| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/05/2022 | Signed-off | CC CONTROLLED PLBG CO.,IN | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/09/2025 | Permit Issued | BRUNI ELECTRIC INC | General Wiring |
| 04/24/2023 | Complete | VOLTAGE ELECTRIC CORP | — |
| 09/26/2022 | Complete | VOLTAGE ELECTRIC CORP | — |
| 07/28/2022 | Complete | VOLTAGE ELECTRIC CORP | — |
| 07/27/2022 | Complete | VOLTAGE ELECTRIC CORP | — |
| 06/09/2019 | Complete | VOLTAGE ELECTRIC CORP | General Wiring |
| 01/16/2019 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| Owner | Filings | Most Recent |
|---|---|---|
| JERRICK ASSOCIATES | 15 | 07/08/2026 |
| TIME EQUITIES | 30 | 07/08/2026 |
| 37-24TH ST EQUITIES LLC | 4 | 03/22/2026 |
| 37-24 STREET LLC | 1 | 03/22/2026 |
| FLORA CO | 1 | 03/22/2026 |
| IRON OAKS LLC | 1 | 03/22/2026 |
| 37-24 24TH STREET EQUITIES | 6 | 03/21/2026 |
| 34-24 24TH ST EQUITIES | 4 | 03/21/2026 |
| TC EQUITIES HOLDING | 8 | 03/21/2026 |
| 37-24 24TH STREET | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ERIC ETTINGER | 1 | 06/17/2026 |
| PAUL PERDEK, PROF. ENG. PLLC | 3 | 03/06/2024 |
| SOLOMON ROSENZWEIG P.E P.C. | 1 | 01/22/2024 |
| HIGH LINE ENGINEERING PC | 6 | 12/05/2022 |
| BAILEYS ENGINEERING PC | 1 | 01/21/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 8 | 03/21/2026 |
| TIME EQUITIES | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JERRICK ASSOCIATES INC | General Contractor | 8 | 07/08/2026 |
| GREGORY PAPANTONIOU | Electrical | 2 | 03/21/2026 |
| CC CONTROLLED PLBG CO.,IN | Plumbing | 2 | 07/08/2026 |
| C C CONTROLLED COMBUSTION | General Contractor | 1 | 07/08/2026 |
| BRUNI ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| CC CONTROLLED PLBG CO INC | Plumbing | 1 | 07/08/2026 |
| HARRIS WTR MAIN & SWR CON | Plumbing | 1 | 09/16/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ETTINGER COMMISSIONING IN | 7384 | 1 | 06/17/2026 |
| SOLOMON ROSENZWEIG P.E. P | 1801 | 1 | 01/22/2024 |
| HIGH LINE ENGINEERING PC | 2920 | 2 | 07/08/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | HARRIS WTR MAIN & SWR CON | 09/15/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | GE 2A CONSTRUCTION | 02/06/2025 |
| DOB NOW | Structural | Signed-off | GE 2A CONSTRUCTION | 03/01/2024 |
| DOB NOW | Supported Scaffold | Signed-off | GE 2A CONSTRUCTION | 02/21/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | GE 2A CONSTRUCTION | 02/09/2024 |
| DOB NOW | Plumbing | Signed-off | CC CONTROLLED PLBG CO.,IN | 12/13/2022 |
| DOB NOW | Plumbing | Signed-off | CC CONTROLLED PLBG CO.,IN | 03/03/2022 |
| DOB NOW | Plumbing | Signed-off | CC CONTROLLED PLBG CO INC | 04/06/2021 |
| DOB NOW | Mechanical Systems | Signed-off | C C CONTROLLED COMBUSTION | 08/11/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | GE 2A CONSTRUCTION | 01/22/2019 |
| BIS | MH | ISSUED | NKG CONTRACTING INC | 05/20/2019 |
| BIS | PL | ISSUED | C.W.C. FIRE SUPPRESSION | 09/15/2016 |
| BIS | OT | ISSUED | BEDNARZ CONSTRUCTION LLC | 07/13/2016 |
| BIS | OT | ISSUED | LC CON INC | 05/06/2016 |
| BIS | PL | ISSUED | ARIANA CONTRACTING INC | 07/16/2015 |
| BIS | OT | ISSUED | GALCO CONTRACTING INC | 06/09/2015 |
| BIS | OT | ISSUED | GALCO CONTRACTING INC | 06/09/2015 |
| BIS | OT | ISSUED | CONPERM CORP | 08/29/2014 |
| BIS | OT | ISSUED | C C CONTROLLED COMBUSTION | 01/13/2014 |
| BIS | OT | ISSUED | JERRICK ASSOCIATES INC | 08/14/2012 |
| BIS | OT | ISSUED | CONPERM CORP | 07/08/2011 |
| BIS | — | ISSUED | CONPERM CORP | 09/14/2009 |
| BIS | — | ISSUED | CONPERM CORP | 08/21/2009 |
| BIS | SP | ISSUED | HEADS UP FIRE SPRINKLER | 03/20/2007 |
| BIS | PL | ISSUED | ADVANTAGE PLBG & MECH.COR | 03/07/2007 |
| BIS | OT | ISSUED | CONPERM CORP | 11/09/2006 |
| BIS | MH | ISSUED | CONPERM CORP | 05/11/2006 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/09/2021 | Mechanical Systems | Ruslan Nagorny | special |
| 07/09/2021 | Fire-Resistant Penetrations and Joints | Ruslan Nagorny | special |
| 07/09/2021 | Final | Ruslan Nagorny | progress |
| 07/09/2021 | Maintenance information | Ruslan Nagorny | energy_progress |
| 07/09/2021 | HVAC and service water heating system controls | Ruslan Nagorny | energy_progress |
| 07/09/2021 | HVAC insulation and sealing | Ruslan Nagorny | energy_progress |
| 07/09/2021 | HVAC and service water heating equipment | Ruslan Nagorny | energy_progress |
| 06/04/2021 | Fire-Resistant Penetrations and Joints | Ruslan Nagorny | special |
| 06/04/2021 | Mechanical Systems | Ruslan Nagorny | special |
| 06/04/2021 | Final | Ruslan Nagorny | progress |
| 06/04/2021 | HVAC insulation and sealing | Ruslan Nagorny | energy_progress |
| 06/04/2021 | HVAC and service water heating equipment | Ruslan Nagorny | energy_progress |
| 06/04/2021 | Maintenance information | Ruslan Nagorny | energy_progress |
| 06/04/2021 | HVAC and service water heating system controls | Ruslan Nagorny | energy_progress |