RoofVerizonUnder Construction35p · 6 filings · 16 docs
ArchitectureGeneralMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems
Project X01463954Permit Issued · 09/29/2026
SUSPENDED SCAFFOLD OUTRIGGER SYSTEM FOR EXTERIOR FACADE RESTORATION AND INSPECTION WORK AT 370 EAST 150 STREET, BRONX, NY 10455
On file for this project
5 documents
Project X00802674Signed-off · 11/14/2024
Modification of mechanical system to include new HVAC equipment and associated ducts and piping as shown on the drawings filed herewith. No change in use, egress, or occupancy.
On file for this project
2 documents
Project X01080815Signed-off · 08/20/2024
Filing for the replacement of the 7th floor roof.
On file for this project
4 documents
Latest 3 of 6 filings on this floor.
PenthouseVerizon1p · 1 filing · 2 docs
Mechanical
Project X00802674Signed-off · 11/14/2024
Modification of mechanical system to include new HVAC equipment and associated ducts and piping as shown on the drawings filed herewith. No change in use, egress, or occupancy.
On file for this project
2 documents
Floor 7Verizon23p · 3 filings · 8 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
Project X00802674Signed-off · 11/14/2024
Modification of mechanical system to include new HVAC equipment and associated ducts and piping as shown on the drawings filed herewith. No change in use, egress, or occupancy.
On file for this project
2 documents
Project X00805898Signed-off · 12/18/2023
Removal of chiller plant and associated piping in cellar thru roof. Installation of new HVAC on 2nd, 3rd, and 5th floors and two new adiabatic coolers on roof with associated ducts and piping. No change in use, egress, or occupancy.
On file for this project
5 documents
Project X00973972Permit Issued · 12/14/2023
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
1 document
Floor 6Verizon17p · 2 filings · 3 docs
Mechanical
Issued Permit Scope
Mechanical Systems · Supported Scaffold
Project X00802674Signed-off · 11/14/2024
Modification of mechanical system to include new HVAC equipment and associated ducts and piping as shown on the drawings filed herewith. No change in use, egress, or occupancy.
On file for this project
2 documents
Project X00973972Permit Issued · 12/14/2023
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
1 document
Floor 5Verizon23p · 3 filings · 8 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
Project X00802674Signed-off · 11/14/2024
Modification of mechanical system to include new HVAC equipment and associated ducts and piping as shown on the drawings filed herewith. No change in use, egress, or occupancy.
On file for this project
2 documents
Project X00805898Signed-off · 12/18/2023
Removal of chiller plant and associated piping in cellar thru roof. Installation of new HVAC on 2nd, 3rd, and 5th floors and two new adiabatic coolers on roof with associated ducts and piping. No change in use, egress, or occupancy.
On file for this project
5 documents
Project X00973972Permit Issued · 12/14/2023
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
1 document
Floor 4Verizon25p · 4 filings · 16 docs
ArchitectureGeneralMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
Project X00802674Signed-off · 11/14/2024
Modification of mechanical system to include new HVAC equipment and associated ducts and piping as shown on the drawings filed herewith. No change in use, egress, or occupancy.
On file for this project
2 documents
Project X01020351Signed-off · 03/28/2024
Installation of new AC Units for new telco equipment with associated piping. No change to use, egress, or occupancy.
On file for this project
10 documents
Project X01020342Signed-off · 03/26/2024
General Construction in conjunction with the installation of new AC Units for new telco equipment with associated piping. No change to use, egress, or occupancy.
On file for this project
4 documents
Latest 3 of 4 filings on this floor.
Floor 3Verizon26p · 4 filings · 12 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
Project X00802674Signed-off · 11/14/2024
Modification of mechanical system to include new HVAC equipment and associated ducts and piping as shown on the drawings filed herewith. No change in use, egress, or occupancy.
On file for this project
2 documents
Project X01080815Signed-off · 08/20/2024
Filing for the replacement of the 7th floor roof.
On file for this project
4 documents
Project X00805898Signed-off · 12/18/2023
Removal of chiller plant and associated piping in cellar thru roof. Installation of new HVAC on 2nd, 3rd, and 5th floors and two new adiabatic coolers on roof with associated ducts and piping. No change in use, egress, or occupancy.
On file for this project
5 documents
Latest 3 of 4 filings on this floor.
Floor 2Verizon33p · 3 filings · 10 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Sprinklers · Supported Scaffold
Project X00802753Signed-off · 09/30/2025
Modification of existing sprinkler system to remove, replace, and relocate sprinkler heads and associated piping as shown on the drawings filed herewith, No change in use, egress, or occupancy.
On file for this project
7 documents
Project X00802674Signed-off · 11/14/2024
Modification of mechanical system to include new HVAC equipment and associated ducts and piping as shown on the drawings filed herewith. No change in use, egress, or occupancy.
On file for this project
2 documents
Project X00973972Permit Issued · 12/14/2023
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
1 document
Floor 1Verizon32p · 5 filings · 14 docs
ArchitectureMechanical
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems
Project X00944356Signed-off · 07/01/2025
Removal of Fuel Oil Tank No. 2 associated with the existing generator. Removal of all associated piping, cap at wall in fuel oil room.
On file for this project
4 documents
Project X00948795Signed-off · 05/20/2025
REPURPOSING OF EXISTING FUEL OIL PIPING. EXTEND NEW PIPING FROM FUEL OIL TANK NO. 1 TO EXISTING PIPING WITH ASSOCIATED VALVES.
On file for this project
5 documents
Project X00802674Signed-off · 11/14/2024
Modification of mechanical system to include new HVAC equipment and associated ducts and piping as shown on the drawings filed herewith. No change in use, egress, or occupancy.
On file for this project
2 documents
Latest 3 of 5 filings on this floor.
CellarVerizon11p · 3 filings · 14 docs
ArchitectureMechanical
Issued Permit Scope
Boiler Equipment
Project X00944356Signed-off · 07/01/2025
Removal of Fuel Oil Tank No. 2 associated with the existing generator. Removal of all associated piping, cap at wall in fuel oil room.
On file for this project
4 documents
Project X00948795Signed-off · 05/20/2025
REPURPOSING OF EXISTING FUEL OIL PIPING. EXTEND NEW PIPING FROM FUEL OIL TANK NO. 1 TO EXISTING PIPING WITH ASSOCIATED VALVES.
On file for this project
5 documents
Project X00805898Signed-off · 12/18/2023
Removal of chiller plant and associated piping in cellar thru roof. Installation of new HVAC on 2nd, 3rd, and 5th floors and two new adiabatic coolers on roof with associated ducts and piping. No change in use, egress, or occupancy.
On file for this project
5 documents
Sub-BasementVerizon22p · 2 filings · 7 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
Project X00802674Signed-off · 11/14/2024
Modification of mechanical system to include new HVAC equipment and associated ducts and piping as shown on the drawings filed herewith. No change in use, egress, or occupancy.
On file for this project
2 documents
Project X00805898Signed-off · 12/18/2023
Removal of chiller plant and associated piping in cellar thru roof. Installation of new HVAC on 2nd, 3rd, and 5th floors and two new adiabatic coolers on roof with associated ducts and piping. No change in use, egress, or occupancy.
On file for this project
5 documents
Site & exteriorTD Bank, VerizonUnder Construction26p · 9 filings · 12 docs
ArchitectureCivilEquipmentGeneralMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Sidewalk Shed · Supported Scaffold
Project X01448909Permit Issued · 08/28/2026
INSTALLATION OF 300 PSF SIDEWALK SHED AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE 2022. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
On file for this project
1 document
Project X01370891Signed-off · 03/17/2026
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
On file for this project
1 document
Project X01370893Signed-off · 03/13/2026
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
On file for this project
1 document
Latest 3 of 9 filings on this floor.
Filed — no permit issuedVerizon12p · 1 filing · 3 docs
ArchitectureGeneral
Project X01424498Approved
Filing for Facade Alterations to comply with LL11, scope to include removal/replacement of cracked, Spalled bricks, repointing deteriorated mortar joints, replace sealant, patch limestone and replace lintels.
On file for this project
3 documents