Miscellaneous two family
38 HEMLOCK STREET
STATEN ISLAND · Arden Heights-Rossville · BIN 5092813
💬 Discuss this project
1987Year Built
2Stories
B9Building Class
R3-1Zoning
2,496 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Miscellaneous two family · 3,500 sf lot · 0.71 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 6 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR112/06/2023
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281112/06/2023
Building Lifecycle
All (19)Filed (1)Permit Issued (1)Signed Off (1)Violation (1)Objection (10)Special Inspection (5)
12/01/2025
Signed off — Alteration
INSTALLATION OF SOLAR PANELS, ROOFTOP, RAILED, GRID-TIED, 13 MODULES, 5.2 KW
S00972426-I1
01/23/2024
Permit issued — Solar
S00972426-I1-SL
01/12/2024
Objection resolved — Addressed
01/12/2024
Objection resolved — Addressed
01/02/2024
Objection resolved — Addressed
01/02/2024
Objection resolved — Addressed
01/02/2024
Objection resolved — Addressed
12/26/2023
Objection raised — Other
12/26/2023
Objection raised — Other
12/26/2023
Objection raised — Zoning
12/26/2023
Objection raised — Other
12/26/2023
Objection raised — Other
12/06/2023
Filed — Alteration
INSTALLATION OF SOLAR PANELS, ROOFTOP, RAILED, GRID-TIED, 13 MODULES, 5.2 KW
S00972426-I1
12/06/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
12/06/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
12/06/2023
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
12/06/2023
Special inspection requirement — Final
Mina Makar
12/06/2023
Special inspection requirement — Air barrier - visual inspection
Mina Makar
04/18/2012
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR01/23/2024
1 project · most recent 12/05/2023
FiledStatusContractorScope
12/05/2023CompleteISLAND ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
12/06/2023Fire-Resistant Penetrations and JointsMina Makarspecial
12/06/2023Structural Stability – Alterations of existing buildingsMina Makarspecial
12/06/2023Energy Code Compliance InspectionsMina Makarprogress
12/06/2023FinalMina Makarprogress
12/06/2023Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 6 on file (BIS + DOB NOW)
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
09/01/2026S00972426-I1Open ↗
09/01/2026S00972426-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026S00972426-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/01/2026S00972426-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026S00972426-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S00972426-I1Open ↗