| Owner | Filings | Most Recent |
|---|---|---|
| ADVANCED CONSTRUCTION EQUIPMENT COR | 5 | 07/08/2026 |
| HARMAN SERVICE | 7 | 03/22/2026 |
| YX CONSTRUCTION | 8 | 03/22/2026 |
| COS CONSTRUCTION | 8 | 03/22/2026 |
| YC CONSTRUCTION INC | 1 | 03/22/2026 |
| 379 HARMAN BLDG | 14 | 03/22/2026 |
| DEWING FINISHING INC | 1 | 03/22/2026 |
| MORAVA KNITS INC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/28/2017 | $300K | — | — → — | $10/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| JOEL PHAGOO P.E. PLLC | 2 | 12/27/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| A1 EXPEDITING SERVICE | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SKILLED MECHANICAL INC | General Contractor | 4 | 07/08/2026 |
| ADVANCED CONSTRUCTION EQUIPMENT | General Contractor | 3 | 07/08/2026 |
| YX CONSTRUCTION INC | General Contractor | 3 | 03/22/2026 |
| R & T ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Signed-off | SKILLED MECHANICAL INC | 01/28/2019 |
| DOB NOW | Supported Scaffold | Signed-off | SKILLED MECHANICAL INC | 12/27/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | ADVANCED CONSTRUCTION EQU | 11/05/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | ADVANCED CONSTRUCTION EQU | 03/29/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | ADVANCED CONSTRUCTION EQU | 11/30/2017 |
| BIS | PL | ISSUED | RRP PLUMBING CORP | 01/02/2020 |
| BIS | EQ | ISSUED | YX CONSTRUCTION INC | 04/17/2019 |
| BIS | — | ISSUED | YX CONSTRUCTION INC | 02/22/2019 |
| BIS | — | ISSUED | COS CONSTRUCTION INC | 03/01/2018 |
| BIS | — | ISSUED | COS CONSTRUCTION INC | 03/01/2018 |
| BIS | — | ISSUED | COS CONSTRUCTION INC | 10/23/2017 |
| BIS | — | ISSUED | COS CONSTRUCTION INC | 10/23/2017 |
| BIS | EQ | RE-ISSUED | COS CONSTRUCTION INC | 10/17/2017 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/25/2019 | Complete | R & T ELECTRICAL CORP | — |
| 11/14/2018 | Complete | R & T ELECTRICAL CORP | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/28/2017 | Final | JOEL PHAGOO | progress |