Issued Permit Scope
Mechanical Systems
Facade Exterior Repairs throughout the building including masonry pointing, brick replacement, stone and terra-cotta repairs, caulking, etc. No change in use, occupancy or egress.
On file for this project
6 documents · 1 drawing sheet
Installation of suspended scaffold for facade repair & inspection.
On file for this project
3 documents · 2 drawing sheets
renovate suite 1107 on 11th fl. New partitions and finishes. No change in use, egress or occupancy
On file for this project
27 documents · 2 drawing sheets
Latest 3 of 7 filings on this floor.
Floor 1212p · 10 filings · 20 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
renovate suite 1206 on 12th fl. Minor non bearing partition and finishes removal. New partitions and finishes. No change in use, egress or occupancy.
On file for this project
24 documents · 1 drawing sheet
non bearing partitions and finishes removal in suite 1206, 1207 on 1th fl. Not change in use, egress or occupancy
On file for this project
5 documents
combine suites 1206, 1207 on 12th floor. Non bearing partition removal. New partitions and finishes. No change in use, egress or occupancy
On file for this project
14 documents
Latest 3 of 10 filings on this floor.
Floor 1113p · 5 filings · 20 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
renovate suite 1107 on 11th fl. New partitions and finishes. No change in use, egress or occupancy
On file for this project
27 documents · 1 drawing sheet
Renovate 11th fl hallway. Non bearing partition and finishes removal. New partition and finishes and finishes. No change in use egress or occupancy
On file for this project
9 documents
Combine suites 1107 and 1108. remove non bearing partitions and finishes. New pantry, flooring and door. No change in use, egress or occupancy
On file for this project
4 documents
Latest 3 of 5 filings on this floor.
Floor 109p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
renovate suite 1004 on 10th fl. non bearing partitions and finishes removal. Nwe partitions and finishes. No change in sue, egress or occupancy
On file for this project
8 documents
renovate suite 1010 on 10th fl. Minor non bearing partition removal. New partitions and finishes. No change in use, egress or occupancy
On file for this project
28 documents · 2 drawing sheets
Renovate 10th fl hallway. No change in use, egress or occupancy
On file for this project
9 documents
Floor 97p · 6 filings · 20 docs
Architecture
Issued Permit Scope
General Construction
Renovate suite 910 on 9th fl. New partitions and finishes. No change in use, egress or occupancy
On file for this project
8 documents
Renovate 9th fl hallway. Non bearing partitions and finishes removal. New partitions and finishes. No change in use, egress or occupancy
On file for this project
4 documents
renovate suite 904 on 9th fl. Minor non bearing partition removal. New partitions and finishes. No change in use, egress or occupancy
On file for this project
4 documents
Latest 3 of 6 filings on this floor.
Floor 8Under Construction20p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Mechanical plans filed herewith to show replacement of existing AC equipment with new split heat pump system, reconnect new air handling unit. No change to use, egress, or occupancy.
On file for this project
12 documents
Non baring partitions and finishes removal in suite 804 on 8th fl. No change in use, egress or occupancy
On file for this project
4 documents
New mech work in suite 808 on 8th fl. No change in use, egress or occupancy.
On file for this project
4 documents
Latest 3 of 7 filings on this floor.
Floor 77p · 4 filings · 20 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
renovate suite 703 on 7th fl. new sheetrock partitions and finishes. No change in use, egress or occupancy
On file for this project
18 documents
Renovate 7th fl hallway. Remove exist. finishes. New partitions and finishes. No change in use, egress or occupancy
On file for this project
4 documents
removal of non bearing partitions and finishes in suite 703. No change in use, egress or occupancy
On file for this project
10 documents
Latest 3 of 4 filings on this floor.
Floor 610p · 6 filings · 20 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
New AC unit and ductwork for suite 610 on 6th fl. No change in use, egress or occupancy
On file for this project
13 documents
renovate suite 610 on 6th fl. new partitions and finishes. No change in use, egress or occupancy
On file for this project
4 documents
Install 2 new offices in suite 604 on 6th fl. No change in use, egress or occupancy
On file for this project
8 documents
Latest 3 of 6 filings on this floor.
Floor 52p · 2 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Sprinklers
New AC unit and assoc. ductwork. No change in use, egress or occupancy
On file for this project
12 documents · 1 drawing sheet
modify exist. sprinkler system on 5th floor. No change in use, egress or occupancy
On file for this project
8 documents
Floor 427p · 8 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Suite 407 on 4th fl, new AC units and assoc ductwork. No change in use, egress or occupancy.
On file for this project
26 documents · 2 drawing sheets
Renovate suite 401 on 4th fl. New partitions and finishes. No change in use, egress or occupancy
On file for this project
16 documents · 1 drawing sheet
renovate suite 406 on 4th fl. New partitions nf finishes. No change in use, egress or occupancy
On file for this project
14 documents
Latest 3 of 8 filings on this floor.
Floor 311p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
suite 304 on 3rd floor, non bearing partitions and finishes removal. new partition and finishes. no change in use, egress or occupancy
On file for this project
4 documents
Renovate suite 307 on 3rd fl. Install pantry sink and elec HWH. Modify exist. sprinkler system. No change in use, egress or occupancy
On file for this project
10 documents
Install new AC units and assoc. ductwork. no change in use egress or occupancy
On file for this project
4 documents
Latest 3 of 5 filings on this floor.
Floor 2
Floor 1Under Construction61p · 4 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Demolish interior non-bearing partitions, door and frames. Installation of new non-bearing GYP, BD, partitions, Doors and frames. Obtain new CofO and Public Assembly permit for an existing eating and drinking establishment on the ground floor
On file for this project
7 documents
Replace 2 fixtures, relocate 2 fixtures, install 1 new sink. Install one new electric hot water heater. All work at ground floor.
On file for this project
42 documents · 6 drawing sheets
MODIFICATION OF EXISTING SPRINKLER SYSTEM ADD SPRINKLER PIPING WET AND ADD SPRINKLER HEADS, MODIFICATION OF PLUMBING WORK TO ADD PLUMBING WATER/SANITARY PIPING AND PLUMBING FIXTURES AS PLAN. NO CHANGE TO USE, EGRESS OR OCCUPANCY PROPOSED.
On file for this project
19 documents
Latest 3 of 4 filings on this floor.
CellarUnder Construction13p · 4 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Demolish interior non-bearing partitions, door and frames. Installation of new non-bearing GYP, BD, partitions, Doors and frames. Obtain new CofO and Public Assembly permit for an existing eating and drinking establishment on the ground floor
On file for this project
7 documents
Replace 2 fixtures, relocate 2 fixtures, install 1 new sink. Install one new electric hot water heater. All work at ground floor.
On file for this project
42 documents · 9 drawing sheets
MODIFICATION OF EXISTING SPRINKLER SYSTEM ADD SPRINKLER PIPING WET AND ADD SPRINKLER HEADS, MODIFICATION OF PLUMBING WORK TO ADD PLUMBING WATER/SANITARY PIPING AND PLUMBING FIXTURES AS PLAN. NO CHANGE TO USE, EGRESS OR OCCUPANCY PROPOSED.
On file for this project
19 documents
Latest 3 of 4 filings on this floor.
Site & exterior33p · 5 filings · 20 docs
ArchitectureCivilEquipmentGeneralMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sidewalk Shed
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
On file for this project
4 documents · 12 drawing sheets
Facade Exterior Repairs throughout the building including masonry pointing, brick replacement, stone and terra-cotta repairs, caulking, etc. No change in use, occupancy or egress.
On file for this project
6 documents · 9 drawing sheets
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
On file for this project
4 documents · 6 drawing sheets
Latest 3 of 5 filings on this floor.
Filed — no permit issued1p · 2 filings · 5 docs
Electrical
No filed description on record for this project.
On file for this project
3 documents
No filed description on record for this project.
On file for this project
2 documents · 1 drawing sheet