ECB12/19/2024GC FAILED MAINTAIN SIDEWALK SHED IN SAFE MATTER AT EXPOSURE #1 AS PER PLANS. THIS CONDITION PRESENTS POSSIBLE DISLODGEMENT HAZARDS DUE TO LACK OF CROSSING BRACES TO SECURE UPRIGHT MEMBERS FOR STABILITY FOR THE$1K due
ECB12/19/20243301.1.1 RESPONSIBILITY FOR SAFETY- OBSERVED NO PROTECTION PROVIDED FOR ADJACENT PROPERTIES AT EXPOSURE 2 & 4 REAR YARD EXPOSURE 3 OF THE JOBSITE. NO ROOF PROTECTION, OVER HEAD PROTECTION & WINDOW PROTECTION PR$2K due
ECB12/19/2024OBSERVED ACTIVE JOBSITE W/ MULTIPLE UNSAFE/VIOLATING CONDITIONS CONSISTING OF JOBSITE W/OUT FIRE EXTINGUISHERS, WORK NOT CONFORMING TO APPROVED PLANS, NO PROTECTION PROVIDED FOR ADJACENT PROPERTIES AND OTHERS.$2K due
ECB12/19/2024OBSERVED ACTIVE JOBSITE WITH VERTICAL ENLARGEMENT DONE & WOOD JOIST REPLACE & INSTALLED THROUGHOUT. UPON REVIEW OF PROVIDED APPROVED PLANS, THE JOBSITE WORK IS OUT OF SEQUENCE. HORIZONTAL ENLARGEMENT IS TO TAKE$1K due
ECB12/19/20243301.5 UNSAFE CONDITIONS- OBSERVED ACTIVE JOBSITE WITH NEW WOOD FLOOR FRAMES INSTALLED WITH WOODEN JOIST THROUGHOUT. NO STRAPS PROVIDED FOR BLOCKING OF JOIST & NO SHORING PROVIDED THROUGHOUT FLOORS TO WITHSTAND$2K due
ECB12/19/20243301.1.2 FIRE CODE- OBSERVED ACTIVE JOBSITE W/OUT ANY FIRE EXTINGUISHERS ONSITE. JOBSITE CONSIST OF WOODEN JOIST & MEMBERS, COMBUSTIBLE MATERIALS/DEBRIS THROUGHOUT & EXPOSED ELECTRICAL WIRING. ON 4TH FLOOR PLAS$2K due
ECB12/19/20241704.1.2 TR1 SPECIAL INSPECTIONS- OBSERVED WOOD JOIST & WOOD BEAM REPLACEMENTS/INSTALLATION THROUGHOUT JOBSITE. UPON REVIEWING DEPARTMENT RECORDS NO SPECIAL INSPECTIONS FOR TR1'S ARE SUBMITTED ON BIS/DOB NOW. S$1K due
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION
DOB06/20/2023VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION
DOB06/20/2023VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION
ECB07/22/2022AT THE TIME OF INSPECTION I OBSERVED SUPPORTED PIPE SCAFFOLD, OVER 40 FEET IN HEIGHT, INSTALLED AT EXP#1 ON TOP OF A SIDEWALK SHED. UPON REVIEW OF DEPARTMENT RECORDS IT WAS OBSERVED THAT NO PERMIT HAS BEEN ISSU$3K due
ECB07/22/2022OBSERVED SIDEWALK SHED INSTALLED AT EXP#1. UPON REVIEW OF DEPARTMENT RECORDS, IT WAS OBSERVED THAT SIDEWALK SHED PERMIT HAS EXPIRED ON 02/21/2020 AND HAS NOT BEEN RENEWED. PERMIT B00236822-I1-SH$6K due
ECB07/22/2022OBSERVED SIDEWALK SHED AT EXP#1 INSTALLED NOT AS PER CODE. MISSING LIGHTING FIXTURES ON UNDERSIDE OF THE SIDEWALK SHED. ALSO SIDEWALK SHED EXTENDED MORE THAN 5 FEET ONTO ADJOINING PROPERTY AT EXP#2 AND EXP#4 AN$10K due
ECB07/22/2022DEBRIS NETTING - OBSERVED SUPPORTED PIPE SCAFFOLD AT EXP #1 INSTALLED NOT AS PER CODE. SUPPORTED PIPE SCAFFOLD HAS INADEQUATE DEBRIS NETTING. DEBRIS NETTING IS LOOSE AND NOT COVERING ENTIRE SCAFFOLD. THIS CONDI$6K due
ECB04/14/2022FAILURE TO OBTAIN A TEMPORARY CONSTRUCTION PERMIT PRIOR TO INSTALLATION/USE OF TEMPORARY CONSTRUCTION EQUIPMENT-SIDEWALK SHED.OBSERVED SIDEWALK SHED ERECTED AT EXP1 ALONG FIFTH AVE WITH NO ACTIVE PERMIT POSTED$3K due
DOB04/14/2021FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
DOB02/17/2021FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
DOB02/17/2021FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
DOB02/17/2021FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
DOB02/17/2021FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
DOB02/17/2021FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
DOB02/17/2021FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
ECB01/26/2021PEDESTRIAN PROTECTION DOES NOT MEET CODE SPECIFICATIONS. NOTE: AT THE TIME OF INSPECTION I OBSERVED SIDEWALK SHED IN PLACE. UPON MY INSPECTION I OBSERVED THE SHED WAS NOT EXTENDED 5FT AS REQUIRE TO SAFEGUARD PE$10K due
ECB01/12/2021PEDESTRIAN PROTECTION DOES NOT MEET CODE SPECIFICATIONS.NOTE:AT TIME OF MY INSPECTION,I OBSERVED A SIDEWALK SHED IN PLACE AT EXPOSURE#1,I OBSERVED THAT A PART OF THE SHED PARAPET IN DISMANTLED FROM THE SHED AND$2K due
ECB01/12/20213314.1 SUPPORTED SCAFFOLD DOES NOT MEET CODE SPECIFICATIONS.NOTE:AT TIME OF MY INSPECTION,I OBSERVED A SUPPORTED SCAFFOLD OF ABOUT 46 FEET AT EXPOSURE#1,I OBSERVED ALSO THAT THE SCAFFOLD DOES NOT COMPLY WITH CO$2K due
ECB01/12/2021FAILURE TO OBTAIN A TEMPORARY CONSTRUCTION PERMIT PRIOR TO INSTALLATION/USE OF TEMPORARY CONSTRUCTION EQUIPMENT.NOTE:AT TIME OF MY INSPECTION I OBSERVED A SUPPORTED SCAFFOLD OF ABOUT 46 FEET HEIGHT ABOVE GROUND$1K due
ECB11/19/2020FAILURE TO NOTIFY THE DEPT PRIOR TO COMMENCEMENT OF WORK THAT REQUIRESTENANT PROTECTION PLAN. NOTED;ACTIVE WORK BEING PERFORMED THROUGHOUT ASSOCIATED W/ A VERTICAL&HORIZONTAL ENLARGEMENT OF BUILDING. GUT RENOVA$1K due
ECB11/19/2020FAILURE TO DISTRIBUTE OR POST SAFE CONSTRUCTION BILL OF RIGHTS. NOTED;ON GOING VERTICAL AND HORIZONTAL ENLARGEMENT AT PROPERTY CONSISTING OFNEW FRAMING,NEW ELECTRICAL WIRING,NEW PLUMBING AT 3RD&4TH FLOORS W/O P$1K due
ECB11/19/2020FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER. NOTED;FIRE RATING COMPROMISED THROUGHOUT OCCUPIED BLDG DUE TO ACTIVE HORIZONTAL ENLARGEMENT IN PROGRESS W/O PERMITS. ENTIRE 3RD FL GUTTED AND NEW 4TH FL AD$2K due
ECB11/19/2020BC-3303.10.1 FAILURE TO COMPLY W/ TENANT PROTECTION REQUIREMENTS. NOTED;ESSENTIAL SERVICES DISRUPTED SPECIFICALLY HEAT AND HOT WATER AS A RESULT OF WORK BEING PERFORMED THROUGHOUT ASSOCIATED W/ A VERTICAL/HORIZ$2K due
ECB11/17/2020FAILURE TO PROVIDE SIDEWALK SHED WHERE REQUIRED NOTED:AT EXP. 3 NO OVERHEAD PROTECTION PROVIDED FOR 1ST FLOOR STORE EXISTING CONSTRUCTION PRESENT OF VERTICAL & HORIZONTAL ENLARGEMENT OF EXISTING(3)STORY BUILDIN$10K due
ECB11/17/2020WORK WITHOUT PERMIT.NOTED;AT 3RD FLOOR LEVEL REMOVED ALL INTERIOR WALLS(FULL DEMO)REMOVED SUPPORTING ROOF WOOD MEMBERS(ROOF JOIST).ERECTED NEW WOOD FRAME AND BRICK CREATING VERTICAL AND HORIZONTAL ENLARGEMENT O$2K due
ECB11/17/2020FAILURE TO FILE A REQUIRED TENANT PROTECTION PLAN. NOTE;ACTIVE/IN PROGRESS CONSTRUCTION AT PROPERTY ASSOCIATED W/ A VERTICAL ENLARGEMENT OF (3)STORY BUILDING TO ADD (2)ADDITIONAL STORIES W/O PERMITS. NEW FRAMIN$10K due
ECB11/17/2020FAILURE TO MAINTAIN BUILDING IN A CODE COMPLIANT MANNER. NOTED;ALL INTERIOR WALLS&FLOORS REMOVED AT THE 3RD FL LEVEL. ALL WOOD MEMBERS SUPPORTING ROOF(JOISTS&RAFTERS) REMOVED. UNSAFE&UNAPPROVED VERTICAL&HORIZON$1K due
DOB01/17/2020VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2017 INSPECTION REPORT
HPD08/04/2017§ 27-2005 ADMIN. CODE: PROPERLY REPAIR THE BROKEN OR DEFECTIVE DOORBELL AT STREET ENTRANCE FOR THE UNIT LOCATED AT APT 3FL, 3rd STORY
HPD11/09/2004§ 27-2005 ADM CODE REPLACE WITH NEW THE MISSING FLOOR TILES THROUGHOUT IN THE ENTIRE APARTMENT LOCATED AT APT 2, 2nd STORY
HPD11/09/2004HMC ADM CODE: § 27-2018.4 ABATE THE NUISANCE CONSISTING OF VERMIN ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 2, 2nd STORY
HPD11/09/2004§ 27-2005 ADMIN. CODE: REPLACE WITH NEW THE MISSING CERAMIC WALL TILES IN THE BATHROOM LOCATED AT APT 2, 2nd STORY
HPD11/09/2004§ 27-2005 ADMIN. CODE: REPLACE WITH NEW THE MISSING BASEBOARDS THROUGHOUT IN THE ENTIRE APARTMENT LOCATED AT APT 2, 2nd STORY
HPD11/09/2004§ 27-2065 ADM CODE - PROVIDE VENTILATION FOR WATER CLOSET COMPARTMENT AND/ OR BATHROOM AND FILE APPLICATION FOR APPROVAL BEFORE DOING WORK .. IN THE BATHROOM LOCATED AT APT 2, 2nd STORY
HPD11/09/2004§ 27-2005 ADMIN. CODE: PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE PLASTER THE WALLS THROUGHOUT IN THE ENTIRE APARTMENT LOCATED AT APT 2, 2nd STORY
HPD11/09/2004§ 27-2005 ADMIN. CODE: REPLACE WITH NEW THE MISSING CEILING LIGHT FIXTURES AND WALL OUTLETS THROUGHOUT LOCATED AT APT 2, 2nd STORY
HPD11/09/2004§ 27-2026 ADMIN. CODE: REPAIR THE BROKEN OR DEFECTIVE CONNECTION WASTELINE OF THE WASH BASIN IN THE BATHROOM LOCATED AT APT 2, 2nd STORY
HPD11/09/2004HMC ADM CODE: § 27-2018.4 ABATE THE NUISANCE CONSISTING OF VERMIN MICE IN THE ENTIRE APARTMENT LOCATED AT APT 2, 2nd STORY
HPD11/09/2004§ 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT THE WALLS AND CEILINGS THROUGHOUT IN THE ENTIRE APARTMENT LOCATED AT APT 2, 2nd STORY
HPD11/09/2004§ 27-2005 ADM CODE & 309 M/D LAW ABATE THE NUISANCE CONSISTING OF EXPOSED ELECTRICAL WIRES ON THE WALLS AND CEILINGS THROUGHOUT IN THE ENTIRE APARTMENT LOCATED AT APT 2, 2nd STORY
HPD11/20/2003§ 9, 170, 171, 300, 301, 302 M.D.LAW-FILE PLANS AND APPLICATION AND OBTAIN A CERTIFICATE OF OCCUPANCY TO LEGALIZE THE CONVERSION FROM A PRIVATE DWELLING TO MULTIPLE DWELLING USE IF LAWFULLY FEASIBLE OR RESTORE TO LAWFUL OCCUPANCY
HPD11/20/2003§ 27-2005 ADMIN. CODE: ABATE THE NUISANCE CONSISTING OF EXPOSED ELECTRICAL WIRES CEILING, 1ST AND 2ND STORY PUBLIC HALL.
HPD07/09/2003§ 27-2005 ADMIN. CODE: PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE METAL CEILING BATHROOM, 3RD STORY PUBLIC HALL.
HPD07/09/2003§ 27-2005, 2007 ADMIN. CODE: REMOVE ALL ENCUMBRANCES CONSISTING OF HOUSEHOLD MATERIALS, 1ST STORY PUBLIC HALL.
HPD07/09/2003§ 27-2013 ADMIN. CODE: PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT WALLS AND CEILINGS, ALL STORIES PUBLIC HALL.
HPD07/09/2003§ 27-2005 ADMIN. CODE: ABATE THE NUISANCE CONSISTING OF EXPOSED ELECTRICAL WIRES CEILING BATHROOM , 3RD STORY PUBLIC HALL.
HPD07/09/2003§ 27-2005 ADMIN. CODE: REPAIR THE ROOF SO THAT IT WILL NOT LEAK BATHROOM, 3RD STORY PUBLIC HALL.
ECB11/17/2020WORK WITHOUT PERMIT.NOTED:AT 3RD FLOOR LEVEL INSTALLED ROUGH PLUMBINGFOR WATER & WASTE LINES (1)TOILET, SINK,SHOWER BODY RESIDENTIAL SINK.INSTALLED NEW ROUGH PIPING FOR GAS LINE.INSTALLED NEW ROUGH PLUMBING FONothing owed — awaiting certificate of correction
ECB11/17/2020WORK WITHOUT PERMIT.NOTED;AT 3RD FLOOR LEVEL INSTALLED NEW ELECTRICAL WIRING FOR LIGHTS SWITCHES AND OUTLETS.INSTALLED NEW ELECTRICAL PANEL WITH BREAKERS.APPROX.50% OF WORK COMPLETED.STOP ALL WORK EXCEPT TO MAKNothing owed — awaiting certificate of correction