← Back
Office with commercial, 7-19 stories
381 Park Ave South
381 PARK AVENUE SOUTH · Gramercy · BIN 1018159
💬 Discuss this project
1910Year Built
16Stories
O6Building Class
C6-4AZoning
209,041 sfGross Floor Area
97Units
LL97 Covered2 Open Violations ▸FISP: UNSAFE
Office with commercial, 7-19 stories · Owner of record: 373-381 PAS ASSOCIATES, LLC · 12,449 sf lot · 16.79 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivilGeneralOther
Permit Issued — active, not yet Signed-off
RoofUnder Construction2p · 2 filings · 8 docs
Floor 15Under Construction1 filing · 5 docs
Floor 14
Floor 133p · 1 filing · 2 docs
Floor 12Under Construction1p · 1 filing · 4 docs
Floor 11Under Construction23p · 4 filings · 20 docs
Floor 10Under Construction1p · 1 filing · 4 docs
Floor 9
Floor 8Under Construction10p · 1 filing · 8 docs
Floor 7Under Construction1 filing · 4 docs
Floor 6Under Construction19p · 4 filings · 20 docs
Floor 5
Floor 4Under Construction13p · 3 filings · 16 docs
Floor 3Under Construction9p · 5 filings · 20 docs
Floor 2Under Construction1p · 1 filing · 5 docs
Floor 1
Cellar1p · 1 filing · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ATCO PROPERTIES MGMT18209/07/2026
373-381 PAS ASSOCIATES29403/22/2026
323-381 PAS ASSOCIATES LL103/22/2026
373-381 PAS AOOCIATE LLC103/22/2026
373 PARK AVE S LLC103/22/2026
373-381 PARK AVE S. LLC303/22/2026
ATCO PROPERTIES MANAGE303/22/2026
ATCO MANAGEMENT303/22/2026
ATCO PROPERTY MANAGEMENT303/22/2026
373-381 PARK AVENUE SOUTH, LLC2003/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ARCHETYPE CONSULTANTS7803/21/2026
JAM CONSULTANTS, INC.403/21/2026
VALERIO ARCHITECTS703/21/2026
AE DESIGN SOLUTION203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ESSENTIAL DESIGN & BUILDGeneral Contractor3307/08/2026
PREMIER SANITATION LLCGeneral Contractor910/01/2026
ALLSTATE SPRINKLER LLCFire Protection907/08/2026
ANDAMIO SCAFFOLDING LLCGeneral Contractor809/07/2026
INTERIOR BUILDING SERVICEGeneral Contractor609/16/2026
BERN CONCEPT INCGeneral Contractor603/21/2026
EVEREST SCAFFOLDING INCGeneral Contractor507/08/2026
CURRENT FIRE PROTECTION INCFire Protection407/08/2026
GMJ ELECTRIC CORPElectrical403/22/2026
GIOVANNI MARTINI CONTRACTGeneral Contractor307/08/2026
AUTHENTIC PLBG CORPPlumbing307/08/2026
AMERICAN CONSTRUCTION MANGeneral Contractor307/08/2026
PFL MECHANICAL CORPPlumbing208/13/2026
KG SPRINKLER CORPFire Protection207/08/2026
RRP PLUMBING CORPPlumbing107/08/2026
GEORGE CHAVEZElectrical103/21/2026
ROBERT B. SAMUELS, INC.Electrical103/22/2026
BEDROCK MECHANICAL INCFire Protection107/08/2026
GRUSHINSKY PIPNG & HTG INFire Protection108/11/2026
METRO STAR CONTRACTING CGeneral Contractor107/01/2026
PRAT ENTERPRISES CORPGeneral Contractor108/12/2026
ARCON PLBG SOLUTIONSPlumbing107/08/2026
HYDROKINETIC PLBG & HTG IPlumbing107/08/2026
PLBG P & H INCPlumbing107/08/2026
BOROWIDE ELECT'L CONTR'SElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CROSSCHECK INSPECTION SER544408/11/2026
ROSINI ENGINEERING, PC3282408/05/2026
KZ ENGINEERING, P.C.4665107/10/2026
WAYPOINT CONSULTING GROUP6175206/15/2026
WONG ARCHITECT1272401/15/2026
DOMANI INSPECTION SERVICE843407/24/2024
JACK GREEN ASSOCIATES4222106/28/2024
HRF SERVICES CORP5616302/29/2024
ASDA ARCHITECTURE + DESIG2015704/18/2023
Building Lifecycle
All (300)Filed (66)Permit Issued (71)Signed Off (31)Facade (FISP) (11)Violation (56)Inspection (35)Special Inspection (30)
09/15/2026
Permit issued — Mechanical Systems
M01371247-I1-MS
09/04/2026
Permit issued — General Construction
M01454774-I1-GC
09/02/2026
Permit issued — Sidewalk Shed
M00986247-I1-SH
08/21/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/13/2026
Permit issued — General Construction
M01440598-I1-GC
08/12/2026
Permit issued — Plumbing
M01432638-I1-PL
08/11/2026
Filed — Alteration
INTERIOR RENOVATION OF EXISTING PARTITION AND CONSTRUCTION OF PARTITION. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
M01440598-I1
08/11/2026
Permit issued — General Construction
M01374585-I1-GC
08/11/2026
Permit issued — Mechanical Systems
M01432626-I1-MS
08/10/2026
Permit issued — Plumbing
M01432638-I1-EW-SP
08/05/2026
Filed — Alteration
INSTALLATION OF NEW PLUMBING FIXTURES (SINK, DISHWASHER, WATER HEATER) IN NEW PANTRY ROOMS AND INSTALLATION OF SPRINKLER SYSTEM FOR ENTIRE FLOOR
M01432638-I1
08/05/2026
Filed — Alteration
INSTALLATION OF AC UNITS, EXHAUST FAN, DUCTS, PIPING, DAMPERS & AIR OUTLETS
M01432626-I1
08/04/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
EUGENE BIFULCO
08/04/2026
Special inspection requirement — Final
EUGENE BIFULCO
07/24/2026
Permit issued — Suspended Scaffold
M01428550-I1-SC
07/21/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
David Rosini
07/20/2026
Special inspection requirement — Energy Code Compliance Inspections
David Rosini
07/20/2026
Special inspection requirement — Maintenance information
David Rosini
07/20/2026
Special inspection requirement — HVAC-R and service water heating system controls
David Rosini
07/20/2026
Special inspection requirement — Shutoff dampers
David Rosini
07/20/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
David Rosini
07/20/2026
Special inspection requirement — HVAC-R and service water heating equipment
David Rosini
07/17/2026
Special inspection requirement — Mechanical Systems
David Rosini
07/17/2026
Special inspection requirement — Sprinkler Systems
David Rosini
07/17/2026
Special inspection requirement — Final
David Rosini
07/10/2026
Filed — Alteration
INSTALLATION OF A SUSPENDED SCAFFOLD FOR FACADE INSPECTION AND REPAIR AS PER PLAN SUBMITTED
M01428550-I1
06/29/2026
Permit issued — General Construction
M01416991-I1-GC
06/24/2026
Permit issued — General Construction
M01413815-I1-GC
06/17/2026
Filed — Alteration
INTERIOR RENOVATION OF EXISTING PARTITION AND CONSTRUCTION OF PARTITION. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
M01413815-I1
06/15/2026
Filed — Alteration
M01416991-I1
06/15/2026
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
06/11/2026
Permit issued — Sidewalk Shed
M00986247-I1-SH
06/08/2026
Filed — Alteration
M01374585-I1
06/08/2026
Special inspection requirement — Masonry
Alejandro Molina
06/08/2026
Special inspection requirement — Post-installed Anchors
Alejandro Molina
06/08/2026
Special inspection requirement — Final
Alejandro Molina
06/03/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
05/20/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
05/07/2026
Filed — Alteration
FILING GC FOR INTERIOR RENOVATION WITH DEMOLITION OF EXISTING PARTITION AND CONSTRUCTION OF NEW PARTITION. EGRESS TO REMAIN THE SAME.
M01361511-P1
04/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
EUGENE BIFULCO
04/30/2026
Special inspection requirement — Final
EUGENE BIFULCO
04/28/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/20/2026
Permit issued — Sprinklers
M01371240-I1-EW-SP
03/19/2026
Permit issued — Plumbing
M01371237-I1-PL
03/18/2026
Permit issued — Sidewalk Shed
M00986247-I1-SH
03/17/2026
Filed — Alteration
FILING PL FOR INSTALLATION OF NEW PLUMBING FIXTURES
M01371237-I1
03/17/2026
Filed — Alteration
FILING MS FOR INSTALLATION OF DUCTWORKS, DUCT INSULATIONS, AND AIR SUPPLY OUTLETS ONLY
M01371247-I1
03/17/2026
Filed — Alteration
FILING SP FOR INSTALLATION OF SPRINKLER SYSTEM FOR ENTIRE FLOOR
M01371240-I1
03/16/2026
Special inspection requirement — HVAC-R and service water heating equipment
David Rosini
03/16/2026
Special inspection requirement — HVAC-R and service water heating system controls
David Rosini
03/16/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
David Rosini
03/12/2026
Special inspection requirement — Sprinkler Systems
David Rosini
03/12/2026
Special inspection requirement — Mechanical Systems
David Rosini
03/12/2026
Special inspection requirement — Final
David Rosini
03/09/2026
Inspection — Pass-Final PL - More than 10 Requested Floors
Pass
View inspection ↗
03/06/2026
Permit issued — General Construction
M01361511-I1-GC
03/03/2026
Filed — Alteration
FILING GC FOR INTERIOR RENOVATION WITH DEMOLITION OF EXISTING PARTITION AND CONSTRUCTION OF NEW PARTITION. EGRESS TO REMAIN THE SAME.
M01361511-I1
02/19/2026
Permit issued — General Construction
M01359149-I1-GC
02/17/2026
Filed — Alteration
M01359149-I1
02/13/2026
Special inspection requirement — Final
Nicholas Tjartjalis
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedINTERIOR BUILDING SERVICE09/15/2026
DOB NOWGeneral ConstructionPermit IssuedPREMIER SANITATION LLC09/04/2026
DOB NOWSidewalk ShedPermit IssuedANDAMIO SCAFFOLDING LLC09/02/2026
DOB NOWGeneral ConstructionPermit IssuedINTERIOR BUILDING SERVICE08/13/2026
DOB NOWPlumbingPermit IssuedPFL MECHANICAL CORP08/12/2026
DOB NOWGeneral ConstructionPermit IssuedPRAT ENTERPRISES CORP08/11/2026
DOB NOWMechanical SystemsPermit IssuedINTERIOR BUILDING SERVICE08/11/2026
DOB NOWPlumbingPermit IssuedGRUSHINSKY PIPNG & HTG IN08/10/2026
DOB NOWSuspended ScaffoldPermit IssuedVICHIHEL RESTORATION INC07/24/2026
DOB NOWGeneral ConstructionPermit IssuedMETRO STAR CONTRACTING C06/29/2026
DOB NOWGeneral ConstructionPermit IssuedINTERIOR BUILDING SERVICE06/24/2026
DOB NOWSidewalk ShedPermit IssuedANDAMIO SCAFFOLDING LLC06/11/2026
DOB NOWSprinklersPermit IssuedBEDROCK MECHANICAL INC03/20/2026
DOB NOWPlumbingPermit IssuedPFL MECHANICAL CORP03/19/2026
DOB NOWSidewalk ShedPermit IssuedANDAMIO SCAFFOLDING LLC03/18/2026
DOB NOWGeneral ConstructionPermit IssuedINTERIOR BUILDING SERVICE03/06/2026
DOB NOWGeneral ConstructionPermit IssuedINTERIOR BUILDING SERVICE02/19/2026
DOB NOWGeneral ConstructionSigned-offPREMIER SANITATION LLC01/30/2026
DOB NOWGeneral ConstructionPermit IssuedPREMIER SANITATION LLC01/26/2026
DOB NOWGeneral ConstructionSigned-offPREMIER SANITATION LLC12/29/2025
DOB NOWGeneral ConstructionSigned-offPREMIER SANITATION LLC12/16/2025
DOB NOWSidewalk ShedPermit IssuedANDAMIO SCAFFOLDING LLC12/05/2025
DOB NOWGeneral ConstructionSigned-offAMERICAN CONSTRUCTION MAN05/01/2025
DOB NOWSprinklersSigned-offHYDROKINETIC PLBG & HTG I01/27/2025
DOB NOWGeneral ConstructionSigned-offAMERICAN CONSTRUCTION MAN01/09/2025
DOB NOWSidewalk ShedPermit IssuedANDAMIO SCAFFOLDING LLC01/06/2025
DOB NOWGeneral ConstructionSigned-offAMERICAN CONSTRUCTION MAN08/29/2024
DOB NOWMechanical SystemsSigned-offESSENTIAL DESIGN & BUILD05/09/2024
DOB NOWGeneral ConstructionSigned-offESSENTIAL DESIGN & BUILD05/09/2024
DOB NOWMechanical SystemsSigned-offESSENTIAL DESIGN & BUILD04/19/2024
DOB NOWSprinklersSigned-offCURRENT FIRE PROTECTION I04/18/2024
DOB NOWPlumbingSigned-offAUTHENTIC PLBG CORP04/16/2024
DOB NOWSprinklersPermit IssuedALLSTATE SPRINKLER LLC04/04/2024
DOB NOWGeneral ConstructionSigned-offESSENTIAL DESIGN & BUILD03/21/2024
DOB NOWMechanical SystemsPermit IssuedBERN CONCEPT INC03/01/2024
DOB NOWPlumbingSigned-offALLSTATE SPRINKLER LLC02/26/2024
DOB NOWPlumbingSigned-offRRP PLUMBING CORP02/20/2024
DOB NOWGeneral ConstructionPermit IssuedBERN CONCEPT INC02/09/2024
DOB NOWSidewalk ShedPermit IssuedANDAMIO SCAFFOLDING LLC01/12/2024
DOB NOWPlumbingSigned-offAUTHENTIC PLBG CORP08/16/2023
+ 60 more permits on file
1 project · most recent 08/05/2026
Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
08/05/2026Permit IssuedINTERIOR BUILDING SERVICEAir Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Lg ZRNU363B8AA 36,000 BTU · Vrf Indoor ×2
ZRNU483M3AA 48,000 BTU · Fan Coil Indoor ×2
ZRNU963B8AA 96,000 BTU · Vrf Outdoor ×2
— ZRUM072BTE6 72,000 BTU · Condensing Unit ×1
ZRUM096BTE6 96,000 BTU · Condensing Unit ×1
ZRUM192BTE6 192,000 BTU · Condensing Unit ×1
Heating
Lg ZRNU363B8AA 40,000 BTU · Vrf Indoor ×2
ZRNU483M3AA 54,000 BTU · Fan Coil Indoor ×2
ZRNU963B8AA 107,000 BTU · Vrf Outdoor ×2
— ZRUM072BTE6 81,000 BTU · Condensing Unit ×1
ZRUM096BTE6 108,000 BTU · Condensing Unit ×1
ZRUM192BTE6 216,000 BTU · Condensing Unit ×1
Ventilation
Greenheck CSP-A390-VG 300 CFM · Exhaust Fan ×2
SQ-M100-VG 710 CFM · Exhaust Fan ×1
3 projects · most recent 08/05/2026
FiledStatusContractorScope
08/05/2026Permit IssuedGRUSHINSKY PIPNG & HTG IN76 heads
03/17/2026Permit IssuedBEDROCK MECHANICAL INC123 heads
02/29/2024Permit IssuedALLSTATE SPRINKLER LLC11 heads
2 projects · most recent 08/05/2026
Water/Sanitary
FiledStatusContractorScope
08/05/2026Permit IssuedPFL MECHANICAL CORPWater/Sanitary
03/17/2026Permit IssuedPFL MECHANICAL CORPWater/Sanitary
25 projects · most recent 04/13/2026
General Wiring
FiledStatusContractorScope
04/13/2026Permit IssuedCITYWIDE ELEC'L WIRING INGeneral Wiring
04/13/2026Permit IssuedCITYWIDE ELEC'L WIRING INGeneral Wiring
05/13/2025Permit IssuedGMJ ELECTRIC CORPGeneral Wiring
04/16/2024Permit IssuedGMJ ELECTRIC CORPGeneral Wiring
03/26/2024CompleteGMJ ELECTRIC CORPGeneral Wiring
03/26/2024CompleteGMJ ELECTRIC CORP—
02/27/2024CompleteGMJ ELECTRIC CORPGeneral Wiring
02/27/2024CompleteGMJ ELECTRIC CORPGeneral Wiring
02/27/2024CompleteGMJ ELECTRIC CORPGeneral Wiring
02/27/2024CompleteGMJ ELECTRIC CORPGeneral Wiring
01/04/2024Permit IssuedBOROWIDE ELECT'L CONTR'S—
08/10/2023CompleteGOTHAM WIRING LICENSEDGeneral Wiring
05/31/2023CompleteOMD ELECTRICAL CORP1 meters, 1 new_meters
10/28/2022Permit IssuedGMJ ELECTRIC CORPGeneral Wiring
07/27/2022CompleteGMJ ELECTRIC CORPGeneral Wiring
1 project · most recent 02/13/2024
Sidewalk Shed
FiledStatusContractorScope
02/13/2024Permit IssuedANDAMIO SCAFFOLDING LLCSidewalk Shed
1 project · most recent 07/10/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
07/10/2026Permit IssuedPRAT ENTERPISE, CORPSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 35
DateTypeResultReport
08/21/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/15/2026Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
06/03/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
05/20/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
04/28/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/09/2026Pass-Final PL - More than 10 Requested FloorsPassView ↗
12/23/2025Pass-Final PL - More than 10 Requested FloorsPassView ↗
10/22/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
10/16/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
09/22/2025Pass-Final PL - More than 10 Requested FloorsPassView ↗
04/07/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/10/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/05/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/22/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/25/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
07/24/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/01/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/26/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/28/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/01/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
03/20/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/14/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/12/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
02/06/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/06/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
Latest 25 of 35.
▾Special Inspection Requirements (DOB NOW) — 116
DateRequirementInspectorRole
08/04/2026Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
08/04/2026FinalEUGENE BIFULCOprogress
07/21/2026Fire-Resistant Penetrations and JointsDavid Rosinispecial
07/20/2026HVAC-R and service water piping design and insulationDavid Rosinienergy_progress
07/20/2026HVAC-R and service water heating equipmentDavid Rosinienergy_progress
07/20/2026HVAC-R and service water heating system controlsDavid Rosinienergy_progress
07/20/2026Maintenance informationDavid Rosinienergy_progress
07/20/2026Shutoff dampersDavid Rosinienergy_progress
07/20/2026Energy Code Compliance InspectionsDavid Rosiniprogress
07/17/2026Sprinkler SystemsDavid Rosinispecial
07/17/2026Mechanical SystemsDavid Rosinispecial
07/17/2026FinalDavid Rosiniprogress
06/08/2026FinalAlejandro Molinaprogress
06/08/2026MasonryAlejandro Molinaspecial
06/08/2026Post-installed AnchorsAlejandro Molinaspecial
04/30/2026FinalEUGENE BIFULCOprogress
04/30/2026Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
03/16/2026HVAC-R and service water heating equipmentDavid Rosinienergy_progress
03/16/2026HVAC-R and service water piping design and insulationDavid Rosinienergy_progress
03/16/2026HVAC-R and service water heating system controlsDavid Rosinienergy_progress
03/12/2026Mechanical SystemsDavid Rosinispecial
03/12/2026Sprinkler SystemsDavid Rosinispecial
03/12/2026FinalDavid Rosiniprogress
02/13/2026FinalNicholas Tjartjalisprogress
12/10/2025FinalKING WONGprogress
Latest 25 of 116.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Corcoran GroupOfficeFloor 3
Project M01371237 Alteration · Permit Entire · 03/17/2026
Project M01371240 Alteration · Permit Entire · 03/17/2026
ValerioOfficeFloor 9
Project M00787987 Alteration · LOC Issued · 10/04/2022
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 2,085 on file (BIS + DOB NOW)
▸Plans & Drawings64
▸DOB NOWPlans/Sketch55
09/06/2026M00084903-I1Request digital key ↗
09/03/2026M00569795-P1Request digital key ↗
09/03/2026M00569795-I1Request digital key ↗
Showing 3 of 55 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler7
09/05/2026M00235924-I1Request digital key ↗
09/05/2026M00235956-I1Request digital key ↗
09/05/2026M00266311-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/04/2026M00340848-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/04/2026M00340849-I1Request digital key ↗
▸Applications & Permits336
▸BISPLAN / WORK APPROVAL APPLICATION195
02/10/2026123311754Open ↗
02/04/2026123311754Open ↗
01/28/2025121982346Open ↗
Showing 3 of 195 on file for this type
▸BISWORK PERMIT APPLICATION134
10/01/2024122504316Open ↗
12/01/2023122247363Open ↗
10/17/2023123392319Open ↗
Showing 3 of 134 on file for this type
▸BISPLACE OF ASSEMBLY4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications533
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION208
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 208 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST76
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 76 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT74
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 74 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature64
09/28/2026M01440598-I1Open ↗
09/06/2026M00084903-I1Open ↗
09/05/2026M00235956-I1Open ↗
Showing 3 of 64 on file for this type
▸DOB NOWProgress Inspector Seal & Signature55
09/28/2026M01043728-P1Open ↗
09/28/2026M00569795-I1Open ↗
09/02/2026M01432626-I1Open ↗
Showing 3 of 55 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature40
09/28/2026M00569795-I1Open ↗
09/19/2026M00235956-I1Open ↗
09/02/2026M01371240-I1Open ↗
Showing 3 of 40 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Trade Schedules & Equipment127
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE52
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 52 on file for this type
▸BISSELF-CERT PLUMBING NOTICE29
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 29 on file for this type
▸BISSCHEDULE B - PLUMBING16
07/23/2024122504316Open ↗
05/10/2024122247363Open ↗
05/02/2024122247363Open ↗
Showing 3 of 16 on file for this type
▸BISEQUIPMENT USE PERMITS14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT12
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 12 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Safety & Tenant Protection4
▸BISSTREET TREE CHECKLIST2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTENANT PROTECTION PLAN AND NOTES2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Environmental & Asbestos161
▸BISASBESTOS: CERTIFICATION (DEP ACP5)85
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 85 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report60
09/28/2026M01440598-I1Open ↗
09/05/2026M00235956-I1Open ↗
09/04/2026M00340849-I1Open ↗
Showing 3 of 60 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'12
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 12 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Energy Compliance197
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS107
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 107 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS52
11/03/2025122247363Open ↗
02/25/2021123504662Open ↗
Showing 2 of 52 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY14
11/03/2025122247363Open ↗
10/21/2024122504316Open ↗
10/15/2024122504316Open ↗
Showing 3 of 14 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)7
11/12/2025122512762Open ↗
11/03/2025122247363Open ↗
10/28/2025122002634Open ↗
Showing 3 of 7 on file for this type
▸BISTR8: Energy Code Progress Inspections6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISENERGY CODE COMPLIANCE INSPECTIONS4
11/03/2025122247363Open ↗
05/22/2024123425114Open ↗
05/22/2024123392319Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BIS* HVAC INSULATION AND SEALING2
11/03/2025122247363Open ↗
02/18/2025122504316Open ↗
▸DOB NOWEN2: As Built Energy Analysis2
09/02/2026M00734296-I1Open ↗
Showing 1 of 2 on file for this type
▸BISNYCECC ANALYSIS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports58
▸BISTECHNICAL REPORT: RESPONSIBILITY52
11/03/2025122247363Open ↗
10/21/2024122504316Open ↗
10/15/2024122504316Open ↗
Showing 3 of 52 on file for this type
▸BISMECHANICAL SYSTEMS2
11/03/2025122247363Open ↗
02/18/2025122504316Open ↗
▸BISHYDRAULIC FLOW CALCULATIONS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BIS* FINAL INSPECTION DIRECTIVE 14 OF 19751
02/13/2023102353935Open ↗
▸BISSTRUCTURAL STEEL - HIGH STRENGTH BOLTING1
02/13/2023120286127Open ↗
▸Approvals, Objections & Sign-offs178
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST101
11/12/2025122512762Open ↗
11/05/2025122247363Open ↗
10/29/2025121982346Open ↗
Showing 3 of 101 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION49
02/17/2023103173744Open ↗
02/17/2023100592208Open ↗
02/17/2023100592208Open ↗
Showing 3 of 49 on file for this type
▸BISADMINISTRATIVE OBJECTIONS16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 16 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE5
08/09/2021123311754Open ↗
08/04/2021123311754Open ↗
Showing 2 of 5 on file for this type
▸BISFINAL4
11/03/2025122247363Open ↗
02/18/2025122504316Open ↗
11/07/2023121390770Open ↗
Showing 3 of 4 on file for this type
▸BISSUPERSEDING LETTER3
10/01/2024122504316Open ↗
11/08/2023121390770Open ↗
Showing 2 of 3 on file for this type
▸Cost, Insurance & Ownership222
▸BISCOST AFFIDAVIT201
11/03/2025122247363Open ↗
09/09/2025123208518Open ↗
12/05/2023122374796Open ↗
Showing 3 of 201 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW313
11/12/2025122512762Open ↗
10/23/2025122002634Open ↗
10/23/2025121982346Open ↗
Showing 3 of 13 on file for this type
▸BISOK TO ISSUE TCO PENDING RESOLUTION OFOPEN FACADE VIOLATION - AFFIDAVIT ATTACHED5
11/03/2025123311754Open ↗
03/10/2025123311754Open ↗
11/14/2024123311754Open ↗
Showing 3 of 5 on file for this type
▸BISCIVIL PENALTY AFFIDAVIT/REQUEST3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Filing & Intake Forms172
▸BISEFILING COVER SHEET98
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 98 on file for this type
▸BISBOROUGH INTAKE FORM43
10/17/2023123392319Open ↗
10/17/2023123425114Open ↗
10/17/2023123060999Open ↗
Showing 3 of 43 on file for this type
▸BISADDITIONAL INFORMATION24
10/22/2024122504316Open ↗
07/23/2024122504316Open ↗
05/10/2024122247363Open ↗
Showing 3 of 24 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸Other Documents15
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISSupporting Document: Fee Exempt3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISSupporting Document: Fee Deferment3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWManufacturer's Specifications1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWCalculations1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type