| Owner | Filings | Most Recent |
|---|---|---|
| HSK MANAGEMENT | 71 | 09/13/2026 |
| HOLLYWOOD CONS GROUP | 2 | 03/22/2026 |
| HIGHLINE DEVELOPERS BKLYN LLC | 2 | 03/21/2026 |
| BL REALTY | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/20/2021 | $950K | — | — → — | $579/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| NIKOLAI KATZ ARCHITECT | 6 | 05/18/2026 |
| SIERRA CONSTRUCTION | 1 | 01/21/2026 |
| ASHRAF CORP | 1 | 12/11/2025 |
| AL FFRED ARCHITECTURE PLLC | 8 | 06/25/2025 |
| BGM ENGINEERING | 4 | 10/10/2023 |
| ASHER ARCHITECT | 1 | 08/08/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| EMPIRE EXPEDITING | 24 | 03/21/2026 |
| NYC PERMIT SERVICES | 2 | 03/21/2026 |
| NY DOB PERMITS | 2 | 03/21/2026 |
| REDCUT EXPEDITING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ACE MAINTENANCE USA LLC | General Contractor | 19 | 07/08/2026 |
| HSK MANAGEMENT INC | General Contractor | 6 | 07/08/2026 |
| AMERICAN POWER ELECT CONS | Electrical | 1 | 03/22/2026 |
| ARCO PLBG AND HTG INC | Plumbing | 1 | 07/08/2026 |
| BT'S PLUMBING AND HEATING | Plumbing | 1 | 07/08/2026 |
| KISHAN PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BGM ENGINEERING, LLC | 1514 | 12 | 05/18/2026 |
| AA BUILDING & INSPECTION | 1519 | 1 | 01/21/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | ACE MAINTENANCE USA LLC | 03/10/2026 |
| DOB NOW | Supported Scaffold | Signed-off | ACE MAINTENANCE USA LLC | 03/05/2026 |
| DOB NOW | Sprinklers | Signed-off | ARCO PLBG AND HTG INC | 03/02/2026 |
| DOB NOW | Plumbing | Signed-off | N AND S PLUMBING INC | 12/05/2025 |
| DOB NOW | General Construction | Permit Issued | ACE MAINTENANCE USA LLC | 10/03/2025 |
| DOB NOW | Structural | Signed-off | ACE MAINTENANCE USA LLC | 09/26/2025 |
| DOB NOW | Mechanical Systems | Signed-off | ACE MAINTENANCE USA LLC | 09/25/2025 |
| DOB NOW | Plumbing | Signed-off | BT'S PLUMBING AND HEATING | 09/16/2025 |
| DOB NOW | General Construction | Permit Issued | ACE MAINTENANCE USA LLC | 05/22/2025 |
| DOB NOW | Construction Fence | Signed-off | ACE MAINTENANCE USA LLC | 05/22/2025 |
| DOB NOW | Mechanical Systems | Signed-off | ACE MAINTENANCE USA LLC | 09/04/2024 |
| DOB NOW | General Construction | Permit Issued | ACE MAINTENANCE USA LLC | 08/09/2024 |
| DOB NOW | Foundation | Signed-off | ACE MAINTENANCE USA LLC | 04/18/2024 |
| DOB NOW | Construction Fence | Signed-off | ACE MAINTENANCE USA LLC | 04/18/2024 |
| DOB NOW | General Construction | Permit Issued | ACE MAINTENANCE USA LLC | 04/17/2024 |
| DOB NOW | Structural | Signed-off | ACE MAINTENANCE USA LLC | 04/16/2024 |
| DOB NOW | Structural | Signed-off | HSK MANAGEMENT INC | 06/26/2023 |
| DOB NOW | Construction Fence | Signed-off | HSK MANAGEMENT INC | 05/11/2023 |
| DOB NOW | Structural | Signed-off | HSK MANAGEMENT INC | 06/28/2022 |
| DOB NOW | Construction Fence | Signed-off | HSK MANAGEMENT INC | 01/06/2022 |
| DOB NOW | Foundation | Signed-off | HSK MANAGEMENT INC | 12/28/2021 |
| DOB NOW | Structural | Signed-off | HSK MANAGEMENT INC | 12/28/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/18/2026 | Permit Issued | ACE MAINTENANCE USA LLC | Heating and Air Conditioning Systems | Heat / Cool Samsung AC024DNHDCG/AA 25,530 BTU · Vrf Indoor ×6 AC024DXADCG/AA 25,530 BTU · Vrf Indoor ×5 AM018ANHDCH/AA 17,840 BTU · Vrf Indoor ×2 AM048TXMDCH/AA 41,493 BTU · Vrf Outdoor ×2 AM012TNVDCH/AA 11,840 BTU · Vrf Indoor ×1 AM018TNVDCH/AA 17,840 BTU · Vrf Indoor ×1 AM024ANHDCH/AA 23,653 BTU · Vrf Indoor ×1 AM036TXMDCH/AA 29,680 BTU · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/18/2026 | Signed-off | KISHAN PLUMBING INC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/15/2026 | Complete | AMERICAN POWER ELECT CONS | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/21/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/12/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/07/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/11/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/09/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/29/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 12/19/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/17/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 12/17/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/08/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/18/2026 | Air barrier - visual inspection | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 05/18/2026 | Fenestration areas | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 05/18/2026 | Lighting in dwelling units | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 05/18/2026 | Air barrier continuity plan testing | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 05/18/2026 | Lighting controls | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 05/18/2026 | Insulation placement and R values | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 05/18/2026 | Fenestration air leakage | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 05/18/2026 | Fire-Resistance Rated Construction | RAUL VELASQUEZ MARTINEZ | progress |
| 05/18/2026 | Energy Code Compliance Inspections | RAUL VELASQUEZ MARTINEZ | progress |
| 05/18/2026 | Fire-Resistant Penetrations and Joints | RAUL VELASQUEZ MARTINEZ | special |
| 05/18/2026 | Exterior Insulation and Finish Systems (EIFS) | RAUL VELASQUEZ MARTINEZ | special |
| 05/18/2026 | Protection of exposed foundation insulation | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 05/18/2026 | Air barrier — testing | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 05/18/2026 | Interior lighting power | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 05/18/2026 | Metering | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 05/18/2026 | Exterior lighting power | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 05/18/2026 | Fenestration and door U-factor and product ratings | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 02/06/2026 | Fenestration and door U-factor and product ratings | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 02/06/2026 | Energy Code Compliance Inspections | RAUL VELASQUEZ MARTINEZ | progress |
| 02/06/2026 | Fire-Resistance Rated Construction | RAUL VELASQUEZ MARTINEZ | progress |
| 02/06/2026 | Lighting in dwelling units | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 02/06/2026 | Interior lighting power | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 02/06/2026 | Protection of exposed foundation insulation | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 02/06/2026 | Air barrier - visual inspection | RAUL VELASQUEZ MARTINEZ | energy_progress |
| 02/06/2026 | Fenestration areas | RAUL VELASQUEZ MARTINEZ | energy_progress |