MANHATTAN · Greenwich Village · BIN 1077930
💬 Discuss this project
1961Year Built
13Stories
D4Building Class
C6-2Zoning
235,875 sfGross Floor Area
105Units
LL97 CoveredRent Stabilized18 Open Violations 15 unresolved · 3 paperwork only ▸FISP: SAFE
Elevator cooperative · Owner of record: BUTTERFIELD HOUSE INC-B.H.S.(37120) · 29,110 sf lot · 8.1 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentLandscapeCivilGeneral
Permit Issued — active, not yet Signed-off
Roof8p · 2 filings · 20 docs
Floor 124p · 2 filings · 17 docs
Floor 1123p · 2 filings · 20 docs
Floor 10Under Construction10p · 3 filings · 20 docs
Floor 9
Floor 8
Floor 7
Floor 63p · 1 filing · 7 docs
Floor 5
Floor 411p · 1 filing · 12 docs
Floor 3Under Construction16p · 5 filings · 20 docs
Floor 29p · 3 filings · 20 docs
Floor 1
Cellar4p · 1 filing · 14 docs
Site & exterior13p · 3 filings · 7 docs
Filed — no permit issued5p · 1 filing · 10 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BUTTERFIELD1803/21/2026
145 EAST 15TH STREET TENANTS807/08/2026
CEPRINE CONSTRUCTION807/08/2026
KINGS GROUP NY CORP703/22/2026
BROWN HARRIS STEVENS603/21/2026
HH BUILDING CONSULTANTS503/22/2026
DOUGLAS ELLIMAN PROPERTY MGMT203/21/2026
BUTTERFIELD HOUSE INC-B.H.S.(37120)103/22/2026
WARD103/21/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SYNERGY BUILDING CONSULTANTS203/21/2026
BURNHAM NATIONWIDE INC303/21/2026
J CALLAHAN CONSULTING203/21/2026
CODE603/21/2026
WALTER T GORMAN PE203/21/2026
MUNICIPAL BUILDING CONSULTANTS503/21/2026
AGOUTI CONSTRUCTION CONSULTING403/21/2026
J A EXPEDITING403/21/2026
LEWSAN CONSULTING403/21/2026
DYNAMIC BUILDING CONSULTANTS603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KINGS GROUP NY CORPGeneral Contractor603/21/2026
KROPAN CORPGeneral Contractor603/21/2026
INTERIOR MASTERS GROUP OFGeneral Contractor407/08/2026
ASA BUILDING MAINT INCGeneral Contractor403/21/2026
CEPRINE CONSTRUCTION INCGeneral Contractor407/08/2026
PASR CORPGeneral Contractor407/08/2026
H.K. MECHANICAL SVC CORPPlumbing207/08/2026
LEGACY PLUMBING & HTG LLCPlumbing203/22/2026
AUTHENTIC PLBG CORPPlumbing207/08/2026
CRYSTAL COMFORT INCGeneral Contractor203/21/2026
SETANTA INCGeneral Contractor207/08/2026
AMERICAN STANDARD P&H CORORP.Plumbing207/08/2026
CENTERLINE GROUP LLCGeneral Contractor207/08/2026
POFI CONSTRUCTION CORPGeneral Contractor203/21/2026
SPIRO SINANISElectrical103/21/2026
DRURY & LANE LLCGeneral Contractor107/08/2026
INTER-NOVA CONTRACTING CORPGeneral Contractor107/08/2026
NEW YORK FLOORMAN, LLCGeneral Contractor107/08/2026
RJ INTERIORS CORPGeneral Contractor107/08/2026
SIGNATURE CONSTRUCTION GROUPGeneral Contractor103/21/2026
SOURCE CONSTRUCTION MANAGGeneral Contractor107/08/2026
AP PLUMBING & HVAC LLCPlumbing107/08/2026
BUDGET PLBG & HTG LLCPlumbing107/08/2026
STEPHEN FOY MECH SVC CORPPlumbing107/08/2026
VILLAGE P & H NY INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
RYAN SPECIAL ENGINEERING2018507/30/2026
WINTON GROUP ARCHITECTURE4343103/24/2026
WALTER T. GORMAN, P.E., P268102/06/2025
JON LIBASCI3068210/17/2024
EC SPECIAL INSPECTIONS8355210/02/2024
CROSSCHECK INSPECTION SER544209/06/2024
GROUP-S LLC5216207/30/2024
CES ENGINEERING LLC1277106/14/2024
H. A. BADER CONSULTANTS2332106/14/2024
MARCH CHADWICK, ARCHITECT2253204/30/2024
Building Lifecycle
All (230)Filed (37)Permit Issued (35)Signed Off (23)Facade (FISP) (12)Violation (31)Inspection (22)Objection (40)Special Inspection (30)
09/02/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/15/2026
Special inspection requirement — Lighting controls
William Ryan
08/15/2026
Special inspection requirement — Energy Code Compliance Inspections
William Ryan
08/15/2026
Special inspection requirement — Energy Code Compliance Inspections
William Ryan
08/15/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
William Ryan
08/15/2026
Special inspection requirement — Tenant Protection Plan Compliance
08/15/2026
Special inspection requirement — Tenant Protection Plan Compliance
William Ryan
08/15/2026
Special inspection requirement — Final
William Ryan
08/09/2026
Filed — Alteration
INTERIOR DEMO OF AN EXISTING APARTMENT.. NO CHANGE OF USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01362961-P1
08/06/2026
Special inspection requirement — Post-installed Anchors
07/30/2026
Filed — Alteration
Removal and installation of interior non bearing partitions and related finishes as per plans filed herewith. Units 3A&3B are being combined per TPPN 03-97. No change in use, egress or occupancy under this application.
M01336468-P1
07/30/2026
Filed — Alteration
Modification to existing plumbing fixtures as per plans filed herewith. No change in use, egress or occupancy under this application.
M01336641-P1
07/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
07/30/2026
Special inspection requirement — Final
NOUR JALLAD
07/29/2026
Special inspection requirement — Lighting controls
William Ryan
07/29/2026
Special inspection requirement — Tenant Protection Plan Compliance
William Ryan
07/29/2026
Special inspection requirement — Energy Code Compliance Inspections
William Ryan
07/29/2026
Special inspection requirement — Final
William Ryan
07/29/2026
Special inspection requirement — Tenant Protection Plan Compliance
07/29/2026
Special inspection requirement — Energy Code Compliance Inspections
William Ryan
07/29/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
William Ryan
07/17/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/03/2026
Permit issued — Plumbing
M01369596-S1-PL
05/27/2026
Permit issued — General Construction
M01362961-I1-GC
05/21/2026
Permit issued — General Construction
M01369596-I1-GC
05/20/2026
Permit issued — General Construction
M01336468-I1-GC
05/04/2026
Permit issued — General Construction
M01362961-I1-GC
04/16/2026
Signed off — Alteration
M01104200-I1
04/16/2026
Signed off — Alteration
PLUMBING FIXTURES INSTALLATION ON 3RD FLOOR OF RESIDENTIAL BUILDING AS PER PLANS FILED HEREWITH. NO CHGANGE TO USE, EGRESS, OR OCCUPANCY.
M01104222-I1
04/09/2026
Objection resolved — Resolved
04/09/2026
Objection resolved — Resolved
04/09/2026
Objection resolved — Resolved
04/08/2026
Objection resolved — Resolved
04/08/2026
Objection resolved — Resolved
04/08/2026
Objection resolved — Resolved
04/07/2026
Objection resolved — Resolved
04/07/2026
Objection resolved — Resolved
04/07/2026
Objection resolved — Resolved
04/07/2026
Objection resolved — Resolved
04/06/2026
Objection raised — Cost
04/06/2026
Objection raised — Scope
04/06/2026
Objection raised — Structural
04/06/2026
Objection raised — Scope
04/06/2026
Objection raised — Scope
04/06/2026
Objection raised — Scope
04/02/2026
Objection raised — Structural
04/02/2026
Objection raised — Scope
04/02/2026
Objection raised — Mechanical
04/02/2026
Objection raised — Scope
03/26/2026
Objection resolved — Resolved
03/26/2026
Objection resolved — Resolved
03/26/2026
Objection resolved — Resolved
03/24/2026
Filed — Alteration
INTERIOR RENOVATION OF APT 3D. FILED IN CONJUNCTION WITH DOB NOW PL. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
M01369596-S1
03/24/2026
Filed — Alteration
INTERIOR RENOVATION OF APT 3D. FILED IN CONJUNCTION WITH DOB NOW PL. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
M01369596-I1
03/09/2026
Permit issued — Plumbing
M01336641-I1-PL
03/06/2026
Filed — Alteration
INTERIOR DEMO OF AN EXISTING APARTMENT.. NO CHANGE OF USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01362961-I1
03/02/2026
Permit issued — General Construction
M01336468-I1-GC
02/10/2026
Objection resolved — Addressed
02/09/2026
Objection raised — Scope
02/03/2026
Objection resolved — Addressed
Latest 60 of 230 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedZONE PLUMBING & HEATING C06/03/2026
DOB NOWGeneral ConstructionPermit IssuedSETANTA INC05/27/2026
DOB NOWGeneral ConstructionPermit IssuedNEW YORK FLOORMAN, LLC05/21/2026
DOB NOWGeneral ConstructionPermit IssuedCENTERLINE GROUP LLC05/20/2026
DOB NOWGeneral ConstructionPermit IssuedSETANTA INC05/04/2026
DOB NOWPlumbingPermit IssuedVILLAGE P & H NY INC03/09/2026
DOB NOWGeneral ConstructionPermit IssuedCENTERLINE GROUP03/02/2026
DOB NOWPlumbingSigned-offAUTHENTIC PLBG CORP04/07/2025
DOB NOWGeneral ConstructionSigned-offKROPAN CORP04/02/2025
DOB NOWGeneral ConstructionSigned-offASA BUILDING MAINT03/12/2025
DOB NOWPlumbingSigned-offFOY MECH AND SONS LLC10/15/2024
DOB NOWGeneral ConstructionSigned-offDRURY LANE10/11/2024
DOB NOWPlumbingSigned-offAMERICAN STANDARD P&H CORORP.10/04/2024
DOB NOWGeneral ConstructionSigned-offKROPAN CORP09/24/2024
DOB NOWMechanical SystemsSigned-offCRYSTAL COMFORT08/19/2024
DOB NOWPlumbingSigned-offBUDGET PLBG & HTG LLC08/12/2024
DOB NOWGeneral ConstructionSigned-offRJ INTERIORS CORP08/08/2024
DOB NOWPlumbingSigned-offCROSSFIELD PLBG.&HTG07/12/2024
DOB NOWMechanical SystemsSigned-offPASR CORP07/10/2024
DOB NOWGeneral ConstructionSigned-offPASR CORP07/09/2024
DOB NOWGeneral ConstructionSigned-offINTERNOVA CONTRACTING02/06/2024
DOB NOWGeneral ConstructionSigned-offINTERIOR MASTERS GROUP OF12/08/2023
DOB NOWPlumbingSigned-offH.K. MECHANICAL SVC CORP10/17/2023
DOB NOWGeneral ConstructionSigned-offASA BUILDING MAINT08/17/2023
DOB NOWPlumbingSigned-offAUTHENTIC PLBG CORP05/02/2023
DOB NOWGeneral ConstructionSigned-offSOURCE CONSTRUCTION MANAG04/18/2023
DOB NOWPlumbingSigned-offAMERICAN STANDARD P&H CORORP.01/04/2023
DOB NOWGeneral ConstructionSigned-offSIGNATURE CONSTRUCTION GR01/04/2023
DOB NOWGeneral ConstructionSigned-offPOFI CONSTRUCTION CORP05/27/2022
DOB NOWPlumbingSigned-offH.K. MECHANICAL SVC CORP05/19/2022
DOB NOWGeneral ConstructionSigned-offINTERIOR MASTERS GROUP OF05/17/2022
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC04/22/2022
DOB NOWSupported ScaffoldSigned-offCEPRINE CONSTRUCTION INC04/22/2022
DOB NOWSidewalk ShedSigned-offKINGS GROUP NY CORP10/02/2018
DOB NOWSidewalk ShedSigned-offKINGS GROUP NY CORP02/06/2018
BISPLISSUEDAQUA PLUMBING & HTNG CORP12/06/2022
BISPLISSUEDBMV MECHANICAL CORP01/10/2021
BISOTISSUEDASA BUILDING MAINT INC11/16/2020
BISOTISSUEDASA BUILDING MAINT INC03/18/2020
BISPLISSUEDAQUA PLUMBING & HTNG CORP03/04/2020
+ 45 more permits on file
1 project · most recent 01/12/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
01/12/2026——Heating and Air Conditioning Systems
Heat / Cool
Daikin FCHH204 9,000 BTU · Vrf Indoor ×7
FCHH208 36,000 BTU · Fan Coil Indoor ×1
2 projects · most recent 07/30/2026
Water/Sanitary Gas
FiledStatusContractorScope
07/30/2026Permit IssuedPARAMOUNT SERVICES, LLCGas, Water/Sanitary
03/24/2026Permit Issued5 BORO'S PLUMBING INCWater/Sanitary
25 projects · most recent 09/03/2026
General Wiring
FiledStatusContractorScope
09/03/2026Permit IssuedAPPROVED ELECTRIC CORP.General Wiring
06/01/2026Permit IssuedVERTEX ELECTRIC CORP.General Wiring
02/19/2026Permit IssuedHI-TECH WIRING ELECL SVCSGeneral Wiring
12/16/2025Permit IssuedKJK ELECTRIC INCGeneral Wiring
08/18/2025CompleteCAVAN ELECTRIC CORP.—
08/14/2025CompleteARGON ELECTRICAL CORPGeneral Wiring
02/17/2025CompleteFUSED ELECTRIC CONTNG CORGeneral Wiring
02/13/2025CompleteINTER CONNECTION ELETRICGeneral Wiring
12/30/2024CompleteARGON ELECTRICAL CORP—
12/20/2024CompleteEUREKA ELECTRIC CONTNG COGeneral Wiring
10/10/2024CompleteBOROWIDE ELECT'L CONTR'SGeneral Wiring
10/09/2024CompleteS.E. ELECTL CONTNG CORPGeneral Wiring
10/07/2024CompleteBELMONT ELECTRICAL, INCGeneral Wiring
09/11/2024CompleteACCURATE ELEC'L CORP.—
08/14/2024CompleteJOSEPH WEINSTEIN ELECTRICGeneral Wiring
1 project · most recent 07/30/2026
Tenant Protection Plan 72 Hour
FiledStatusContractorScope
07/30/2026Permit IssuedCENTERLINE GROUP LLCTenant Protection Plan 72 Hour
▾Field Inspections (DOB CAP) — 22
DateTypeResultReport
09/02/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/17/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/18/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/18/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/13/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/28/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/25/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/20/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/20/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/10/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/12/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/07/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/21/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/13/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/20/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/17/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/13/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/12/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/16/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/09/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/09/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/09/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 75
DateRequirementInspectorRole
08/15/2026Tenant Protection Plan ComplianceWilliam Ryanspecial
08/15/2026Fire-Resistant Penetrations and JointsWilliam Ryanspecial
08/15/2026Energy Code Compliance InspectionsWilliam Ryanprogress
08/15/2026Lighting controlsWilliam Ryanenergy_progress
08/15/2026Energy Code Compliance InspectionsWilliam Ryanprogress
08/15/2026FinalWilliam Ryanprogress
08/15/2026Tenant Protection Plan Compliance—special
08/06/2026Post-installed Anchors—special
07/30/2026Fire-Resistant Penetrations and Joints—special
07/30/2026FinalNOUR JALLADprogress
07/29/2026Lighting controlsWilliam Ryanenergy_progress
07/29/2026Tenant Protection Plan ComplianceWilliam Ryanspecial
07/29/2026Energy Code Compliance InspectionsWilliam Ryanprogress
07/29/2026Energy Code Compliance InspectionsWilliam Ryanprogress
07/29/2026Tenant Protection Plan Compliance—special
07/29/2026Fire-Resistant Penetrations and JointsWilliam Ryanspecial
07/29/2026FinalWilliam Ryanprogress
12/18/2025Mechanical SystemsWilliam Ryanspecial
12/18/2025FinalWilliam Ryanprogress
12/18/2025Tenant Protection Plan ComplianceWilliam Ryanspecial
12/18/2025HVAC-R and service water piping design and insulationWilliam Ryanenergy_progress
12/18/2025HVAC-R and service water heating system controlsWilliam Ryanenergy_progress
12/18/2025HVAC-R and service water heating equipmentWilliam Ryanenergy_progress
12/18/2025Shutoff dampersWilliam Ryanenergy_progress
12/18/2025Fire-Resistance Rated ConstructionWilliam Ryanprogress
Latest 25 of 75.
▾Documents — 823 on file (BIS + DOB NOW)
▸Plans & Drawings37
▸DOB NOWPlans/Sketch37
09/06/2026M00017017-I1Request digital key ↗
09/02/2026M00698050-I1Request digital key ↗
09/02/2026M00698049-I1Request digital key ↗
Showing 3 of 37 on file for this type
▸Applications & Permits169
▸BISWORK PERMIT APPLICATION70
12/07/2022122395979Open ↗
03/18/2020102486640Open ↗
11/14/2019102486640Open ↗
Showing 3 of 70 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION68
12/09/2024104284347Open ↗
03/25/2024122838493Open ↗
11/29/2022122395979Open ↗
Showing 3 of 68 on file for this type
▸DOB NOWLPC Approval/Permit31
09/02/2026M00698050-I1Open ↗
09/02/2026M00698049-I1Open ↗
09/01/2026M08023844-I1Open ↗
Showing 3 of 31 on file for this type
▸Seals & Professional Certifications172
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION69
12/31/2019122849846Open ↗
04/18/2019123718307Open ↗
04/18/2019123718307Open ↗
Showing 3 of 69 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature37
09/06/2026M00017017-I1Open ↗
09/02/2026M00698050-I1Open ↗
09/02/2026M00698049-I1Open ↗
Showing 3 of 37 on file for this type
▸DOB NOWProgress Inspector Seal & Signature37
09/12/2026M01100629-S1Open ↗
09/01/2026M01336468-I1Open ↗
09/01/2026M01336468-I1Open ↗
Showing 3 of 37 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature20
09/12/2026M01100629-S1Open ↗
09/01/2026M01336468-I1Open ↗
09/01/2026M01336641-I1Open ↗
Showing 3 of 20 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
04/06/2018140751069Open ↗
Showing 1 of 3 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
04/06/2018140751069Open ↗
▸BISPC FULL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
04/06/2018140751069Open ↗
▸Trade Schedules & Equipment76
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE33
12/03/2019122849846Open ↗
10/17/2019122849846Open ↗
10/03/2019123718307Open ↗
Showing 3 of 33 on file for this type
▸BISSELF-CERT PLUMBING NOTICE30
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 30 on file for this type
▸BISSCHEDULE B - PLUMBING11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
04/12/2024122838493Open ↗
▸BISDETECTOR:CARBON MONOXIDE-CERT.OF INSTALL1
04/12/2024122838493Open ↗
▸Safety & Tenant Protection11
▸BISTenant Protection Plan and Notes10
04/18/2019123718307Open ↗
10/11/2018123421181Open ↗
08/02/2017123302639Open ↗
Showing 3 of 10 on file for this type
▸BISDS1-Demolition Submittal Certification Form1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos65
▸DOB NOWDEP ACP-5: Asbestos Assessment Report31
09/02/2026M00698050-I1Open ↗
09/02/2026M00698049-I1Open ↗
09/02/2026M00720532-P1Open ↗
Showing 3 of 31 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)18
04/18/2019123718307Open ↗
10/11/2018123421181Open ↗
04/06/2018140751069Open ↗
Showing 3 of 18 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM3
08/07/2017121226315Open ↗
Showing 1 of 3 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/27/2026M01029639-I1Open ↗
08/27/2026M01029639-S2Open ↗
08/27/2026M01029639-S1Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Energy Compliance57
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS28
12/31/2019122849846Open ↗
02/04/2019123239691Open ↗
10/11/2018123421181Open ↗
Showing 3 of 28 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS12
07/09/2020140751069Open ↗
12/31/2019122849846Open ↗
02/04/2019123239691Open ↗
Showing 3 of 12 on file for this type
▸BISTECHNICAL REPORT: ENERGY4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISTR8: Energy Code Progress Inspections2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISENERGY CODE 1ST REVIEW COMPLETE2
04/18/2019123718307Open ↗
08/04/2017121226315Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
04/12/2024122838493Open ↗
03/02/2021122280398Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
07/09/2020140751069Open ↗
04/06/2018140751069Open ↗
▸DOB NOWEN2: As Built Energy Analysis2
09/02/2026M00698049-I1Open ↗
08/13/2026M00720532-I1Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
04/06/2018140751069Open ↗
▸BISLIGHTING IN DWELLING UNITS1
04/12/2024122838493Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026M00988505-S2Open ↗
▸Inspections & Test Reports18
▸BISTECHNICAL REPORT: RESPONSIBILITY14
05/02/2022123718307Open ↗
06/07/2021102486640Open ↗
03/05/2021122280398Open ↗
Showing 3 of 14 on file for this type
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISMECHANICAL SYSTEMS1
04/12/2024122838493Open ↗
▸BIS* FINAL INSPECTION DIRECTIVE 14 OF 19751
12/16/2024104284347Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
03/31/2022123718307Open ↗
▸Approvals, Objections & Sign-offs73
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST27
12/16/2024104284347Open ↗
04/12/2024122838493Open ↗
05/04/2022123718307Open ↗
Showing 3 of 27 on file for this type
▸BISLANDMARKS APPROVAL27
05/10/2019123718307Open ↗
04/06/2018140751069Open ↗
12/22/2017123239691Open ↗
Showing 3 of 27 on file for this type
▸BISADMINISTRATIVE OBJECTIONS11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISLANDMARKS SIGNOFF4
04/12/2024122838493Open ↗
04/07/2022123718307Open ↗
03/02/2021122280398Open ↗
Showing 3 of 4 on file for this type
▸BISSUPERSEDING LETTER2
03/18/2020102486640Open ↗
11/14/2019102486640Open ↗
▸BISFINAL2
04/12/2024122838493Open ↗
05/03/2022123718307Open ↗
▸Cost, Insurance & Ownership60
▸BISCOST AFFIDAVIT54
06/07/2021102486640Open ↗
07/09/2020140751069Open ↗
12/31/2019122849846Open ↗
Showing 3 of 54 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW34
12/16/2024104284347Open ↗
04/12/2024122838493Open ↗
04/25/2022123718307Open ↗
Showing 3 of 4 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Filing & Intake Forms61
▸BISEFILING COVER SHEET27
04/18/2019123718307Open ↗
10/11/2018123421181Open ↗
12/08/2017123239691Open ↗
Showing 3 of 27 on file for this type
▸BISBOROUGH INTAKE FORM20
12/07/2022122395979Open ↗
03/18/2020102486640Open ↗
02/25/2020102486640Open ↗
Showing 3 of 20 on file for this type
▸BISADDITIONAL INFORMATION12
02/25/2020102486640Open ↗
02/19/2020102486640Open ↗
12/08/2017123239691Open ↗
Showing 3 of 12 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET2
04/06/2018140751069Open ↗
Showing 1 of 2 on file for this type
▸Other Documents24
▸DOB NOWProof of Historic Building11
09/01/2026M08023844-I1Open ↗
08/18/2026M01362961-P1Open ↗
08/13/2026M00886114-I1Open ↗
Showing 3 of 11 on file for this type
▸BISDepartment of Consumer Affairs (DCA) Form5
08/09/2017123101482Open ↗
08/07/2017121226315Open ↗
08/01/2017123101482Open ↗
Showing 3 of 5 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION4
03/25/2024122838493Open ↗
05/09/2018122849846Open ↗
Showing 2 of 4 on file for this type
▸BISSupporting Document: Fee Exempt1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISOAC REGISTRATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BIS* VENT. SYS.-ENGINEER/INSTALLER 27-136,7791
12/16/2024104284347Open ↗
▸DOB NOWBSA Meeting Minutes/BSA Resolution1
09/06/2026M00017017-I1Open ↗