| Firm | Filings | Most Recent |
|---|---|---|
| MICHAEL A. BIAGIOLI, ARCHITECT | 7 | 02/26/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| PATRICIA L. GASS | 8 | 03/21/2026 |
| LC EXPEDITING | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| 3584 CONSTRUCTION CORP | General Contractor | 8 | 04/09/2026 |
| JPI PLUMBING & HEATING IN | Plumbing | 1 | 07/08/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A TECH ENGINEERING NYC, P | 6738 | 2 | 12/29/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | S&B CONSTRUCTION | 01/21/2026 |
| DOB NOW | Curb Cut | Signed-off | S&B CONSTRUCTION | 12/03/2025 |
| DOB NOW | Foundation | Permit Issued | S&B CONSTRUCTION | 02/07/2025 |
| DOB NOW | Plumbing | Signed-off | QUALITY PLUMBING, INC | 11/04/2024 |
| DOB NOW | Construction Fence | Signed-off | S&B CONSTRUCTION | 08/01/2024 |
| DOB NOW | Plumbing | Signed-off | JPI PLUMBING & HEATING IN | 03/14/2024 |
| DOB NOW | General Construction | Permit Issued | S&B CONSTRUCTION | 02/07/2024 |
| DOB NOW | Construction Fence | Signed-off | S&B CONSTRUCTION | 07/26/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 02/26/2025 | Signed-off | 3584 CONSTRUCTION CORP | Heating and Air Conditioning Systems | Heat / Cool Rheem RHEEM: TCD2B24S21SXA 64,400 BTU · Furnace ×2 Rheem - TCD2B48S21SA 23,600 BTU · Condensing Unit ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/26/2025 | Signed-off | JPI PLUMBING & HEATING IN | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2024 | Complete | RIDGE ELECTRIC CORP. | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/21/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/21/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 05/02/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/15/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/01/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 01/03/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/27/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/26/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/02/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/20/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/04/2025 | Maintenance information | anthony santoro | energy_progress |
| 03/04/2025 | HVAC-R and service water heating system controls | anthony santoro | energy_progress |
| 03/04/2025 | HVAC-R and service water heating equipment | anthony santoro | energy_progress |
| 03/04/2025 | Permanent certificate | anthony santoro | energy_progress |
| 03/04/2025 | HVAC-R and service water piping design and insulation | anthony santoro | energy_progress |
| 03/04/2025 | Metering | anthony santoro | energy_progress |
| 02/24/2025 | HVAC-R and service water heating system controls | anthony santoro | energy_progress |
| 02/24/2025 | Permanent certificate | anthony santoro | energy_progress |
| 02/24/2025 | HVAC-R and service water heating equipment | anthony santoro | energy_progress |
| 02/24/2025 | Metering | anthony santoro | energy_progress |
| 02/24/2025 | HVAC-R and service water piping design and insulation | anthony santoro | energy_progress |
| 02/24/2025 | Maintenance information | anthony santoro | energy_progress |
| 10/08/2024 | Maintenance information | anthony santoro | energy_progress |
| 10/08/2024 | Metering | anthony santoro | energy_progress |
| 10/08/2024 | HVAC-R and service water piping design and insulation | anthony santoro | energy_progress |
| 10/08/2024 | Permanent certificate | anthony santoro | energy_progress |
| 10/08/2024 | HVAC-R and service water heating equipment | anthony santoro | energy_progress |
| 10/08/2024 | HVAC-R and service water heating system controls | anthony santoro | energy_progress |
| 07/07/2023 | Chimneys and vents | anthony santoro | special |
| 07/07/2023 | Preliminary | anthony santoro | progress |
| 07/07/2023 | Air barrier — testing | anthony santoro | energy_progress |
| 07/07/2023 | Insulation placement and R values | anthony santoro | energy_progress |
| 07/07/2023 | Fenestration and door U-factor and product ratings | anthony santoro | energy_progress |
| 07/07/2023 | Maintenance information | anthony santoro | energy_progress |
| 07/07/2023 | Electric vehicle service equipment requirements | anthony santoro | energy_progress |