← Back
Primarily 2 family with 1 store or office
376 UNION AVENUE
BROOKLYN · BIN 3323015
💬 Discuss this project
1910Year Built
3Stories
S2Building Class
R7AZoning
3,784 sfGross Floor Area
3Units
0 Open ViolationsFDNY Report ↗
Primarily 2 family with 1 store or office · Owner of record: RHOMBUS POWERS LLC · 2,494 sf lot · 1.52 FAR built · Flood zone X
Locations of Work
Architecture
Roof2p · 2 filings · 20 docs
Floor 21p · 1 filing · 20 docs
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
RHOMBUS PROPERTIES2107/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/01/2021$2.6M—— → —$700/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MICHAEL MUROFF ARCHITECT LLC601/03/2025
BUILDTECH ENGINEERING DPC203/07/2024
R&P CONSULTING ENGINEERS LLC109/07/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MICHAEL MUROFF ARCHITECT LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BW & SON CONSTRUCTION LLCGeneral Contractor1307/08/2026
EASTERN BH MECHANICAL INCGeneral Contractor407/08/2026
TRI CITY MECHANICAL GROUP CORPPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BUILDTECH ENGINEERING6369801/03/2025
Building Lifecycle
All (66)Filed (9)Permit Issued (11)Signed Off (6)Violation (3)Inspection (2)Objection (16)Special Inspection (19)
09/09/2025
Signed off — Alteration
INSTALL A NEW 5-TON MULTIZONE INVERTER HEAT-PUMP AND 5 INTERIOR AIR HANDLER UNITS.
B00873987-I1
09/09/2025
Signed off — Alteration
INSTALL A NEW 5-TON MULTIZONE INVERTER HEAT-PUMP AND 5 INTERIOR AIR HANDLER UNITS.
B00803539-I1
09/08/2025
Signed off — Alteration
INSTALL A NEW 5-TON MULTIZONE INVERTER HEAT-PUMP AND 5 INTERIOR AIR HANDLER UNITS.
B00873987-S1
08/28/2025
Signed off — Alteration
INSTALL A NEW 5-TON MULTIZONE INVERTER HEAT-PUMP AND 5 INTERIOR AIR HANDLER UNITS.
B00803539-S1
03/24/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
02/27/2025
Signed off — Alteration
INSTALL A NEW 5-TON MULTIZONE INVERTER HEAT-PUMP AND 5 INTERIOR AIR HANDLER UNITS.
B00873987-S2
02/27/2025
Signed off — Alteration
INSTALL A NEW 5-TON MULTIZONE INVERTER HEAT-PUMP AND 5 INTERIOR AIR HANDLER UNITS.
B00803539-S2
01/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Luis Pichardo
01/28/2025
Special inspection requirement — Fire-Resistance Rated Construction
Luis Pichardo
01/28/2025
Special inspection requirement — Final
Juan Ramos
01/24/2025
Permit issued — Mechanical Systems
B00873987-S2-MS
01/24/2025
Permit issued — Mechanical Systems
B00803539-S2-MS
01/09/2025
Special inspection requirement — Lighting in dwelling units
Luis Pichardo
01/09/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Luis Pichardo
01/09/2025
Special inspection requirement — Final
Juan Ramos
01/09/2025
Special inspection requirement — Fire-Resistance Rated Construction
Luis Pichardo
01/03/2025
Filed — Alteration
INSTALL A NEW 5-TON MULTIZONE INVERTER HEAT-PUMP AND 5 INTERIOR AIR HANDLER UNITS.
B00873987-P3
01/03/2025
Filed — Alteration
INSTALL A NEW 5-TON MULTIZONE INVERTER HEAT-PUMP AND 5 INTERIOR AIR HANDLER UNITS.
B00803539-P2
12/17/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Luis Pichardo
12/17/2024
Special inspection requirement — Fire-Resistance Rated Construction
Luis Pichardo
12/17/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Luis Pichardo
12/17/2024
Special inspection requirement — Final
Juan Ramos
12/17/2024
Special inspection requirement — Fire-Resistance Rated Construction
Luis Pichardo
12/17/2024
Special inspection requirement — Lighting in dwelling units
Luis Pichardo
12/17/2024
Special inspection requirement — Final
Juan Ramos
12/16/2024
Permit issued — General Construction
B00873987-I1-GC
12/16/2024
Permit issued — General Construction
B00803539-I1-GC
08/07/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/14/2024
Permit issued — General Construction
B00803539-I1-GC
05/01/2024
Permit issued — General Construction
B00803539-I1-GC
03/07/2024
Filed — Alteration
INSTALL A NEW 5-TON MULTIZONE INVERTER HEAT-PUMP AND 5 INTERIOR AIR HANDLER UNITS.
B00873987-S2
03/07/2024
Filed — Alteration
INSTALL A NEW 5-TON MULTIZONE INVERTER HEAT-PUMP AND 5 INTERIOR AIR HANDLER UNITS.
B00803539-S2
03/01/2024
Special inspection requirement — Final
Juan Ramos
03/01/2024
Special inspection requirement — Mechanical Systems
Luis Pichardo
02/22/2024
Special inspection requirement — Mechanical Systems
Luis Pichardo
02/22/2024
Special inspection requirement — Final
Juan Ramos
12/08/2023
Permit issued — Plumbing
B00873987-S1-PL
10/06/2023
Permit issued — Plumbing
B00803539-S1-PL
09/13/2023
Permit issued — General Construction
B00873987-I1-GC
09/08/2023
Filed — Alteration
INSTALL A NEW 5-TON MULTIZONE INVERTER HEAT-PUMP AND 5 INTERIOR AIR HANDLER UNITS.
B00873987-P1
09/07/2023
Filed — Alteration
INSTALL A NEW 5-TON MULTIZONE INVERTER HEAT-PUMP AND 5 INTERIOR AIR HANDLER UNITS.
B00873987-S1
09/07/2023
Filed — Alteration
INSTALL A NEW 5-TON MULTIZONE INVERTER HEAT-PUMP AND 5 INTERIOR AIR HANDLER UNITS.
B00803539-S1
09/06/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Luis Pichardo
08/24/2023
Objection resolved — Addressed
08/24/2023
Objection resolved — Addressed
08/24/2023
Objection resolved — Addressed
08/24/2023
Objection resolved — Addressed
06/12/2023
Objection raised — Admin
06/12/2023
Objection raised — Scope
06/12/2023
Objection raised — Inspections
06/12/2023
Objection raised — Admin
06/07/2023
Filed — Alteration
INSTALL A NEW 5-TON MULTIZONE INVERTER HEAT-PUMP AND 5 INTERIOR AIR HANDLER UNITS.
B00873987-I1
05/05/2023
Permit issued — General Construction
B00803539-I1-GC
03/03/2023
Permit issued — General Construction
B00803539-I1-GC
02/06/2023
Objection resolved — Addressed
02/06/2023
Objection resolved — Addressed
02/06/2023
Objection resolved — Addressed
02/06/2023
Objection resolved — Addressed
01/27/2023
Objection raised — Other
01/27/2023
Objection raised — Other
Latest 60 of 66 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offEASTERN BH MECHANICAL INC01/24/2025
DOB NOWMechanical SystemsSigned-offEASTERN BH MECHANICAL INC01/24/2025
DOB NOWGeneral ConstructionSigned-offBW & SON CONSTRUCTION LLC12/16/2024
DOB NOWGeneral ConstructionSigned-offBW & SON CONSTRUCTION LLC12/16/2024
DOB NOWGeneral ConstructionSigned-offBW & SON CONSTRUCTION LLC05/14/2024
DOB NOWGeneral ConstructionSigned-offBW & SON CONSTRUCTION LLC05/01/2024
DOB NOWPlumbingSigned-offFLAVIO MECHANICAL CORP12/08/2023
DOB NOWPlumbingSigned-offFLAVIO MECHANICAL CORP10/06/2023
DOB NOWGeneral ConstructionSigned-offBW & SON CONSTRUCTION LLC09/13/2023
DOB NOWGeneral ConstructionSigned-offBW & SON CONSTRUCTION LLC05/05/2023
DOB NOWGeneral ConstructionSigned-offBW & SON CONSTRUCTION LLC03/03/2023
BISMHISSUEDMEDRA EXHAUST SYSTEMS COR10/02/2015
1 project · most recent 10/07/2023
General Wiring
FiledStatusContractorScope
10/07/2023Permit IssuedSUPREME ELECTRIC CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
03/24/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/07/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 19
DateRequirementInspectorRole
01/28/2025Fire-Resistant Penetrations and JointsLuis Pichardospecial
01/28/2025Fire-Resistance Rated ConstructionLuis Pichardoprogress
01/28/2025FinalJuan Ramosprogress
01/09/2025Lighting in dwelling unitsLuis Pichardoenergy_progress
01/09/2025Fire-Resistant Penetrations and JointsLuis Pichardospecial
01/09/2025FinalJuan Ramosprogress
01/09/2025Fire-Resistance Rated ConstructionLuis Pichardoprogress
12/17/2024Fire-Resistant Penetrations and JointsLuis Pichardospecial
12/17/2024Fire-Resistance Rated ConstructionLuis Pichardoprogress
12/17/2024Fire-Resistant Penetrations and JointsLuis Pichardospecial
12/17/2024FinalJuan Ramosprogress
12/17/2024Fire-Resistance Rated ConstructionLuis Pichardoprogress
12/17/2024Lighting in dwelling unitsLuis Pichardoenergy_progress
12/17/2024FinalJuan Ramosprogress
03/01/2024FinalJuan Ramosprogress
03/01/2024Mechanical SystemsLuis Pichardospecial
02/22/2024Mechanical SystemsLuis Pichardospecial
02/22/2024FinalJuan Ramosprogress
09/06/2023Fire-Resistant Penetrations and JointsLuis Pichardospecial
▾Documents — 70 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/27/2026B00803539-S2Request digital key ↗
08/27/2026B00803539-P2Request digital key ↗
08/27/2026B00803539-S1Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION2
07/16/2015321143482Open ↗
03/26/2015321100517Open ↗
▸BISWORK PERMIT APPLICATION1
10/02/2015321143482Open ↗
▸Seals & Professional Certifications32
▸DOB NOWProgress Inspector Seal & Signature12
09/02/2026B00873987-S2Open ↗
08/29/2026B00803539-S2Open ↗
08/29/2026B00873987-I1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/27/2026B00803539-P2Open ↗
08/27/2026B00803539-S2Open ↗
08/27/2026B00803539-S1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/02/2026B00873987-S2Open ↗
08/29/2026B00803539-S2Open ↗
08/29/2026B00873987-I1Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
07/16/2015321143482Open ↗
03/26/2015321100517Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
07/16/2015321143482Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
07/16/2015321143482Open ↗
▸Environmental & Asbestos13
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/27/2026B00803539-P2Open ↗
08/27/2026B00803539-S2Open ↗
08/27/2026B00803539-S1Open ↗
Showing 3 of 9 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
07/16/2015321143482Open ↗
03/26/2015321100517Open ↗
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED1
09/17/2015321143482Open ↗
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION1
09/28/2015321143482Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
07/16/2015321143482Open ↗
03/26/2015321100517Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
10/03/2017321143482Open ↗
▸Approvals, Objections & Sign-offs4
▸BISADMINISTRATIVE OBJECTIONS2
07/16/2015321143482Open ↗
03/26/2015321100517Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
09/22/2015321143482Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
10/03/2017321143482Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
10/03/2017321143482Open ↗
07/16/2015321143482Open ↗
03/26/2015321100517Open ↗
▸Filing & Intake Forms3
▸BISEFILING COVER SHEET2
07/16/2015321143482Open ↗
03/26/2015321100517Open ↗
▸BISBOROUGH INTAKE FORM1
10/03/2017321143482Open ↗