CORP | 09/02/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | BUILDWELL GROUP INC | 10/07/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | HKS CONSTRUCTION CORP | 06/27/2019 |
| DOB NOW | Supported Scaffold | Signed-off | HKS CONSTRUCTION CORP | 03/18/2019 |
| DOB NOW | Supported Scaffold | Signed-off | HKS CONSTRUCTION CORP | 08/23/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | HKS CONSTRUCTION CORP | 07/03/2018 |
| DOB NOW | Supported Scaffold | Signed-off | HKS CONSTRUCTION CORP | 04/11/2018 |
| BIS | SP | ISSUED | PHOENIX PLMBG & MECH CORP | 10/25/2021 |
| BIS | PL | ISSUED | HOD PIPING & HEATING CORP | 03/02/2021 |
| BIS | OT | ISSUED | RK CONTRACTING INC | 12/14/2020 |
| BIS | OT | ISSUED | CITYLINE RESTORATION INC | 02/11/2020 |
| BIS | OT | ISSUED | SNS ORGNIZATION LTD | 06/06/2019 |
| BIS | — | ISSUED | ATLAS BUILDERS LLC | 02/21/2019 |
| BIS | OT | ISSUED | SACON ENTERPRISES LIMITED | 07/10/2018 |
| BIS | PL | ISSUED | HAROLD HEADLEY PLUMBING | 07/06/2018 |
| BIS | OT | ISSUED | SACON ENTERPRISES LIMITED | 06/27/2018 |
| BIS | OT | ISSUED | CITYLINE RESTORATION INC | 02/12/2018 |
| BIS | PL | ISSUED | TOP PLUMBING GROUP,INC | 08/24/2017 |
| BIS | OT | ISSUED | NIC DESIGN MGMT INC | 08/24/2017 |
| BIS | OT | ISSUED | EURO T.I. INC | 07/14/2017 |
| BIS | OT | ISSUED | HH BUILDING CONSULTING & | 06/12/2017 |
| BIS | OT | ISSUED | STEEL TONE CONSTRUCTION | 04/10/2017 |
| BIS | OT | ISSUED | CITYLINE RESTORATION INC | 02/17/2017 |
| BIS | OT | ISSUED | STEEL TONE CONSTRUCTION | 12/20/2016 |
| BIS | PL | ISSUED | SO PLUMBING & HEATING INC | 12/20/2016 |
| BIS | EQ | ISSUED | HKS CONSTRUCTION CORP | 09/12/2016 |
| BIS | OT | ISSUED | EURO T.I. INC | 08/10/2016 |
| BIS | OT | ISSUED | CITYLINE RESTORATION INC | 02/19/2016 |
| BIS | OT | ISSUED | CITYLINE RESTORATION INC | 12/18/2015 |
| BIS | OT | ISSUED | HH BUILDING CONSULTING & | 08/20/2015 |
| BIS | EQ | ISSUED | HKS CONSTRUCTION CORP | 07/21/2015 |
| BIS | BL | ISSUED | G. BAUER, INC | 01/02/2015 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/16/2024 | Structural Stability – Alterations of existing buildings | TREVOR O. FLOWERS | special |
| 11/16/2024 | Post-installed Anchors | TREVOR O. FLOWERS | special |
| 09/10/2024 | Tenant Protection Plan Compliance | Withdrawn | special |
| 09/10/2024 | Post-installed Anchors | RICHARD KOENIGSBERG | special |
| 09/10/2024 | Final | RICHARD KOENIGSBERG | progress |
| 09/10/2024 | Structural Stability – Alterations of existing buildings | RICHARD KOENIGSBERG | special |
| 09/10/2024 | Masonry | RICHARD KOENIGSBERG | special |
| 04/06/2021 | Energy Code Compliance Inspections | JAMES MOORE | progress |
| 04/06/2021 | Fire-Resistant Penetrations and Joints | JAMES MOORE | special |
| 04/06/2021 | HVAC insulation and sealing | JAMES MOORE | energy_progress |
| 03/30/2021 | Fire-Resistant Penetrations and Joints | JAMES MOORE | special |
| 03/30/2021 | Energy Code Compliance Inspections | JAMES MOORE | progress |
| 03/30/2021 | HVAC insulation and sealing | JAMES MOORE | energy_progress |
| 01/21/2021 | Fire-Resistant Penetrations and Joints | JAMES MOORE | special |
| 01/21/2021 | Energy Code Compliance Inspections | JAMES MOORE | progress |
| 01/21/2021 | HVAC insulation and sealing | JAMES MOORE | energy_progress |