Office with commercial, 7-19 stories
38 EAST 19TH STREET
MANHATTAN · BIN 1080755
💬 Discuss this project
1900Year Built
10Stories
O6Building Class
M1-5MZoning
101,724 sfGross Floor Area
20Units
LL97 Covered1 Active Violation 0 unresolved · 1 paperwork only ▸FISP: SWARMP
Office with commercial, 7-19 stories · Owner of record: 880 Broadway Tenant · 12,400 sf lot · 8.2 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofCannon Hill Partners, Atlassian18p · 4 filings · 20 docs
Floor 10General construction and demolition modifications, multiple 61p · 9 filings · 20 docs
Floor 9Pipe scaffold installation47p · 9 filings · 20 docs
Floor 8General construction and demolition modifications, multiple 63p · 9 filings · 20 docs
Floor 7Netflix38p · 5 filings · 20 docs
Floor 6Netflix28p · 5 filings · 20 docs
Floor 5Netflix27p · 7 filings · 20 docs
Floor 4Atlassian32p · 3 filings · 20 docs
Floor 3Netflix, Cannon Hill PartnersUnder Construction110p · 11 filings · 20 docs
Floor 2Cannon Hill Partners65p · 11 filings · 20 docs
Floor 1Cannon Hill Partners52p · 7 filings · 20 docs
MezzanineCannon Hill Partners3p · 2 filings · 20 docs
CellarABC Carpet & Home4p · 1 filing · 3 docs
Site & exteriorPipe scaffold installation24p · 2 filings · 11 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
33 Realty Associates6303/21/2026
Cannon Hill Capital Partners1604/09/2026
880 Broadway Tenant103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/10/2025$38.0M—33 REALTY ASSOCIATES, L.P. → 880 BROADWAY TENANT, LLC$374/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Rizzo Group2503/21/2026
Codegreen2403/21/2026
Hierarch-E203/21/2026
Milrose Consultants803/21/2026
Synergy Building Consultants303/21/2026
Spring Scaffolding403/21/2026
Patuxent Engineering403/21/2026
Efg Consulting403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Clune Construction CoGeneral Contractor3107/08/2026
Icon InteriorsGeneral Contractor2007/08/2026
Core Scaffold SystemsScaffold2007/08/2026
JT Magen & CompanyGeneral Contractor1407/08/2026
Spring ScaffoldingScaffold807/08/2026
Armon MechanicalPlumbing707/08/2026
Armon MechanicalFire Protection507/08/2026
Darby Construction ServiceGeneral Contractor507/08/2026
Par Fire ProtectionFire Protection407/08/2026
Par Plumbing CoPlumbing307/08/2026
Urban IntelligenceScaffold303/21/2026
Abco-Peerless SprinklerFire Protection207/08/2026
Ashland PlumbingPlumbing207/08/2026
Plumbing P & HPlumbing203/22/2026
Sirina Fire ProtectionFire Protection107/08/2026
R.j.electrical ContractorElectrical103/21/2026
Metflow Fire ControlFire Protection107/08/2026
Gotham Wiring LicensedElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Milrose Consultants2003506/24/2026
Domani Inspection Service8432101/17/2025
Amaracon Testing & Inspec5842406/13/2024
Codegreen5101606/04/2024
Chen Engineering Services1826201/29/2021
HT Engineering6274101/31/2020
Building Lifecycle
All (300)Filed (68)Permit Issued (80)Signed Off (38)Facade (FISP) (12)Violation (26)Inspection (22)Objection (24)Special Inspection (30)
09/15/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
06/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Christopher Drutjons
06/26/2026
Special inspection requirement — Fire-Resistance Rated Construction
Christopher Drutjons
06/26/2026
Special inspection requirement — Final
Stephanie Lan
06/26/2026
Special inspection requirement — Sprayed fire-resistant materials
Christopher Drutjons
06/24/2026
Filed — Alteration
Removal & installation of interior non-bearing partitions and related finishes as per drawings filed herewith. No change in use, egress or occupancy.
M01352998-P1
05/29/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/03/2026
Permit issued — Plumbing
M01353006-I1-EW-SP
03/24/2026
Permit issued — Sprinklers
M01353006-I1-PL
03/11/2026
Permit issued — Structural
M01361571-I1-ST
03/11/2026
Permit issued — General Construction
M01352998-I1-GC
03/09/2026
Filed — Alteration
Removal & installation of interior non-bearing partitions and related finishes as per drawings filed herewith. No change in use, egress or occupancy.
M01352998-I1
03/09/2026
Filed — Alteration
Structural modifications as per plans filed herewith. NO change in use, egress or occupancy.
M01361571-I1
03/04/2026
Objection resolved — Addressed
03/03/2026
Permit issued — Mechanical Systems
M01353002-I1-MS
02/27/2026
Filed — Alteration
Installation of 2 drinking fountains & 112 new sprinkler heads. No change in use, egress or occupancy.
M01353006-I1
02/27/2026
Filed — Alteration
Fitout of 3rd floor - supply, return, and exhaust ductwork. No change in use, egress or occupancy.
M01353002-I1
02/20/2026
Objection raised — Electrical
02/07/2026
Filed — No Work
M01232773-I1
02/04/2026
Signed off — Alteration
M01339324-I1
01/29/2026
Special inspection requirement — Sprinkler Systems
Christopher Drutjons
01/29/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Christopher Drutjons
01/29/2026
Special inspection requirement — Post-installed Anchors
Christopher Drutjons
01/08/2026
Permit issued — Suspended Scaffold
M01339324-I1-SC
12/23/2025
Filed — Alteration
M01339324-I1
05/28/2025
Special inspection requirement — Public Assembly Emergency Lighting
HATIM ELSAID
04/11/2025
Signed off — Alteration
Installation of 2 drinking fountains & 112 new sprinkler heads. No change in use, egress or occupancy.
M01054501-I1
04/04/2025
Signed off — Alteration
M01054489-I1
04/04/2025
Signed off — Alteration
M01022950-I1
03/31/2025
Signed off — Alteration
Tenant fit out of commercial office space. Scope is the installation of ductwork, terminal units and additional electric heat to serve the space.
M01054495-I1
02/05/2025
Signed off — Alteration
Sprinkler modifications taking place on the 2nd, 3rd floors & roof as per plans filed herewith. No change to use, egress or occupancy.
M08040401-I1
01/30/2025
Signed off — Alteration
General construction / demolition modifications taking place on the 2nd, 3rd & 8th through 10th floors as per plans filed herewith. No change to use, egress or occupancy.
M08040228-I1
01/29/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY PLYWOOD FENCE AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
M00890354-S1
01/29/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY PLYWOOD FENCE AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
M00890354-I1
01/17/2025
Filed — Alteration
Sprinkler modifications taking place on the 2nd, 3rd floors & roof as per plans filed herewith. No change to use, egress or occupancy.
M08040401-P2
01/13/2025
Signed off — Alteration
Mechanical modifications taking place on the 1st & 2nd floors as per plans filed herewith. No change to use, egress nor occupancy.
M08041097-I1
01/13/2025
Signed off — Alteration
Mechanical modifications taking place on the 2nd, 3rd floors & roof as per plans filed herewith. No change to use, egress or occupancy.
M08040325-I1
12/19/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
12/03/2024
Filed — Alteration
General construction / demolition modifications taking place on the 2nd, 3rd & 8th through 10th floors as per plans filed herewith. No change to use, egress or occupancy.
M08040228-P1
12/03/2024
Special inspection requirement — Final
JOHN MCMONAGLE
11/22/2024
Special inspection requirement — Mechanical Systems
JOHN MCMONAGLE
11/22/2024
Special inspection requirement — Final
JOHN MCMONAGLE
11/21/2024
Filed — Alteration
Mechanical modifications taking place on the 1st & 2nd floors as per plans filed herewith. No change to use, egress nor occupancy.
M08041097-P1
11/14/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
11/14/2024
Special inspection requirement — Sprinkler Systems
JOHN MCMONAGLE
11/14/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOHN MCMONAGLE
11/14/2024
Special inspection requirement — Post-installed Anchors
JOHN MCMONAGLE
11/04/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
10/29/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
10/29/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/26/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
10/09/2024
Signed off — Alteration
Mechanical modifications taking place on the 8th thru 10th floors as per plans filed herewith. No change in use, egress nor occupancy.
M08027427-I1
10/03/2024
Signed off — Alteration
General construction modifications taking place on the 1st, 2nd, 3rd, 8th & 10th floors as per plans filed herewith. No change to use, egress nor occupancy.
M08041058-I1
10/02/2024
Special inspection requirement — Final
JOHN MCMONAGLE
10/02/2024
Special inspection requirement — Heating Systems
JOHN MCMONAGLE
10/02/2024
Special inspection requirement — Mechanical Systems
JOHN MCMONAGLE
10/01/2024
Filed — Alteration
Mechanical modifications taking place on the 8th thru 10th floors as per plans filed herewith. No change in use, egress nor occupancy.
M08027427-P1
09/24/2024
Signed off — Alteration
Sprinkler modifications taking place on the 1st & 2nd floors as per plans filed herewith. No change to use, egress nor occupancy.
M08041108-I1
09/24/2024
Permit issued — Mechanical Systems
M01054495-I1-MS
09/24/2024
Permit issued — General Construction
M01054489-I1-GC
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersPermit IssuedAbco-Peerless Sprinkler04/03/2026
DOB NOWPlumbingSigned-offAshland Plumbing03/24/2026
DOB NOWStructuralSigned-offJT Magen & Company03/11/2026
DOB NOWGeneral ConstructionPermit IssuedJT Magen & Company03/11/2026
DOB NOWMechanical SystemsSigned-offJT Magen & Company03/03/2026
DOB NOWSuspended ScaffoldSigned-offTC Zone01/08/2026
DOB NOWMechanical SystemsSigned-offJT Magen & Company09/24/2024
DOB NOWGeneral ConstructionSigned-offJT Magen & Company09/24/2024
DOB NOWStructuralSigned-offJT Magen & Company09/24/2024
DOB NOWPlumbingSigned-offAshland Plumbing06/27/2024
DOB NOWSprinklersSigned-offAbco-Peerless Sprinkler06/26/2024
DOB NOWGeneral ConstructionSigned-offJT Magen & Company06/21/2024
DOB NOWMechanical SystemsSigned-offJT Magen & Company06/18/2024
DOB NOWSupported ScaffoldSigned-offSpring Scaffolding06/13/2024
DOB NOWConstruction FenceSigned-offSpring Scaffolding06/13/2024
DOB NOWGeneral ConstructionSigned-offClune Construction Co06/04/2024
DOB NOWStructuralSigned-offJT Magen & Company05/24/2024
DOB NOWPlumbingSigned-offArmon Mechanical04/02/2024
DOB NOWPlumbingSigned-offArmon Mechanical04/01/2024
DOB NOWPlumbingSigned-offArmon Mechanical04/01/2024
DOB NOWSprinklersSigned-offArmon Mechanical03/26/2024
DOB NOWMechanical SystemsSigned-offClune Construction Co03/21/2024
DOB NOWMechanical SystemsSigned-offClune Construction Co03/21/2024
DOB NOWGeneral ConstructionSigned-offClune Construction Co03/21/2024
DOB NOWGeneral ConstructionSigned-offClune Construction Co03/21/2024
DOB NOWMechanical SystemsSigned-offClune Construction Co02/13/2024
DOB NOWStructuralSigned-offDarby Construction Service11/14/2023
DOB NOWGeneral ConstructionSigned-offDarby Construction Service09/22/2023
DOB NOWMechanical SystemsSigned-offDarby Construction Service09/15/2023
DOB NOWConstruction FenceSigned-offSpring Scaffolding06/15/2023
DOB NOWSupported ScaffoldSigned-offSpring Scaffolding06/15/2023
DOB NOWSprinklersSigned-offArmon Mechanical03/27/2023
DOB NOWSupported ScaffoldSigned-offCore Scaffold Systems03/20/2023
DOB NOWSprinklersSigned-offArmon Mechanical03/17/2023
DOB NOWMechanical SystemsSigned-offClune Construction Co03/14/2023
DOB NOWPlumbingSigned-offArmon Mechanical03/14/2023
DOB NOWPlumbingSigned-offArmon Mechanical03/10/2023
DOB NOWPlumbingSigned-offArmon Mechanical03/10/2023
DOB NOWSprinklersSigned-offArmon Mechanical03/09/2023
DOB NOWSprinklersSigned-offArmon Mechanical03/09/2023
+ 60 more permits on file
2 projects · most recent 02/27/2026
FiledStatusContractorScope
02/27/2026Permit IssuedAbco-Peerless Sprinkler109 heads
04/05/2021Permit IssuedSirina Fire Protection—
1 project · most recent 02/27/2026
Water/Sanitary
FiledStatusContractorScope
02/27/2026Signed-offAshland PlumbingWater/Sanitary
11 projects · most recent 08/14/2026
General Wiring Lighting
FiledStatusContractorScope
08/14/2026Permit IssuedD&D Electl Construction CoGeneral Wiring
01/02/2025CompleteM.C. Electrical NYGeneral Wiring
01/02/2025CompleteM.C. Electrical NYGeneral Wiring
01/02/2025CompleteM.C. Electrical NYGeneral Wiring
08/09/2024CompleteCrana ElectricGeneral Wiring
09/10/2023CompleteMarkey ElectricalGeneral Wiring, Lighting
02/21/2023Complete5 J'S Electl Conts—
09/01/2022CompletePolo Electric Corp D/B/AGeneral Wiring
12/15/2020CompleteUpdate Systems ElectricalGeneral Wiring
11/04/2020CompleteFreedom Electl & DataGeneral Wiring, Lighting
08/15/2018CompleteV. Vass Electric—
1 project · most recent 03/09/2026
FiledStatusContractorScope
03/09/2026Signed-offJT Magen & Company1 scope_items
▾Field Inspections (DOB CAP) — 22
DateTypeResultReport
09/15/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/29/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/19/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/14/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/04/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/29/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
10/29/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/26/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/27/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/20/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/20/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/16/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/03/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/27/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/27/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/26/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/14/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
04/30/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/15/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/29/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/18/2023Pass-Final SP Permit WithdrawalPassView ↗
05/15/2023Fail-Final SP Permit WithdrawalFailView ↗
▾Special Inspection Requirements (DOB NOW) — 107
DateRequirementInspectorRole
06/26/2026Fire-Resistance Rated ConstructionChristopher Drutjonsprogress
06/26/2026FinalStephanie Lanprogress
06/26/2026Fire-Resistant Penetrations and JointsChristopher Drutjonsspecial
06/26/2026Sprayed fire-resistant materialsChristopher Drutjonsspecial
01/29/2026Sprinkler SystemsChristopher Drutjonsspecial
01/29/2026Post-installed AnchorsChristopher Drutjonsspecial
01/29/2026Fire-Resistant Penetrations and JointsChristopher Drutjonsspecial
05/28/2025Public Assembly Emergency LightingHATIM ELSAIDprogress
12/03/2024FinalJOHN MCMONAGLEprogress
11/22/2024Mechanical SystemsJOHN MCMONAGLEspecial
11/22/2024FinalJOHN MCMONAGLEprogress
11/14/2024Sprinkler SystemsJOHN MCMONAGLEspecial
11/14/2024Fire-Resistant Penetrations and JointsJOHN MCMONAGLEspecial
11/14/2024Post-installed AnchorsJOHN MCMONAGLEspecial
10/02/2024FinalJOHN MCMONAGLEprogress
10/02/2024Heating SystemsJOHN MCMONAGLEspecial
10/02/2024Mechanical SystemsJOHN MCMONAGLEspecial
09/13/2024Mechanical SystemsJOHN MCMONAGLEspecial
09/13/2024FinalJOHN MCMONAGLEprogress
09/13/2024Heating SystemsJOHN MCMONAGLEspecial
06/11/2024FinalJOHN MCMONAGLEprogress
06/05/2024Structural Wood FrameHATIM ELSAIDprogress
06/05/2024MasonryHATIM ELSAIDspecial
06/05/2024Concrete - Cast-In-PlaceHATIM ELSAIDspecial
06/05/2024Post-installed AnchorsHATIM ELSAIDspecial
Latest 25 of 107.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
NetflixOfficeFloors 3, 5–7
Project M01352998 Alteration · Permit Entire · 03/09/2026
Project M01361571 Alteration · Permit Entire · 03/09/2026
Project M01353002 Alteration · Permit Entire · 02/27/2026
Project M01353006 Alteration · Permit Entire · 02/27/2026
Project M01054489 Alteration · LOC Issued · 06/13/2024
Project M01054495 Alteration · LOC Issued · 06/13/2024
Project M01054501 Alteration · LOC Issued · 06/13/2024
Project M00450647 Alteration · LOC Issued · 02/05/2021
Project M00197579 Alteration · LOC Issued · 09/25/2019
Project M00200904 Alteration · LOC Issued · 08/09/2019
Project M00200930 Alteration · LOC Issued · 08/09/2019
Project M00200932 Alteration · LOC Issued · 08/09/2019
AtlassianOfficeFloor 4
Project M00896582 Alteration · LOC Issued · 09/18/2023
Project M00921700 Alteration · LOC Issued · 09/18/2023
Project M00896588 Alteration · LOC Issued · 09/13/2023
Cannon Hill PartnersOfficeFloors 1–3, Roof
Project M08040325 Alteration · LOC Issued · 03/03/2023
Project M08040392 Alteration · LOC Issued · 03/03/2023
Project M08040401 Alteration · LOC Issued · 03/03/2023
Project M08041097 Alteration · LOC Issued · 02/28/2023
Project M08041108 Alteration · LOC Issued · 02/28/2023
Project M08041328 Alteration · LOC Issued · 02/28/2023
ABC Carpet & HomeRetailCellar
Project M00298154 Alteration · LOC Issued · 01/31/2020
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 1,379 on file (BIS + DOB NOW)
▸Plans & Drawings71
▸DOB NOWPlans/Sketch46
09/06/2026M00040026-I1Request digital key ↗
09/05/2026M00060422-I1Request digital key ↗
08/31/2026M00826403-P1Request digital key ↗
Showing 3 of 46 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler8
09/05/2026M00298154-I1Request digital key ↗
09/04/2026M00200908-I1Request digital key ↗
09/04/2026M00200908-P1Request digital key ↗
Showing 3 of 8 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems5
09/05/2026M00197493-I1Request digital key ↗
09/04/2026M00197535-I1Request digital key ↗
Showing 2 of 5 on file for this type
▸DOB NOWPlans/Sketch - Plumbing3
09/05/2026M00200932-I1Request digital key ↗
09/05/2026M00200936-I1Request digital key ↗
09/05/2026M00200930-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural2
09/04/2026M00197579-I1Request digital key ↗
Showing 1 of 2 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold2
09/05/2026M00060422-I1Request digital key ↗
09/05/2026M00060422-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed2
09/05/2026M00060422-I1Request digital key ↗
09/05/2026M00060422-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Standpipe1
09/04/2026M00450647-I1Request digital key ↗
▸Applications & Permits297
▸BISPLAN / WORK APPROVAL APPLICATION176
12/04/2025123502192Open ↗
07/14/2025123502192Open ↗
06/11/2025123660528Open ↗
Showing 3 of 176 on file for this type
▸BISWORK PERMIT APPLICATION72
12/20/2023123660528Open ↗
02/24/2023123358641Open ↗
02/24/2023123358641Open ↗
Showing 3 of 72 on file for this type
▸DOB NOWLPC Approval/Permit42
08/31/2026M08041097-I1Open ↗
08/27/2026M00896582-I1Open ↗
Showing 2 of 42 on file for this type
▸BISPLACE OF ASSEMBLY5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Zoning, Tax Lot & Property Records6
▸BISZONING EXHIBIT I: CERTIFICATION6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸Seals & Professional Certifications280
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION113
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 113 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature67
09/06/2026M00040026-I1Open ↗
09/05/2026M00197493-I1Open ↗
09/05/2026M00197493-P1Open ↗
Showing 3 of 67 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature47
10/17/2026M08040401-P1Open ↗
09/23/2026M00200904-I1Open ↗
09/23/2026M00200904-I1Open ↗
Showing 3 of 47 on file for this type
▸DOB NOWProgress Inspector Seal & Signature27
09/04/2026M01352998-I1Open ↗
09/04/2026M01352998-I1Open ↗
09/02/2026M08027378-I1Open ↗
Showing 3 of 27 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment81
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE38
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 38 on file for this type
▸BISSCHEDULE B - PLUMBING24
05/29/2025123660528Open ↗
05/01/2025123660528Open ↗
12/20/2024123660528Open ↗
Showing 3 of 24 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA7
11/09/2023123663268Open ↗
03/23/2023123528619Open ↗
04/30/2021123663277Open ↗
Showing 3 of 7 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISEQUIPMENT USE PERMITS5
03/22/2022123502192Open ↗
03/22/2022123502192Open ↗
03/22/2022123502192Open ↗
Showing 3 of 5 on file for this type
▸BISSTANDPIPE INSP REPORT : FP-841
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT1
03/22/2022123502192Open ↗
▸Safety & Tenant Protection4
▸BISSTREET TREE CHECKLIST4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Environmental & Asbestos96
▸DOB NOWDEP ACP-5: Asbestos Assessment Report58
09/05/2026M00197493-P1Open ↗
09/05/2026M00197493-I1Open ↗
09/05/2026M00298154-I1Open ↗
Showing 3 of 58 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)24
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 24 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISDEP FORM V5 - ASBESTOS VARIANCE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISASBESTOS-EXEMPTION (ASB4)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISAPPLICANT SHALL PROVIDE 1 ACP-21 FORMPRIOR TO SIGN OFF: TRU6883MN182
01/28/2022123442195Open ↗
Showing 1 of 2 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance48
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS23
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 23 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY8
01/28/2022120625868Open ↗
01/28/2022120625868Open ↗
06/21/2021122090496Open ↗
Showing 3 of 8 on file for this type
▸BISENERGY CODE 1ST REVIEW COMPLETE6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISTR8: Energy Code Progress Inspections2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
10/20/2022122090496Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
10/19/2022122090496Open ↗
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWPreliminary Commissioning Report Certification1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports55
▸BISTECHNICAL REPORT: RESPONSIBILITY49
10/03/2024123358641Open ↗
11/01/2022123689810Open ↗
11/01/2022123689810Open ↗
Showing 3 of 49 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISSTRUCTURAL STABILITY - EXISTING BUILDINGS1
08/26/2022140797109Open ↗
▸BISTECHNICAL REPORT: PILE DRIVING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISMECHANICAL SYSTEMS1
10/19/2022122090496Open ↗
▸Approvals, Objections & Sign-offs145
▸BISLANDMARKS APPROVAL30
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 30 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST28
10/04/2024123358641Open ↗
12/06/2023123663268Open ↗
03/24/2023123528619Open ↗
Showing 3 of 28 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE19
12/04/2025123502192Open ↗
07/14/2025123502192Open ↗
01/27/2025123502192Open ↗
Showing 3 of 19 on file for this type
▸BISLANDMARKS SIGNOFF18
10/04/2024123358641Open ↗
03/24/2023123528619Open ↗
11/02/2022123689810Open ↗
Showing 3 of 18 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 16 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION12
02/28/2022123442195Open ↗
Showing 1 of 12 on file for this type
▸BISADMINISTRATIVE OBJECTIONS10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISSUPERSEDING LETTER8
12/20/2023123660528Open ↗
02/24/2023123358641Open ↗
Showing 2 of 8 on file for this type
▸BISFINAL3
10/03/2024123358641Open ↗
10/19/2022122090496Open ↗
08/26/2022140797109Open ↗
▸BISTRANSIT AUTHORITY/MTA/PANYNJ APPROVAL1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership99
▸BISCOST AFFIDAVIT94
04/30/2025123660528Open ↗
02/12/2025123660528Open ↗
12/19/2024123660528Open ↗
Showing 3 of 94 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW35
10/08/2024123660528Open ↗
12/06/2023123663268Open ↗
10/19/2022122090496Open ↗
Showing 3 of 5 on file for this type
▸Filing & Intake Forms138
▸BISADDITIONAL INFORMATION54
08/14/2025123502192Open ↗
05/01/2025123660528Open ↗
01/29/2025123660528Open ↗
Showing 3 of 54 on file for this type
▸BISEFILING COVER SHEET47
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 47 on file for this type
▸BISBOROUGH INTAKE FORM36
02/24/2023123358641Open ↗
02/16/2023123358641Open ↗
Showing 2 of 36 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Other Documents48
▸DOB NOWProof of Historic Building28
08/31/2026M08041097-I1Open ↗
08/27/2026M00896582-I1Open ↗
Showing 2 of 28 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISPLOT DIAGRAM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTCO - Supporting Documents2
08/14/2025123502192Open ↗
08/14/2025123502192Open ↗
▸DOB NOWIRA Certification1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type