| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/02/2026 | — | — | Gas, Water/Sanitary |
| 04/23/2021 | Signed-off | SAMUEL & SONS P & H INC | Gas, Water/Sanitary |
| 02/16/2021 | Permit Issued | SAMUEL & SONS P & H INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/13/2025 | Complete | EMPIRE ELECTRIC NYC LLC | — |
| 01/30/2024 | On Hold - Returned Check | SEGA ELECTRIC LLC | General Wiring |
| 03/09/2023 | Cancelled | LSM ELECTRICAL CONTNG INC | General Wiring |
| 01/16/2023 | Complete | LSM ELECTRICAL CONTNG INC | General Wiring |
| 06/17/2022 | Complete | RICHARD NEU | — |
| 06/13/2022 | Permit Issued | SEGA ELECTRIC LLC | General Wiring |
| 07/16/2020 | Permit Issued | GRAMERCY ELECTRIC INC | General Wiring |
| 03/12/2018 | Complete | 4000 ELECTRIC CORP | — |
| Owner | Filings | Most Recent |
|---|---|---|
| SDG MANAGEMENT | 65 | 09/13/2026 |
| T-MOBILE | 6 | 07/08/2026 |
| MNK ENTERPRISES | 6 | 07/08/2026 |
| JJS BUILDERS | 4 | 03/22/2026 |
| 157 BROADWAY ASSOCIATES | 94 | 03/22/2026 |
| 157 BROADWAY ASSOCS | 1 | 03/22/2026 |
| 157 BROADWAY SSOCIATES LL | 1 | 03/22/2026 |
| PIONEER CONSTRUCTION CORP | 1 | 03/22/2026 |
| MR. ED FOX. 157 BROADWAY | 1 | 03/22/2026 |
| OWNER OF 550 WEST 157 STR | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ABLE ARCHITECTS LLC | 6 | 08/02/2026 |
| KM CONSULTING ENGINEERS, INC. | 2 | 04/09/2026 |
| SKYPEAK LLC | 1 | 03/24/2026 |
| SOHAIL HUMAYUN | 1 | 10/21/2025 |
| SCHERER DESIGN GROUP | 1 | 09/10/2024 |
| ALLEN SHINFELD, P.E. PLLC | 2 | 01/29/2024 |
| TECTONIC ENGINEERING & SURVEYING CO | 1 | 11/27/2023 |
| JUNG H. CHOI, ARCHITECT, PC | 7 | 07/18/2023 |
| KMB DESIGN GROUP, LLC | 1 | 02/23/2023 |
| GBN ENGINEERING LLC | 1 | 01/05/2023 |
| PVE ENGINEERING | 1 | 10/12/2022 |
| ENTHINK ENGINEERS LLC | 1 | 06/17/2022 |
| COM-EX ENGINEERING OF NY, PLLC | 1 | 03/12/2020 |
| GREEN DESIGN | 1 | 03/12/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| ARCHIEL, LLC | 4 | 03/21/2026 |
| CONSTRUCTION PERMIT SERVICES | 3 | 03/21/2026 |
| BILTMORE GROUP | 2 | 03/21/2026 |
| NORTHEAST EXPEDITING | 10 | 03/21/2026 |
| SPEEDY INTERNATIONAL | 2 | 03/21/2026 |
| ATLANTIC BUILDING SUPPLY INC. | 2 | 03/21/2026 |
| CCM CONSULTING GROUP, INC. | 1 | 03/21/2026 |
| GC1 EXPEDITING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AREEBA INC | General Contractor | 6 | 03/21/2026 |
| JJS BUILDERS | General Contractor | 6 | 03/21/2026 |
| RCGC, LLC | General Contractor | 5 | 07/08/2026 |
| TRISTRUX LLC | General Contractor | 4 | 03/21/2026 |
| PASQUALE QUARATINO INC | General Contractor | 4 | 03/21/2026 |
| SAMUEL & SONS P & H INC | Plumbing | 3 | 07/08/2026 |
| SMARTLINK LLC | General Contractor | 3 | 03/21/2026 |
| DONE RIGHT KITCHEN EXHAUS | General Contractor | 3 | 03/21/2026 |
| MNK ENTERPRISES LLC | General Contractor | 2 | 07/08/2026 |
| ANTHONY COSTANZO | Electrical | 1 | 03/21/2026 |
| SQUAN CONSTRUCTION SERVIC | General Contractor | 1 | 07/08/2026 |
| WESTROCK MECHANICAL CORP | General Contractor | 1 | 07/08/2026 |
| PASQUALE QUARATINO INC | Plumbing | 1 | 07/08/2026 |
| GOTHAM COMMUNICATIONS LLC | General Contractor | 1 | 07/08/2026 |
| HARARI DAVID | Electrical | 1 | 03/21/2026 |
| JEAN-CLAUDE BELIZAIRE | Electrical | 1 | 03/21/2026 |
| JESUS CORPORAN | Electrical | 1 | 03/21/2026 |
| JOHN FRANCICA | Electrical | 1 | 03/21/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| SYED-NAQVI ALTAF | Electrical | 1 | 03/21/2026 |
| SYED-NAQVI, ALTAF | Electrical | 1 | 03/21/2026 |
| A CELL COMMUNICATIONS INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| KM CONSULTING NY, INC. | 5305 | 1 | 04/09/2026 |
| ABLE ARCHITECTS | 9452 | 3 | 04/02/2026 |
| SOHAIL HUMAYUN P E INC | 8457 | 1 | 10/21/2025 |
| SCHERER DESIGN GROUP | 7921 | 1 | 09/10/2024 |
| ALLEN SHINFELD, P.E. PLLC | 1305 | 2 | 01/29/2024 |
| TECTONIC ENGINEERING CONS | 106 | 2 | 11/27/2023 |
| LEO Y LEE ASSOCIATES | 2481 | 2 | 05/10/2023 |
| KMB DESIGN GROUP, LLC | 513 | 1 | 02/23/2023 |
| GBN ENGINEERING LLC | 4670 | 1 | 01/05/2023 |
| JUNG H CHOI ARCHITECT | 3020 | 1 | 02/16/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | DONE RIGHT KITCHEN EXHAUS | 12/12/2025 |
| DOB NOW | Mechanical Systems | Signed-off | WESTROCK MECHANICAL CORP | 10/18/2024 |
| DOB NOW | Antenna | Permit Issued | TRISTRUX LLC | 08/30/2024 |
| DOB NOW | Antenna | Permit Issued | TRISTRUX LLC | 01/19/2024 |
| DOB NOW | General Construction | Signed-off | RCGC, LLC | 01/17/2024 |
| DOB NOW | Plumbing | Signed-off | PASQUALE QUARATINO INC | 08/25/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | MNK ENTERPRISES LLC | 06/15/2023 |
| DOB NOW | General Construction | Signed-off | AREEBA INC | 04/17/2023 |
| DOB NOW | Antenna | Signed-off | A CELL COMMUNICATIONS INC | 03/03/2023 |
| DOB NOW | Antenna | Signed-off | GOTHAM COMMUNICATIONS LLC | 02/24/2023 |
| DOB NOW | General Construction | Signed-off | AREEBA INC | 10/28/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | MNK ENTERPRISES LLC | 06/17/2022 |
| DOB NOW | Plumbing | Signed-off | SAMUEL & SONS P & H INC | 11/12/2021 |
| DOB NOW | General Construction | Permit Issued | RCGC, LLC | 10/13/2021 |
| DOB NOW | Plumbing | Permit Issued | SAMUEL & SONS P & H INC | 08/16/2021 |
| DOB NOW | General Construction | Permit Issued | RCGC, LLC | 07/29/2021 |
| DOB NOW | Plumbing | Signed-off | SAMUEL & SONS P & H INC | 07/06/2021 |
| DOB NOW | Antenna | Signed-off | SQUAN CONSTRUCTION SERVIC | 04/02/2021 |
| DOB NOW | Antenna | Signed-off | SMARTLINK LLC | 05/08/2020 |
| DOB NOW | Sidewalk Shed | Permit Issued | JJS BUILDERS | 10/02/2018 |
| DOB NOW | Sidewalk Shed | Permit Issued | JJS BUILDERS | 03/13/2018 |
| BIS | OT | ISSUED | RCGC, LLC | 10/13/2021 |
| BIS | OT | ISSUED | RCGC, LLC | 10/08/2020 |
| BIS | OT | ISSUED | RCGC, LLC | 10/08/2020 |
| BIS | OT | ISSUED | RCGC, LLC | 06/04/2020 |
| BIS | OT | ISSUED | RCGC, LLC | 06/04/2020 |
| BIS | OT | ISSUED | RCGC, LLC | 03/13/2020 |
| BIS | OT | ISSUED | RCGC, LLC | 03/13/2020 |
| BIS | OT | ISSUED | LUCKY GENERAL CONSTR CORP | 07/03/2018 |
| BIS | PL | ISSUED | HARLEY PLUMB & HEAT INC | 09/06/2017 |
| BIS | MH | ISSUED | AQEL SHEET METAL INC | 08/29/2017 |
| BIS | OT | ISSUED | LUCKY GENERAL CONSTR CORP | 05/09/2017 |
| BIS | OT | ISSUED | LUCKY GENERAL CONSTR CORP | 12/16/2016 |
| BIS | FP | ISSUED | MASTER FIRE SYSTEMS, INC | 09/06/2016 |
| BIS | OT | ISSUED | RC3 ELECTRIC, LLC | 06/09/2016 |
| BIS | OT | ISSUED | LUCKY GENERAL CONSTR CORP | 02/19/2016 |
| BIS | PL | ISSUED | HARLEY PLUMB & HEAT INC | 11/24/2015 |
| BIS | OT | ISSUED | HARLEY PLUMBING & HEATING | 11/24/2015 |
| BIS | OT | ISSUED | LUCKY GENERAL CONSTR CORP | 09/28/2015 |
| BIS | PL | ISSUED | PLUMBING & HTG DOCTOR INC | 05/06/2015 |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/15/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/12/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/22/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 06/16/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 06/09/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/29/2022 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| 02/25/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/24/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/19/2021 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 11/19/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/19/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/06/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/27/2026 | Tenant Protection Plan Compliance | JINN HWANG | special |
| 03/27/2026 | Final | JINN HWANG | progress |
| 03/27/2026 | Fire-Resistant Penetrations and Joints | JINN HWANG | special |
| 03/27/2026 | Interior lighting power | JINN HWANG | energy_progress |
| 03/27/2026 | Lighting controls | JINN HWANG | energy_progress |
| 03/27/2026 | Fire-Resistance Rated Construction | JINN HWANG | progress |
| 03/27/2026 | Energy Code Compliance Inspections | JINN HWANG | progress |
| 03/24/2026 | Tenant Protection Plan Compliance | — | special |
| 03/13/2026 | Final | — | progress |
| 02/18/2026 | Interior lighting power | JINN HWANG | energy_progress |
| 02/18/2026 | Lighting controls | JINN HWANG | energy_progress |
| 02/02/2026 | Tenant Protection Plan Compliance | JINN HWANG | special |
| 01/31/2026 | Fire-Resistant Penetrations and Joints | JINN HWANG | special |
| 01/31/2026 | Final | JINN HWANG | progress |
| 01/29/2024 | Fire-Resistance Rated Construction | ALLEN SHINFELD | progress |
| 01/29/2024 | Interior lighting power | ALLEN SHINFELD | energy_progress |
| 01/29/2024 | Lighting controls | ALLEN SHINFELD | energy_progress |
| 01/29/2024 | Tenant Protection Plan Compliance | ALLEN SHINFELD | special |
| 01/29/2024 | Fire-Resistant Penetrations and Joints | ALLEN SHINFELD | special |
| 01/29/2024 | Energy Code Compliance Inspections | ALLEN SHINFELD | progress |
| 01/29/2024 | Final | ALLEN SHINFELD | progress |
| 07/18/2023 | Tenant Protection Plan Compliance | — | special |
| 02/16/2023 | Tenant Protection Plan Compliance | — | special |
| 08/28/2022 | Energy Code Compliance Inspections | ALAN DUDLEY | progress |
| 08/28/2022 | Structural Stability – Alterations of existing buildings | Leo Lee | special |