| Firm | Filings | Most Recent |
|---|---|---|
| JAMES V MORRI | 3 | 10/29/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| JAMES V MORRI, RA | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JACOBSON CONTRACTING,INC | General Contractor | 2 | 03/21/2026 |
| LMS ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| ALISON PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JAMES V MORRI, RA | 1042 | 2 | 10/29/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | ALISON PLBG & HTG INC | 02/07/2024 |
| DOB NOW | General Construction | Signed-off | JACOBSON CONTRACTING,INC | 10/19/2023 |
| BIS | OT | ISSUED | ALBA INC | 02/28/2011 |
| BIS | PL | ISSUED | JFR CONSTRUCTION CORP | 02/25/2011 |
| BIS | PL | ISSUED | JFR CONSTRUCTION CORP | 12/29/2009 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/15/2023 | Complete | LMS ELECTRICAL CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/30/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 09/30/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 09/26/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/05/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/15/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 02/15/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/30/2024 | Final | James Morri | progress |
| 10/30/2024 | Fenestration air leakage | James Morri | energy_progress |
| 10/30/2024 | Fire-Resistant Penetrations and Joints | James Morri | special |
| 10/30/2024 | Structural Wood Frame | James Morri | progress |
| 10/30/2024 | Fire-Resistance Rated Construction | James Morri | progress |
| 10/30/2024 | Preliminary | James Morri | progress |
| 10/30/2024 | Energy Code Compliance Inspections | James Morri | progress |
| 10/30/2024 | Air barrier - visual inspection | James Morri | energy_progress |
| 10/30/2024 | Permanent certificate | James Morri | energy_progress |
| 10/30/2024 | Lighting in dwelling units | James Morri | energy_progress |
| 10/30/2024 | Fenestration areas | James Morri | energy_progress |
| 10/30/2024 | Lighting controls | James Morri | energy_progress |
| 10/30/2024 | Maintenance information | James Morri | energy_progress |
| 10/30/2024 | Insulation placement and R values | James Morri | energy_progress |
| 10/30/2024 | Fenestration and door U-factor and product ratings | James Morri | energy_progress |
| 10/09/2024 | Fire-Resistant Penetrations and Joints | James Morri | special |
| 10/09/2024 | Energy Code Compliance Inspections | James Morri | progress |
| 10/09/2024 | Final | James Morri | progress |
| 10/09/2024 | Fire-Resistance Rated Construction | James Morri | progress |
| 10/09/2024 | Preliminary | James Morri | progress |
| 10/09/2024 | Structural Wood Frame | James Morri | progress |
| 10/09/2024 | Air barrier - visual inspection | James Morri | energy_progress |
| 10/09/2024 | Fenestration air leakage | James Morri | energy_progress |
| 10/09/2024 | Fenestration and door U-factor and product ratings | James Morri | energy_progress |
| 10/09/2024 | Insulation placement and R values | James Morri | energy_progress |