| Owner | Filings | Most Recent |
|---|---|---|
| 37-14 34th Street Property | 36 | 03/21/2026 |
| Nere Li Development | 9 | 07/08/2026 |
| 3714 Lic Development | 8 | 03/21/2026 |
| Bridge Plaza Clinic | 2 | 03/21/2026 |
| Garthchester Realty | 1 | 10/13/2026 |
| Metropolis Realty | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/07/2017 | $16.5M | — | — → — | — not available |
| 10/21/2014 | $9.7M | — | AT-CORT I, L.L.C. → 37-14 34TH STREET PROPERTY LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| BHK Engineering | 1 | 10/12/2026 |
| Nic 88 | 4 | 04/01/2025 |
| Morali Architecture | 1 | 07/29/2020 |
| Building | 1 | 08/02/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| NY Restaurant | 4 | 03/21/2026 |
| Anthony Morali Architect | 2 | 03/21/2026 |
| Building | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| New Empire Builder | Scaffold | 3 | 07/08/2026 |
| NY Building Associates | General Contractor | 2 | 03/21/2026 |
| NY Building Associates | Scaffold | 2 | 03/21/2026 |
| KJK Electric | Electrical | 1 | 03/22/2026 |
| New Empire Builder | General Contractor | 1 | 07/08/2026 |
| S & L Plumbing | Plumbing | 1 | 06/28/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BHK Engineering | 9589 | 1 | 10/12/2026 |
| Nic 88 | 8371 | 3 | 04/01/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | S & L Plumbing | 04/11/2025 |
| DOB NOW | Construction Fence | Permit Issued | NY Building Associates | 03/28/2025 |
| DOB NOW | General Construction | Permit Issued | NY Building Associates | 03/28/2025 |
| DOB NOW | Curb Cut | Signed-off | New Empire Builder | 01/06/2021 |
| DOB NOW | Supported Scaffold | Signed-off | New Empire Builder | 07/30/2020 |
| DOB NOW | Supported Scaffold | Signed-off | New Empire Builder | 12/19/2019 |
| DOB NOW | Supported Scaffold | Signed-off | New Empire Builder | 08/05/2019 |
| BIS | — | ISSUED | New Empire Builder | 06/16/2022 |
| BIS | SP | ISSUED | RRP Plumbing | 11/03/2020 |
| BIS | EQ | ISSUED | New Empire Builder | 06/25/2020 |
| BIS | — | ISSUED | New Empire Builder | 06/25/2020 |
| BIS | — | ISSUED | New Empire Builder | 04/01/2020 |
| BIS | PL | ISSUED | RRP Plumbing | 02/05/2020 |
| BIS | SP | ISSUED | RRP Plumbing | 10/09/2019 |
| BIS | EQ | ISSUED | Core Scaffold Systems | 09/04/2019 |
| BIS | EQ | ISSUED | New Empire Builder | 07/29/2019 |
| BIS | — | ISSUED | New Empire Builder | 04/12/2019 |
| BIS | PL | ISSUED | RRP Plumbing | 01/31/2019 |
| BIS | EQ | ISSUED | Core Scaffold Systems | 09/11/2018 |
| BIS | EQ | ISSUED | New Empire Builder | 08/17/2018 |
| BIS | — | ISSUED | New Empire Builder | 08/17/2018 |
| BIS | EQ | ISSUED | Core Scaffold Systems | 09/13/2017 |
| BIS | — | ISSUED | New Empire Builder | 08/23/2017 |
| BIS | — | ISSUED | New Empire Builder | 08/04/2017 |
| BIS | EQ | ISSUED | New Empire Builder | 08/04/2017 |
| BIS | — | ISSUED | New Empire Builder | 08/04/2017 |
| BIS | — | ISSUED | Project Builders Group | 05/11/2017 |
| BIS | — | ISSUED | Project Builders Group | 03/02/2017 |
| BIS | — | ISSUED | Project Builders Group | 03/02/2017 |
| BIS | EQ | ISSUED | Project Builders Group | 03/02/2017 |
| BIS | EQ | ISSUED | Project Builders Group | 03/02/2017 |
| BIS | — | ISSUED | Project Builders Group | 03/04/2016 |
| BIS | — | ISSUED | Project Builders Group | 03/04/2016 |
| BIS | EQ | ISSUED | Project Builders Group | 03/01/2016 |
| BIS | — | ISSUED | Project Builders Group | 07/17/2015 |
| BIS | EQ | ISSUED | Project Builders Group | 06/16/2015 |
| BIS | — | ISSUED | Project Builders Group | 06/15/2015 |
| BIS | EQ | ISSUED | Pro Construction Specialt | 06/10/2015 |
| BIS | EQ | ISSUED | Project Builders Group | 05/18/2015 |
| BIS | OT | ISSUED | Project Builders Group | 04/28/2015 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/01/2025 | Permit Issued | S & L Plumbing | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/25/2021 | Complete | Q.Y. Electric | 80 meters, 80 new_meters |
| 08/05/2020 | Complete | Q.Y. Electric | General Wiring |
| 06/12/2020 | Complete | Q.Y. Electric | General Wiring, Lighting |
| 11/18/2019 | Complete | KJK Electric | General Wiring |
| 04/29/2019 | Complete | Kwong Ming Electric | — |
| 03/02/2018 | Complete | KJK Electric | 1 meters, 1 new_meters |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/01/2025 | Fire-Resistant Penetrations and Joints | Eric Sun | special |
| 04/01/2025 | Tenant Protection Plan Compliance | Eric Sun | special |
| 04/01/2025 | HVAC-R and service water piping design and insulation | Eric Sun | energy_progress |
| 04/01/2025 | HVAC-R and service water heating equipment | Eric Sun | energy_progress |
| 04/01/2025 | HVAC-R and service water heating system controls | Eric Sun | energy_progress |
| 07/31/2019 | Final | TONY ONYEAGORO | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Crispy Chiken | Restaurant / Food Service | Floor 1 | Project Q01188479 |