Whole building & multi-floor projectsLong Island University2 filings
Project B08020813Signed-off · 10/12/2023
INSTALLATION OF A TEMPORARY AUDITORIUM SCAFFOLD PLATFORM SYSTEM AS PER PLANS IN CONJUNCTION WITH STRUCTURAL WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH 2014 NYC BUILDING CODE, CHAPTER 33.
On file for this project
4 documents
INSTALLATION OF TEMPORARY WORK PLATFORMS @ MULTIPLE LEVELS AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. WORK PLATFORMS TO COMPLY WITH CHAPTER 33 OF NYC BUIDLING CODE.
On file for this project
3 documents
RoofMR. Michael NG Long Island University Brooklyn Campus2p · 3 filings · 17 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems
FILING HEREWITH DRAWINGS TO REMOVE AND REPLACE ONE (1) NEW WOOD WATER TANK AND ASSOCIATED PIPING TO EXISTING SYSTEM. THIS APPLICATION DO NOT REQUIRE A NEW OR AMENDED CERTIFICATE OF OCCUPANCY AS THERE IS NO CHANGE IN USE, EXISTS OR OCCUPANCY.
On file for this project
3 documents
INSTALL TWO (2) REPLACEMENT SPLIT AC SYSTEMS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents · 1 drawing sheet
Project B00776871Signed-off · 11/27/2023
Filing to reflect the removal of the 7th floor scope.
On file for this project
23 documents
Floor 7MR. Michael NG Long Island University Brooklyn Campus1p · 2 filings · 17 docs
ArchitectureEquipmentMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Supported Scaffold
Project B00776871Signed-off · 11/27/2023
Filing to reflect the removal of the 7th floor scope.
On file for this project
23 documents
INSTALLATION OF A TEMPORARY MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. MATERIAL HOIST TO COMPLY WITH NYC BUILDING CODE, CHAPTER 33.
On file for this project
3 documents
Floor 6MR. Michael NG Long Island University Brooklyn Campus, Brook1p · 4 filings · 17 docs
ArchitectureDMEquipmentMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Supported Scaffold
Project B00776871Signed-off · 11/27/2023
Filing to reflect the removal of the 7th floor scope.
On file for this project
23 documents
INSTALLATION OF TEMPORARY SCAFFOLD AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE.
On file for this project
6 documents
Interior Selected demolition of Floors Cellar - through 6th Floor of paramount theater located at 385 flatbush avenue extension. No change in egress use or occupancy.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 5MR. Michael NG Long Island University Brooklyn Campus, Brook3p · 4 filings · 17 docs
ArchitectureEquipmentMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Supported Scaffold
Project B00776871Signed-off · 11/27/2023
Filing to reflect the removal of the 7th floor scope.
On file for this project
23 documents
INSTALLATION OF TEMPORARY SCAFFOLD AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE.
On file for this project
6 documents · 1 drawing sheet
Interior Selected demolition of Floors Cellar - through 6th Floor of paramount theater located at 385 flatbush avenue extension. No change in egress use or occupancy.
On file for this project
3 documents
Latest 3 of 4 filings on this floor.
Floor 4MR. Michael NG Long Island University Brooklyn Campus, Brook2p · 5 filings · 17 docs
ArchitectureEquipmentMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Protection and Mechanical Methods · Supported Scaffold
INSTALL TWO (2) REPLACEMENT SPLIT AC SYSTEMS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents · 1 drawing sheet
Project B00776871Signed-off · 11/27/2023
Filing to reflect the removal of the 7th floor scope.
On file for this project
23 documents
INSTALLATION OF TEMPORARY SCAFFOLD AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE.
On file for this project
6 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 3Live Nation, MR. Michael NG Long Island University Brooklyn 6p · 7 filings · 17 docs
ArchitectureDMElectricalEquipmentFire ProtectionLandscapeMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Sprinklers · Supported Scaffold
SPRINKLER/ STANDPIPE WORK AS PER PLANS FILED HEREWITH.
On file for this project
12 documents · 3 drawing sheets
Project B00776871Signed-off · 11/27/2023
Filing to reflect the removal of the 7th floor scope.
On file for this project
23 documents
INSTALLATION OF TEMPORARY SCAFFOLD AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE.
On file for this project
6 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 2Live Nation, MR. Michael NG Long Island University Brooklyn 9p · 10 filings · 17 docs
ArchitectureDMElectricalEquipmentFire ProtectionGeneralLandscapeMechanicalStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Sprinklers · Supported Scaffold
SPRINKLER/ STANDPIPE WORK AS PER PLANS FILED HEREWITH.
On file for this project
12 documents · 3 drawing sheets
Project B00776871Signed-off · 11/27/2023
Filing to reflect the removal of the 7th floor scope.
On file for this project
23 documents
INSTALLATION OF TEMPORARY SCAFFOLD AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE.
On file for this project
6 documents · 2 drawing sheets
Latest 3 of 10 filings on this floor.
Floor 1Live Nation, MR. Michael NG Long Island University Brooklyn 7p · 11 filings · 20 docs
ArchitectureDMElectricalEquipmentFire ProtectionGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Protection and Mechanical Methods · Sprinklers · Supported Scaffold
PLUMBING AND SPRINKLER SCOPE FILED IN ASSOCIATION WITH INTERIOR RENOVATION.
On file for this project
10 documents
SPRINKLER/ STANDPIPE WORK AS PER PLANS FILED HEREWITH.
On file for this project
12 documents · 3 drawing sheets
Project B00776871Signed-off · 11/27/2023
Filing to reflect the removal of the 7th floor scope.
On file for this project
23 documents
Latest 3 of 11 filings on this floor.
CellarLive Nation, MR. Michael NG Long Island University Brooklyn 10p · 9 filings · 20 docs
ArchitectureDMFire ProtectionGeneralPlumbingStructural
Issued Permit Scope
Foundation · General Construction · Plumbing · Sprinklers
PLUMBING AND SPRINKLER SCOPE FILED IN ASSOCIATION WITH INTERIOR RENOVATION.
On file for this project
10 documents
SPRINKLER/ STANDPIPE WORK AS PER PLANS FILED HEREWITH.
On file for this project
12 documents · 4 drawing sheets
Project B00776871Signed-off · 11/27/2023
Filing to reflect the removal of the 7th floor scope.
On file for this project
23 documents
Latest 3 of 9 filings on this floor.
BasementLong Island University2p · 1 filing · 18 docs
Plumbing
Project B08044382Signed-off · 11/02/2023
Provide new 2 hot water boilers and associated pumps for future new tenant. No change in use and egress.
On file for this project
20 documents
Sub-BasementLong Island University2 filings · 18 docs
Mechanical
Issued Permit Scope
Boiler Equipment · Mechanical Systems
Project B08044860Signed-off · 01/25/2024
removal of abandoned boiler. no change in use or egress. Existing Oil Tank will be abandoned, The Abandoned process will be filed under different application by Plumber.
On file for this project
4 documents
Project B08044382Signed-off · 11/02/2023
Provide new 2 hot water boilers and associated pumps for future new tenant. No change in use and egress.
On file for this project
20 documents
Site & exteriorLong Island University8 filings · 20 docs
ArchitectureCivilEquipmentGeneralMechanicalStructural
Issued Permit Scope
Construction Fence · General Construction · Protection and Mechanical Methods · Sidewalk Shed · Supported Scaffold
INSTALLATION OF 300 PSF SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE 2014 CODE NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
4 documents · 8 drawing sheets
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY BETAMAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 3 drawing sheets
Latest 3 of 8 filings on this floor.
Filed — no permit issuedBrooklyn Paramount Theater1 filing · 3 docs
GeneralMechanical
INSTALLATION OF TEMPORARY PLYWOOD FENCE AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents · 5 drawing sheets