| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/20/2021 | $1.2M | — | Private party → Private party | $534/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| JX FLAME SOLUTION INC | 5 | 01/12/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| DY EXPEDITING | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DAYS SERVICE GROUP LLC | General Contractor | 6 | 03/21/2026 |
| CROSSFIELD PLBG.&HTG | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JX FLAME SOLUTION INC | 7286 | 3 | 01/12/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | DAYS SERVICE GROUP LLC | 01/26/2022 |
| DOB NOW | Plumbing | Permit Issued | CROSSFIELD PLBG.&HTG | 06/29/2021 |
| DOB NOW | Plumbing | Permit Issued | CROSSFIELD PLBG.&HTG | 06/21/2021 |
| DOB NOW | General Construction | Signed-off | DAYS SERVICE GROUP LLC | 06/17/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/10/2021 | Permit Issued | CROSSFIELD P & H CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/24/2020 | Complete | ANTONIO CERIELLO ELEC INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/28/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 01/03/2022 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 12/01/2021 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 10/27/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/20/2021 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/20/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/20/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/18/2021 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/13/2022 | Fenestration areas | JIE ZHU | energy_progress |
| 01/13/2022 | Energy Code Compliance Inspections | JIE ZHU | progress |
| 01/13/2022 | Fire-Resistance Rated Construction | JIE ZHU | progress |
| 01/13/2022 | Fire-Resistant Penetrations and Joints | JIE ZHU | special |
| 01/13/2022 | Fenestration and door U-factor and product ratings | JIE ZHU | energy_progress |
| 01/13/2022 | Fenestration air leakage | JIE ZHU | energy_progress |
| 01/13/2022 | Insulation placement and R values | JIE ZHU | energy_progress |
| 01/13/2022 | HVAC-R and service water piping design and insulation | JIE ZHU | energy_progress |
| 08/12/2021 | Energy Code Compliance Inspections | JIE ZHU | progress |
| 08/12/2021 | HVAC-R and service water piping design and insulation | JIE ZHU | energy_progress |
| 08/12/2021 | HVAC-R and service water heating system controls | JIE ZHU | energy_progress |
| 08/12/2021 | HVAC-R and service water heating equipment | JIE ZHU | energy_progress |
| 08/10/2021 | HVAC-R and service water piping design and insulation | JIE ZHU | energy_progress |
| 08/10/2021 | Fenestration areas | JIE ZHU | energy_progress |
| 08/10/2021 | Fenestration air leakage | JIE ZHU | energy_progress |
| 08/10/2021 | Fenestration and door U-factor and product ratings | JIE ZHU | energy_progress |
| 08/10/2021 | Insulation placement and R values | JIE ZHU | energy_progress |
| 08/10/2021 | Fire-Resistance Rated Construction | JIE ZHU | progress |
| 08/10/2021 | Energy Code Compliance Inspections | JIE ZHU | progress |
| 08/10/2021 | Fire-Resistant Penetrations and Joints | JIE ZHU | special |