| Firm | Filings | Most Recent |
|---|---|---|
| Stanley M. Krebushevski, R.A | 3 | 11/01/2022 |
| William Montague Engineering | 3 | 08/30/2022 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Oak Developers | Scaffold | 9 | 07/08/2026 |
| Oak Developers | General Contractor | 7 | 07/08/2026 |
| JB Buzco Plumbing | Plumbing | 3 | 07/08/2026 |
| Quality Plumbing | Plumbing | 1 | 07/08/2026 |
| Rightway Plumbing & Heating | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SRA Planning & Expediting | 5677 | 3 | 11/01/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | Oak Developers | 09/28/2022 |
| DOB NOW | Plumbing | Signed-off | JB Buzco Plumbing | 09/27/2022 |
| DOB NOW | Sprinklers | Signed-off | Rightway Plumbing & Heating | 09/06/2022 |
| DOB NOW | Plumbing | Signed-off | JB Buzco Plumbing | 08/26/2022 |
| DOB NOW | Construction Fence | Signed-off | Oak Developers | 05/11/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | Oak Developers | 05/11/2022 |
| DOB NOW | Plumbing | Signed-off | Quality Plumbing | 10/20/2021 |
| DOB NOW | Foundation | Permit Issued | Oak Developers | 09/27/2021 |
| DOB NOW | Construction Fence | Signed-off | Oak Developers | 09/27/2021 |
| DOB NOW | Plumbing | Signed-off | JB Buzco Plumbing | 09/13/2021 |
| DOB NOW | Foundation | Permit Issued | Oak Developers | 08/25/2021 |
| DOB NOW | Construction Fence | Signed-off | Oak Developers | 08/03/2021 |
| DOB NOW | Construction Fence | Signed-off | Oak Developers | 05/24/2021 |
| DOB NOW | Construction Fence | Signed-off | Oak Developers | 04/15/2021 |
| BIS | OT | ISSUED | Sunrun Installation Service | 08/26/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/01/2022 | Permit Issued | Oak Developers | Air Conditioning Systems, Heating Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/01/2022 | Signed-off | JB Buzco Plumbing | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/24/2022 | Complete | Ridge Electric | General Wiring |
| 08/29/2022 | Complete | Sunrun Solar Electl | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/01/2022 | Signed-off | JB Buzco Plumbing | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/01/2022 | Signed-off | JB Buzco Plumbing | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/31/2022 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/31/2022 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 10/11/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/27/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/26/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 09/12/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/21/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/21/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/26/2021 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 10/25/2021 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 09/24/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/10/2022 | Fenestration and door U-factor and product ratings | WILLIAM MONTAGUE | energy_progress |
| 11/10/2022 | Subsurface Investigations (Borings/Test Pits) | WILLIAM MONTAGUE | special |
| 11/10/2022 | Structural Steel - High Strength Bolting | WILLIAM MONTAGUE | special |
| 11/10/2022 | Subgrade Inspections | WILLIAM MONTAGUE | special |
| 11/10/2022 | Concrete - Cast-In-Place | WILLIAM MONTAGUE | special |
| 11/10/2022 | Mechanical Systems | WILLIAM MONTAGUE | special |
| 11/10/2022 | Fire-Resistant Penetrations and Joints | WILLIAM MONTAGUE | special |
| 11/10/2022 | Fire-Resistance Rated Construction | WILLIAM MONTAGUE | progress |
| 11/10/2022 | Final | WILLIAM MONTAGUE | progress |
| 11/10/2022 | Energy Code Compliance Inspections | WILLIAM MONTAGUE | progress |
| 11/10/2022 | Footing and Foundation | WILLIAM MONTAGUE | progress |
| 11/10/2022 | Structural Wood Frame | WILLIAM MONTAGUE | progress |
| 11/10/2022 | Permanent certificate | WILLIAM MONTAGUE | energy_progress |
| 11/10/2022 | Air barrier - visual inspection | WILLIAM MONTAGUE | energy_progress |
| 11/10/2022 | Insulation placement and R values | WILLIAM MONTAGUE | energy_progress |
| 11/10/2022 | Fenestration areas | WILLIAM MONTAGUE | energy_progress |
| 11/10/2022 | HVAC-R and service water heating system controls | WILLIAM MONTAGUE | energy_progress |
| 11/10/2022 | Interior lighting power | WILLIAM MONTAGUE | energy_progress |
| 11/10/2022 | Ventilation and air distribution system | WILLIAM MONTAGUE | energy_progress |
| 11/10/2022 | HVAC-R and service water heating equipment | WILLIAM MONTAGUE | energy_progress |
| 11/10/2022 | Duct leakage testing, insulation and design | WILLIAM MONTAGUE | energy_progress |
| 11/10/2022 | Metering | WILLIAM MONTAGUE | energy_progress |
| 11/10/2022 | HVAC-R and service water piping design and insulation | WILLIAM MONTAGUE | energy_progress |
| 11/10/2022 | Maintenance information | WILLIAM MONTAGUE | energy_progress |
| 11/10/2022 | Air barrier — testing | WILLIAM MONTAGUE | energy_progress |