RoofUnder Construction23p · 5 filings · 20 docs
ArchitectureEquipmentMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Structural
Installation of outrigger for facade repair & inspection.
On file for this project
6 documents · 1 drawing sheet
Filing herewith for the proposed removal of an exterior stair not required for egress and the minor masonry and parapet restoration required after removal. No change in use, egress or occupancy
On file for this project
3 documents · 1 drawing sheet
Facade restoration. No change in egress, use or occupancy.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Penthouse121p · 6 filings · 20 docs
ArchitectureCivilDMFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Herewith Filing Plumbing and Sprinkler work in conjunction with buildout of new bathroom and pantry, Application is filed in conjunction with Alt-1 M01129462-I1
On file for this project
30 documents · 8 drawing sheets
Filing herewith for the proposed removal of an exterior stair not required for egress and the minor masonry and parapet restoration required after removal. No change in use, egress or occupancy
On file for this project
3 documents
Project M79054162Signed-off · 12/03/2021
Filing herewith drawings indicating plumbing modifications as shown on plans.. There will be no change in use, occupancy or egress under this application.
Latest 3 of 6 filings on this floor.
Floor 12Under Construction158p · 9 filings · 20 docs
ArchitectureCivilDMFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
PARTIAL FLOOR INTERIOR ALTERATION. REMOVAL OF NON-LOAD BEARING PARTITIONS, CEILINGS AND FINISHES. INSTALLATION OF NEWNON-LOAD BEARING PARTITIONS, CEILINGS, FINISHES AND MILLWORK.WORK FILED ON THIS APPLICATION INVOLVES NO CHANGE IN OCCUPANCY,
On file for this project
21 documents · 3 drawing sheets
OFFICE RENOVATION WORK (CRITEO) WORK TO INCLUDE PARTION, CEILING AND DOOR MODIFICATIONS AS INDICATED ON PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY,
On file for this project
24 documents · 4 drawing sheets
Project M79054162Signed-off · 12/03/2021
Filing herewith drawings indicating plumbing modifications as shown on plans.. There will be no change in use, occupancy or egress under this application.
Latest 3 of 9 filings on this floor.
Floor 11Under Construction56p · 5 filings · 20 docs
ArchitectureCivilDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
PARTIAL FLOOR INTERIOR ALTERATION. REMOVAL OF NON-LOAD BEARING PARTITIONS, CEILINGS AND FINISHES. INSTALLATION OF NEWNON-LOAD BEARING PARTITIONS, CEILINGS, FINISHES AND MILLWORK.WORK FILED ON THIS APPLICATION INVOLVES NO CHANGE IN OCCUPANCY,
On file for this project
21 documents · 8 drawing sheets
OFFICE RENOVATION WORK WORK TO INCLUDE PARTION, CEILING AND DOOR MODIFICATIONS TO STAIRWELL ENCLOSURE WORK AS INDICATED ON PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY,
On file for this project
15 documents
GENERAL CONSTRUCTION RENOVATION WORK IN COMMERCIAL SPACE TO INCLUDE REMOVAL OF EXISTING AND CONSTRUCTION OF NEW PARTITIONS, FINISHES, DOORS, CEILINGS, CONVENIENCE STAIR MODIFICATIONS AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE,EGRESS AND OCCUPANCY
On file for this project
10 documents · 5 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 1028p · 3 filings · 20 docs
ArchitectureDMFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
GENERAL CONSTRUCTION RENOVATION WORK IN COMMERCIAL SPACE TO INCLUDE REMOVAL OF EXISTING AND CONSTRUCTION OF NEW PARTITIONS, FINISHES, DOORS, CEILINGS, CONVENIENCE STAIR MODIFICATIONS AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE,EGRESS AND OCCUPANCY
On file for this project
10 documents · 5 drawing sheets
MODIFICATIONS TO AN EXISTING SPRINKLER SYSTEMS AS SHOWN ON PLANS FILED HEREWITH
On file for this project
5 documents · 1 drawing sheet
MECHANICAL WORK IN COMMERICAL OFFICE SPACE AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION
On file for this project
9 documents · 1 drawing sheet
Floor 9
Floor 860p · 8 filings · 20 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
OFFICE RENOVATION WORK (TFC) WORK TO INCLUDE PARTION, CEILING AND DOOR MODIFICATIONS AS INDICATED ON PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY,
On file for this project
15 documents · 10 drawing sheets
MODIFICATIONS TO EXISTING SPRINKLER SYSTEM AS INDICATED ON PLANS. NO CHANGE IN USE, EGRESS OR OCUPANCY.
On file for this project
4 documents
INTERIOR RENOVATIONS WORK TO INCLUDE PARTITION, CEILING AND DOOR MODIFICATIONS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY
On file for this project
3 documents · 5 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 7
Floor 62p · 2 filings · 12 docs
Fire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Sprinklers
Relocation of existing ductwork and diffusers as a result of office renovations at the 6th floor (300 sf) and the 8th floor (650 sf).
On file for this project
8 documents
Sprinkler changes to accommodate office renovations at the 6th and 8th floors.
On file for this project
4 documents
Floor 560p · 7 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sign · Sprinklers
OFFICE RENOVATION WORK (MALIN GROUP) WORK TO INCLUDE PARTION, CEILING AND DOOR MODIFICATIONS AS INDICATED ON PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY,
On file for this project
29 documents · 8 drawing sheets
Mechanical Modifications as per plans. no change in use egress or occupancy.
On file for this project
3 documents · 2 drawing sheets
Removal of existing sprinkler heads, installation of temp loop heads and minor sprinkler modifications as indicated on plans. No change in use egress or occupancy.
On file for this project
4 documents · 2 drawing sheets
Latest 3 of 7 filings on this floor.
Floor 42p · 1 filing · 4 docs
ArchitectureStructural
Issued Permit Scope
Sign
NON ILLUMINATED NON ADVERTISING DOUBLE FACED PROJECTING ACCESSORY BANNER SIGN - BARRYS NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Floor 3Under Construction44p · 3 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sign · Sprinklers
Sprinkler modifications as per plans filed herewith. No change of use egress or occupancy.
On file for this project
28 documents · 10 drawing sheets
REMOVAL OF NON-LOAD BEARING PARTITIONS, CEILINGS AND FINISHES AS INDICATED ON PLANS. NO CHANGE IN OCCUPANCY,
On file for this project
1 drawing sheet
NON ILLUMINATED NON ADVERTISING DOUBLE FACED PROJECTING ACCESSORY BANNER SIGN - BARRYS NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Floor 22p · 1 filing · 4 docs
ArchitectureStructural
Issued Permit Scope
Sign
NON ILLUMINATED NON ADVERTISING DOUBLE FACED PROJECTING ACCESSORY BANNER SIGN - BARRYS NO CHANGE TO USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Floor 117p · 9 filings · 20 docs
ArchitectureElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sign · Sprinklers · Structural
Erect illuminatednhanging non advertising hanging sign in window. No change of use, egress or occupancy
On file for this project
7 documents
Erect illuminated interior hanging non advertising sign. No change of use, egress or occupancy.
On file for this project
3 documents
Erect hanging illuminaged sign inside window. No change of use, egress or occupancy.
On file for this project
4 documents
Latest 3 of 9 filings on this floor.
Mezzanine6p · 1 filing · 20 docs
Architecture
Issued Permit Scope
General Construction
Herewith Filing Plumbing and Sprinkler work in conjunction with buildout of new bathroom and pantry, Application is filed in conjunction with Alt-1 M01129462-I1
On file for this project
30 documents
Cellar12p · 4 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Structural
modification to existing fire sprinkler system to accommodate CVS build out.
On file for this project
4 documents
STRUCTURAL MODIFICATIONS FOR EXISTING COMMERCIAL SPACE AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
6 documents
Filing plumbing applications to add new fixtures as per plans filed. No change of use egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Site & exterior19p · 6 filings · 18 docs
ArchitectureElectricalEquipmentGeneralStructural
Issued Permit Scope
Construction Fence · General Construction · Protection and Mechanical Methods · Sidewalk Shed · Sign
Installation of temporary overhead protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
On file for this project
2 documents · 5 drawing sheets
Installation of temporary heavy duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
On file for this project
2 documents · 7 drawing sheets
Facade restoration. No change in egress, use or occupancy.
On file for this project
3 documents · 6 drawing sheets
Latest 3 of 6 filings on this floor.