Mansion type or town house
374 CLINTON STREET
BROOKLYN · BIN 3378558
💬 Discuss this project
1900Year Built
3Stories
A7Building Class
R6BZoning
7,914 sfGross Floor Area
1Units
Rent Stabilized5 Open Violations ▸FDNY Report ↗
Mansion type or town house · Owner of record: 374 CLINTON STREET CORP · 7,000 sf lot · 1.13 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanical
Permit Issued — active, not yet Signed-off
RoofUnder Construction13p · 1 filing · 20 docs
Floor 1Under Construction7p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SOMERAROAD904/09/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JM ZONING, LLC.803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TOJI CONSTRUCTION LLCGeneral Contractor404/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DOMANI INSPECTION SERVICE843506/17/2026
Building Lifecycle
All (77)Filed (7)Permit Issued (4)Inspection (5)Objection (35)Special Inspection (26)
07/22/2026
Objection resolved — Resolved
07/22/2026
Objection resolved — Resolved
07/22/2026
Objection resolved — Resolved
07/22/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
07/16/2026
Objection raised — Inspections
07/13/2026
Objection resolved — Addressed
06/23/2026
Objection raised — Other
06/23/2026
Objection raised — Cost
06/23/2026
Objection raised — Inspections
06/23/2026
Objection raised — Scope
06/23/2026
Objection raised — Admin
06/22/2026
Objection raised — Other
06/17/2026
Filed — Alteration
FILING HEREWITH STRUCTURAL WORK IN CONJUNCTION WITH GARAGE RENOVATIONS AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B00816065-P3
06/17/2026
Filed — Alteration
FILING HEREWITH STRUCTURAL WORK IN CONJUNCTION WITH GARAGE RENOVATIONS AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B00816065-P2
06/05/2026
Filed — Alteration
FILING HEREWITH STRUCTURAL WORK IN CONJUNCTION WITH GARAGE RENOVATIONS AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B00816065-P1
05/28/2026
Special inspection requirement — Final
JOHN MCMONAGLE
05/28/2026
Special inspection requirement — Concrete - Cast-In-Place
JOHN MCMONAGLE
05/28/2026
Special inspection requirement — Subgrade Inspections
JOHN MCMONAGLE
05/28/2026
Special inspection requirement — Final
JOHN MCMONAGLE
05/28/2026
Special inspection requirement — Footing and Foundation
JOHN MCMONAGLE
05/28/2026
Special inspection requirement — Final
JOHN MCMONAGLE
05/28/2026
Special inspection requirement — Fire-Resistance Rated Construction
JOHN MCMONAGLE
05/28/2026
Special inspection requirement — Interior lighting power
JOHN MCMONAGLE
05/28/2026
Special inspection requirement — Structural Steel - Details
JOHN MCMONAGLE
05/28/2026
Special inspection requirement — Structural Steel - High Strength Bolting
JOHN MCMONAGLE
05/28/2026
Special inspection requirement — Structural Steel - Welding
JOHN MCMONAGLE
05/28/2026
Special inspection requirement — Post-installed Anchors
05/28/2026
Special inspection requirement — Masonry
04/16/2026
Inspection — No Access-Final PL - Up to 3 Requested Floors
No Access
View inspection ↗
04/10/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/10/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
03/27/2026
Permit issued — Mechanical Systems
B00816065-S2-MS
03/27/2026
Permit issued — Structural
B00816065-S1-ST
03/27/2026
Permit issued — General Construction
B00816065-I1-GC
03/27/2026
Permit issued — Foundation
B00816065-S3-FO
01/07/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/07/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/24/2024
Objection resolved — Addressed
11/29/2023
Objection resolved — Addressed
11/15/2023
Objection resolved — Addressed
11/15/2023
Objection resolved — Addressed
11/13/2023
Objection resolved — Addressed
11/06/2023
Objection resolved — Addressed
10/23/2023
Objection raised — Other
10/23/2023
Objection raised — Structural
10/23/2023
Objection resolved — Addressed
10/23/2023
Objection resolved — Addressed
10/19/2023
Filed — Alteration
FILING HEREWITH STRUCTURAL WORK IN CONJUNCTION WITH GARAGE RENOVATIONS AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B00816065-S3
10/18/2023
Objection resolved — Addressed
10/09/2023
Objection resolved — Addressed
10/03/2023
Objection resolved — Addressed
09/27/2023
Objection raised — Admin
09/27/2023
Objection raised — Fire_Protection
09/27/2023
Objection raised — Admin
09/25/2023
Filed — Alteration
FILING HEREWITH STRUCTURAL WORK IN CONJUNCTION WITH GARAGE RENOVATIONS AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B00816065-S1
09/25/2023
Special inspection requirement — Final
JOHN MCMONAGLE
09/25/2023
Special inspection requirement — Footing and Foundation
JOHN MCMONAGLE
09/25/2023
Special inspection requirement — Concrete - Cast-In-Place
JOHN MCMONAGLE
09/25/2023
Special inspection requirement — Subgrade Inspections
JOHN MCMONAGLE
09/22/2023
Objection resolved — Addressed
Latest 60 of 77 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedTOJI CONSTRUCTION LLC03/27/2026
DOB NOWStructuralPermit IssuedTOJI CONSTRUCTION LLC03/27/2026
DOB NOWGeneral ConstructionPermit IssuedTOJI CONSTRUCTION LLC03/27/2026
DOB NOWFoundationPermit IssuedTOJI CONSTRUCTION LLC03/27/2026
1 project · most recent 06/17/2026
Associated Ducts and Piping Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
06/17/2026Permit IssuedTOJI CONSTRUCTION LLCAssociated Ducts and Piping, Heating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric SUZ-KA24NAHZ 4,940 CFM · Condensing Unit ×1
1 project · most recent 06/17/2026
Steel
FiledStatusContractorScope
06/17/2026Permit IssuedTOJI CONSTRUCTION LLCSteel
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
04/16/2026No Access-Final PL - Up to 3 Requested FloorsNo AccessView ↗
04/10/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/10/2026Pass-Final General Construction Non-Directive 14PassView ↗
01/07/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
01/07/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 26
DateRequirementInspectorRole
07/22/2026Fire-Resistant Penetrations and Joints—special
05/28/2026FinalJOHN MCMONAGLEprogress
05/28/2026Concrete - Cast-In-PlaceJOHN MCMONAGLEspecial
05/28/2026Subgrade InspectionsJOHN MCMONAGLEspecial
05/28/2026FinalJOHN MCMONAGLEprogress
05/28/2026Footing and FoundationJOHN MCMONAGLEprogress
05/28/2026FinalJOHN MCMONAGLEprogress
05/28/2026Fire-Resistance Rated ConstructionJOHN MCMONAGLEprogress
05/28/2026Interior lighting powerJOHN MCMONAGLEenergy_progress
05/28/2026Structural Steel - DetailsJOHN MCMONAGLEspecial
05/28/2026Structural Steel - High Strength BoltingJOHN MCMONAGLEspecial
05/28/2026Structural Steel - WeldingJOHN MCMONAGLEspecial
05/28/2026Post-installed Anchors—special
05/28/2026Masonry—special
09/25/2023FinalJOHN MCMONAGLEprogress
09/25/2023Footing and FoundationJOHN MCMONAGLEprogress
09/25/2023Concrete - Cast-In-PlaceJOHN MCMONAGLEspecial
09/25/2023Subgrade InspectionsJOHN MCMONAGLEspecial
07/21/2023HVAC-R and service water heating system controlsJOHN MCMONAGLEenergy_progress
07/21/2023Ventilation and air distribution systemJOHN MCMONAGLEenergy_progress
07/21/2023Fire-Resistant Penetrations and JointsJOHN MCMONAGLEspecial
07/21/2023FinalJOHN MCMONAGLEprogress
07/21/2023Mechanical SystemsJOHN MCMONAGLEspecial
07/21/2023HVAC-R and service water heating equipmentJOHN MCMONAGLEenergy_progress
07/21/2023Permanent certificateJOHN MCMONAGLEenergy_progress
Latest 25 of 26.
▾Documents — 29 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/16/2026B00816065-S1Request digital key ↗
08/16/2026B00816065-I1Request digital key ↗
08/16/2026B00816065-P2Request digital key ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications18
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/16/2026B00816065-P2Open ↗
08/16/2026B00816065-S1Open ↗
08/16/2026B00816065-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/06/2026B00816065-S3Open ↗
09/01/2026B00816065-P2Open ↗
09/01/2026B00816065-P2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/06/2026B00816065-S3Open ↗
09/01/2026B00816065-P3Open ↗
08/30/2026B00816065-S2Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form4
08/16/2026B00816065-S3Open ↗
08/16/2026B00816065-S1Open ↗
08/16/2026B00816065-I1Open ↗
Showing 3 of 4 on file for this type