← Back
Public elementary, junior or senior high
I.S. 141 The Steinway
37-11 21 AVENUE · Astoria (North)-Ditmars-Steinway · BIN 4016102
💬 Discuss this project
1931Year Built
4Stories
W1Building Class
R5BZoning
122,134 sfGross Floor Area
0Units
LL97 Covered4 Open Violations 1 unresolved · 3 paperwork only ▸
Public elementary, junior or senior high · Owner of record: NYC DEPARTMENT OF EDUCATION · 51,811 sf lot · 2.36 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanicalPlumbingGeneralOther
Floor 11 filing · 15 docs
Cellar5p · 1 filing · 19 docs
Filed — no permit issued29p · 2 filings · 11 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NY SCHOOL CONSTRUCTION AUTHORITY1403/21/2026
SCHOOL CONSTRUCTION AUTHORITY1203/21/2026
NYC SCHOOL CONSTRUCTION AUTHORITY1107/08/2026
DEPARTMENT OF EDUCATION DSF503/21/2026
NYC SCHOOL CONSTRUCTION403/21/2026
NYC SCHOOL CONST AUTHORITY203/21/2026
DDC203/21/2026
NYC DEPARTMENT OF EDUCATION103/22/2026
NYC SCHOOL CONSTRUC AUTH103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CPL ARCHITECTURE ENGINEERING AND PL411/20/2025
EME GROUP/SALAS O'BRIEN108/22/2024
GREENMAN-PEDERSEN, INC.210/19/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CPL ARCHITECTURE403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RAZALINE BUILDERS INCGeneral Contractor504/09/2026
SAI JI PLUMBING INCGeneral Contractor403/21/2026
SAI JI PLUMBING, INCPlumbing207/08/2026
CARUSO, VElectrical103/21/2026
DUARTE, LUIGIElectrical103/21/2026
GENE HUMPHREYSElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
UNIVERSAL TESTING AND INS400411/20/2025
KS ENGINEERS, P.C.7715203/06/2025
Building Lifecycle
All (119)Filed (7)Permit Issued (7)Signed Off (2)Violation (60)Inspection (2)Objection (14)Special Inspection (27)
06/05/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
03/04/2026
Violation issued (ECB, open)
Construction
03/04/2026
Violation issued (ECB, open)
Construction
01/13/2026
Objection resolved — Addressed
01/13/2026
Objection resolved — Addressed
12/22/2025
Permit issued — Mechanical Systems
Q00971186-I1-GC
12/01/2025
Objection raised — Other
12/01/2025
Objection raised — Other
11/20/2025
Filed — Alteration
Replace existing fixed audience seating and provide new ADA seats. Replace exist tile flooring and paint floor. Modify stage platform and stair to install a new permanent WC lift. Provide new chase to accommodate new drinking fountains support.
Q01318901-I1
11/20/2025
Filed — Alteration
Replace existing fixed audience seating and provide new ADA seats. Replace exist tile flooring and paint floor. Modify stage platform and stair to install a new permanent WC lift. Provide new chase to accommodate new drinking fountains support.
Q01318901-S1
11/13/2025
Special inspection requirement — Masonry
NELSON LOPEZ
11/13/2025
Special inspection requirement — Structural Steel - Details
NELSON LOPEZ
11/13/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
NELSON LOPEZ
11/13/2025
Special inspection requirement — Concrete - Cast-In-Place
NELSON LOPEZ
11/13/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
NELSON LOPEZ
11/13/2025
Special inspection requirement — Post-installed Anchors
NELSON LOPEZ
11/13/2025
Special inspection requirement — Structural Steel - Welding
NELSON LOPEZ
11/13/2025
Special inspection requirement — Sprayed fire-resistant materials
NELSON LOPEZ
11/13/2025
Special inspection requirement — Final
NELSON LOPEZ
10/20/2025
Violation issued (ECB, open)
Construction
09/30/2025
Permit issued — Mechanical Systems
Q00971186-I1-GC
05/19/2025
Signed off — Alteration
Q00603880-I1
05/15/2025
Signed off — Alteration
Q00603880-S1
03/19/2025
Permit issued — Mechanical Systems
Q00971186-I1-GC
03/06/2025
Filed — Alteration
Remove and replace ceilings. Paint concrete ceilings.
Q00971186-P1
03/06/2025
Special inspection requirement — Lighting controls
Mohamed Shahid
03/06/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mohamed Shahid
03/06/2025
Special inspection requirement — Mechanical Systems
Mohamed Shahid
03/06/2025
Special inspection requirement — Post-installed Anchors
Mohamed Shahid
03/06/2025
Special inspection requirement — Energy Code Compliance Inspections
Mohamed Shahid
03/06/2025
Special inspection requirement — Final
Mohamed Shahid
03/06/2025
Special inspection requirement — Maintenance information
Mohamed Shahid
03/06/2025
Special inspection requirement — Interior lighting power
Mohamed Shahid
11/18/2024
Objection resolved — Addressed
10/25/2024
Objection resolved — Addressed
09/30/2024
Objection resolved — Addressed
09/26/2024
Objection raised — Other
09/19/2024
Objection resolved — Addressed
09/19/2024
Objection resolved — Addressed
09/08/2024
Objection raised — Other
09/04/2024
Objection raised — Other
09/04/2024
Objection raised — Other
09/04/2024
Objection raised — Other
08/22/2024
Filed — Alteration
Q01099813-I1
08/21/2024
Special inspection requirement — Final
08/21/2024
Special inspection requirement — Air barrier - visual inspection
08/21/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
08/21/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
08/21/2024
Special inspection requirement — Energy Code Compliance Inspections
07/17/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/27/2024
Violation issued (ECB, closed)
Construction
12/28/2023
Filed — Alteration
Remove and replace ceilings. Paint concrete ceilings.
Q00971186-I1
11/09/2023
Permit issued — Mechanical Systems
Q00603880-S1-MS
11/09/2023
Permit issued — Plumbing
Q00603880-I1-PL
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/14/2022
Permit issued — Plumbing
Q00603880-I1-PL
11/14/2022
Permit issued — Mechanical Systems
Q00603880-S1-MS
10/19/2021
Filed — Alteration
Q00603880-S1
Latest 60 of 119 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedRAZALINE BUILDERS INC12/22/2025
DOB NOWMechanical SystemsPermit IssuedRAZALINE BUILDERS INC09/30/2025
DOB NOWMechanical SystemsPermit IssuedRAZALINE BUILDERS INC03/19/2025
DOB NOWMechanical SystemsSigned-offSAI JI PLUMBING INC11/09/2023
DOB NOWPlumbingSigned-offSAI JI PLUMBING, INC11/09/2023
DOB NOWPlumbingSigned-offSAI JI PLUMBING, INC11/14/2022
DOB NOWMechanical SystemsSigned-offSAI JI PLUMBING INC11/14/2022
BISMHISSUEDACS SYSTEM ASSOCIATES INC.03/10/2016
BISOTISSUEDLIU ELECTRIC LLC08/20/2015
BISOTISSUEDBRI-DEN CONSTRUCTION CO04/20/2015
BISOTISSUEDBRI-DEN CONSTRUCTION CO04/20/2015
BISPLISSUEDFORSYTHE P&H CORP09/23/2014
BISMHISSUEDACS SYSTEM ASSOCIATES INC.09/23/2014
BISOTISSUEDBRI-DEN CONSTRUCTION CO09/02/2014
BISOTISSUEDBRI-DEN CONSTRUCTION CO09/02/2014
BISOTISSUEDBRI-DEN CONSTRUCTION CO09/02/2014
BISOTISSUEDBRI-DEN CONSTRUCTION CO04/04/2013
BISOTISSUEDBRI-DEN CONSTRUCTION CO04/04/2013
BISMHISSUEDACS SYSTEM ASSOCIATES INC.03/15/2013
BISMHISSUEDACS SYSTEM ASSOCIATES INC.05/30/2012
BISPLISSUEDFORSYTHE P&H CORP05/01/2012
BISOTISSUEDBRI-DEN CONSTRUCTION CO04/27/2012
BISOTISSUEDBRI-DEN CONSTRUCTION CO04/27/2012
BISEQISSUEDBRI-DEN CONSTRUCTION CO04/02/2012
BISEQISSUEDBRI-DEN CONSTRUCTION CO03/30/2012
BISEQISSUEDBRI-DEN CONSTRUCTION CO03/30/2012
BISEQISSUEDBRI-DEN CONSTRUCTION CO03/30/2012
BISEQISSUEDBRI-DEN CONSTRUCTION CO03/06/2012
BISEQISSUEDBRI-DEN CONSTRUCTION CO03/06/2012
BISEQISSUEDBRI-DEN CONSTRUCTION CO03/06/2012
BISEQISSUEDBRI-DEN CONSTRUCTION CO03/06/2012
BISEQISSUEDBRI-DEN CONSTRUCTION CO08/23/2011
BISOTISSUEDLLF CONST SVCS INC (SCA)08/05/2011
BISPLISSUEDFORSYTHE P&H CORP05/05/2011
BISEQISSUEDBRI-DEN CONSTRUCTION CO03/24/2011
BISEQRE-ISSUEDBRI-DEN CONSTRUCTION CO03/09/2011
BISEQISSUEDBRI-DEN CONSTRUCTION CO03/09/2011
BISEQISSUEDCHAMPION CONTRUCTION CORP02/25/2011
BISEQISSUEDBRI-DEN CONSTRUCTION CO02/04/2011
BISEQISSUEDBRI-DEN CONSTRUCTION CO02/04/2011
+ 17 more permits on file
1 project · most recent 11/20/2025
Water/Sanitary
FiledStatusContractorScope
11/20/2025——Water/Sanitary
17 projects · most recent 05/26/2026
General Wiring Lighting
FiledStatusContractorScope
05/26/2026Permit IssuedVIAL ELECTRIC & COMPANYLighting
03/27/2026Permit IssuedVIAL ELECTRIC & COMPANYLighting
10/20/2025CompleteGEMINI ELECTRIC CO., INC.—
05/16/2025CompleteCHARAN ELEC'L ENTERP'S IN—
04/28/2025CompleteGEMINI ELECTRIC CO., INC.—
02/19/2025CompleteJAMES F. VOLPE ELEC'LGeneral Wiring
09/15/2024CompleteLIU ELECTRIC, LLC—
04/08/2024Permit IssuedBARBARO ELECT CO.INCGeneral Wiring
12/01/2023Permit IssuedA & S ELECTRIC INC.General Wiring
01/23/2023CompleteABM ELECTRIC, INC—
12/27/2022CompleteCHARAN ELEC'L ENTERP'S IN—
06/11/2021CompleteTRIBECA ELECTRICAL CORPGeneral Wiring
09/16/2020CompleteCHARAN ELEC'L ENTERP'S IN—
06/16/2020Permit IssuedGEMINI ELECTRIC CO., INC.General Wiring
06/05/2020CompleteCHARAN ELEC'L ENTERP'S IN—
1 project · most recent 11/20/2025
Steel Concrete Masonry
FiledStatusContractorScope
11/20/2025——Steel, Concrete, Masonry
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
06/05/2026Pass-Final General Construction Non-Directive 14PassView ↗
07/17/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 27
DateRequirementInspectorRole
11/13/2025MasonryNELSON LOPEZspecial
11/13/2025Structural Steel - DetailsNELSON LOPEZspecial
11/13/2025Structural Stability – Alterations of existing buildingsNELSON LOPEZspecial
11/13/2025Concrete - Cast-In-PlaceNELSON LOPEZspecial
11/13/2025Fire-Resistant Penetrations and JointsNELSON LOPEZspecial
11/13/2025Post-installed AnchorsNELSON LOPEZspecial
11/13/2025Structural Steel - WeldingNELSON LOPEZspecial
11/13/2025Sprayed fire-resistant materialsNELSON LOPEZspecial
11/13/2025FinalNELSON LOPEZprogress
03/06/2025Lighting controlsMohamed Shahidenergy_progress
03/06/2025Fire-Resistant Penetrations and JointsMohamed Shahidspecial
03/06/2025Mechanical SystemsMohamed Shahidspecial
03/06/2025Post-installed AnchorsMohamed Shahidspecial
03/06/2025Energy Code Compliance InspectionsMohamed Shahidprogress
03/06/2025FinalMohamed Shahidprogress
03/06/2025Maintenance informationMohamed Shahidenergy_progress
03/06/2025Interior lighting powerMohamed Shahidenergy_progress
08/21/2024Final—progress
08/21/2024Air barrier - visual inspection—energy_progress
08/21/2024Fire-Resistant Penetrations and Joints—special
08/21/2024Structural Stability – Alterations of existing buildings—special
08/21/2024Energy Code Compliance Inspections—progress
10/05/2021HVAC-R and service water piping design and insulationNELSON LOPEZenergy_progress
10/05/2021HVAC-R and service water heating system controlsNELSON LOPEZenergy_progress
10/05/2021HVAC-R and service water heating equipmentNELSON LOPEZenergy_progress
Latest 25 of 27.
▾Documents — 70 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/27/2026Q00603880-S1Request digital key ↗
08/27/2026Q00603880-I1Request digital key ↗
08/21/2026Q01099813-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION2
06/05/2019440550798Open ↗
06/03/2019440542584Open ↗
▸Seals & Professional Certifications20
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/27/2026Q00603880-I1Open ↗
08/27/2026Q00603880-S1Open ↗
08/21/2026Q01099813-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/01/2026Q01318901-I1Open ↗
08/29/2026Q00971186-P1Open ↗
08/29/2026Q00971186-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/01/2026Q01318901-I1Open ↗
08/29/2026Q00971186-P1Open ↗
08/28/2026Q00603880-I1Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
06/05/2019440550798Open ↗
06/03/2019440542584Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
06/05/2019440550798Open ↗
06/03/2019440542584Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
06/05/2019440550798Open ↗
06/03/2019440542584Open ↗
▸Environmental & Asbestos5
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)2
06/05/2019440550798Open ↗
06/03/2019440542584Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/27/2026Q00603880-S1Open ↗
08/27/2026Q00603880-I1Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/20/2026Q00971186-I1Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
06/05/2019440550798Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
06/05/2019440550798Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026Q00603880-I1Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
06/05/2019440550798Open ↗
06/03/2019440542584Open ↗
▸Approvals, Objections & Sign-offs19
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter7
08/27/2026Q00603880-I1Open ↗
08/27/2026Q00603880-S1Open ↗
08/20/2026Q00971186-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)7
08/13/2026Q01318901-I1Open ↗
08/13/2026Q00603880-S1Open ↗
08/13/2026Q01099813-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)3
08/13/2026Q00603880-I1Open ↗
08/13/2026Q01318901-I1Open ↗
08/13/2026Q00603880-S1Open ↗
▸BISDESIGN COMM. APPROVAL: CITY-OWNED PROPERTY (EXTERIOR WORK)2
06/05/2019440550798Open ↗
06/03/2019440542584Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
06/05/2019440550798Open ↗
06/03/2019440542584Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET2
06/05/2019440550798Open ↗
06/03/2019440542584Open ↗
▸Other Documents8
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal6
08/13/2026Q00971186-P1Open ↗
08/13/2026Q00603880-I1Open ↗
08/13/2026Q00603880-S1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWNYCSCA Exhibit 22
08/13/2026Q00603880-S1Open ↗
08/13/2026Q00603880-I1Open ↗