| Owner | Filings | Most Recent |
|---|---|---|
| BRICKSTONE GROUP | 9 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/22/2025 | $2.4M | — | — → — | $1,301/sf building |
| 04/16/2024 | $1.3M | — | — → — | $710/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CQ&J CORPORATION | 5 | 03/10/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| WM ARCH | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MORELL BUILDERS INC | General Contractor | 3 | 03/21/2026 |
| TWO BROTHERS K CONST CORP | General Contractor | 3 | 03/21/2026 |
| PLBG P & H INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CL ENGINEERING P.C. | 6781 | 2 | 03/10/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | MORELL BUILDERS INC | 10/09/2024 |
| DOB NOW | Plumbing | Signed-off | PLBG P & H INC | 05/07/2024 |
| DOB NOW | Structural | Signed-off | TWO BROTHERS K CONST CORP | 05/07/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/23/2025 | Cancelled | FLOW STATE ELECTRIC, LLC | General Wiring |
| 11/08/2024 | Complete | FLOW STATE ELECTRIC, LLC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/27/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 02/14/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/13/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/01/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/01/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/01/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/10/2025 | Fenestration areas | CALVIN TRAN | energy_progress |
| 03/10/2025 | Metering | CALVIN TRAN | energy_progress |
| 03/10/2025 | HVAC-R and service water heating system controls | CALVIN TRAN | energy_progress |
| 03/10/2025 | Interior lighting power | CALVIN TRAN | energy_progress |
| 03/10/2025 | Insulation placement and R values | CALVIN TRAN | energy_progress |
| 03/10/2025 | Fire-Resistant Penetrations and Joints | CHRISTIAN LOZADA | special |
| 03/10/2025 | Structural Stability – Alterations of existing buildings | CHRISTIAN LOZADA | special |
| 03/10/2025 | Energy Code Compliance Inspections | CALVIN TRAN | progress |
| 03/10/2025 | Final | CALVIN TRAN | progress |
| 03/10/2025 | Fire-Resistance Rated Construction | CALVIN TRAN | progress |
| 03/10/2025 | Structural Wood Frame | CALVIN TRAN | progress |
| 03/10/2025 | Air barrier - visual inspection | CALVIN TRAN | energy_progress |
| 03/10/2025 | HVAC-R and service water piping design and insulation | CALVIN TRAN | energy_progress |
| 03/10/2025 | Fenestration air leakage | CALVIN TRAN | energy_progress |
| 03/10/2025 | HVAC-R and service water heating equipment | CALVIN TRAN | energy_progress |
| 03/10/2025 | Fenestration and door U-factor and product ratings | CALVIN TRAN | energy_progress |
| 01/29/2025 | Maintenance information | CALVIN TRAN | energy_progress |
| 01/29/2025 | Energy Code Compliance Inspections | CALVIN TRAN | progress |
| 01/29/2025 | HVAC-R and service water heating equipment | CALVIN TRAN | energy_progress |
| 01/29/2025 | HVAC-R and service water heating system controls | CALVIN TRAN | energy_progress |
| 01/29/2025 | HVAC-R and service water piping design and insulation | CALVIN TRAN | energy_progress |
| 11/18/2024 | Energy Code Compliance Inspections | CALVIN TRAN | progress |
| 11/18/2024 | HVAC-R and service water heating equipment | CALVIN TRAN | energy_progress |
| 11/18/2024 | HVAC-R and service water piping design and insulation | CALVIN TRAN | energy_progress |
| 11/18/2024 | Maintenance information | CALVIN TRAN | energy_progress |