| Owner | Filings | Most Recent |
|---|---|---|
| CITIGROUP CORP REALTY SERVICES | 166 | 03/21/2026 |
| CITI | 109 | 08/27/2026 |
| CITIGROUP CORPORATE REALTY | 93 | 03/21/2026 |
| CITIGROUP NORTH AMERICAM, INC. | 81 | 03/21/2026 |
| CITIGROUP | 40 | 03/22/2026 |
| CITIGROUP GLOBAL MARKETS INC. | 18 | 03/21/2026 |
| CITIGROUP CORP REALTY SERV | 7 | 03/21/2026 |
| BENSON INDUSTRIES | 4 | 03/21/2026 |
| CITIGROUP CORP.REALTY SERVICES | 2 | 03/21/2026 |
| FC 42 HOTEL | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/10/2016 | $1.8B | — | 388 REALTY OWNER LLC → CITIGROUP TECHNOLOGY, INC. | $751/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SAFWAY ATLANTIC LLC | 7 | 07/01/2026 |
| JAROS BAUM & BOLLES | 12 | 06/22/2026 |
| NELSON ARCHITECTURE &INTERIORS, INC | 4 | 04/02/2026 |
| SYSKA HENNESSY GROUP | 3 | 02/26/2026 |
| NEIL TUCKER | 3 | 02/19/2026 |
| GENSLER | 16 | 12/01/2025 |
| ME ENGINEERS | 4 | 11/18/2025 |
| SKIDMORE OWINGS & MERRILL LLP | 7 | 04/26/2022 |
| HOWARD I SHAPIRO & ASSOCIATES | 1 | 08/06/2021 |
| BONSIGNORE ARCHITECTS | 7 | 07/02/2021 |
| FISKAA ENGINEERING | 8 | 05/28/2021 |
| WAVIC ENGINEERING PLLC | 1 | 03/24/2021 |
| GILSANZ MURRAY STEFICEK LLP | 1 | 02/26/2021 |
| TOHFAZ UDDIN PE PC | 2 | 02/19/2020 |
| THORNTON TOMASETTI | 1 | 11/11/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| A1 EXPEDITING SERVICE CORP. | 84 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 1 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 14 | 03/21/2026 |
| HOWARD I SHAPIRO ASSOCIATES | 2 | 03/21/2026 |
| CLARKE CONSTRUCTION CONSULTANTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SAFWAY ATLANTIC, LLC | General Contractor | 26 | 07/08/2026 |
| JAMES E FITZGERALD INC | General Contractor | 14 | 07/08/2026 |
| CROSS MANAGEMENT CORP | General Contractor | 10 | 08/27/2026 |
| TISHMAN INTERIORS CORP | General Contractor | 9 | 07/08/2026 |
| ASHLAR MECHANICAL CORP | Fire Protection | 6 | 07/08/2026 |
| TURNER CONSTRUCTION COMPANY | General Contractor | 5 | 07/08/2026 |
| STARR INDUSTRIES LLC | General Contractor | 5 | 07/08/2026 |
| DIFALZO ELECTRIC NY, INC | Electrical | 3 | 03/22/2026 |
| YORK SCAFFOLD EQUIPMENT CORP. | General Contractor | 3 | 07/08/2026 |
| PAR PLUMBING CO., INC | Plumbing | 3 | 07/08/2026 |
| JRM CONSTRUCTION MGMT LLC | General Contractor | 3 | 07/08/2026 |
| PREFERRED SPKLR AND MECH | Fire Protection | 3 | 07/08/2026 |
| SIRINA FIRE PROT CORP | Fire Protection | 2 | 07/08/2026 |
| PREFERRED MECHANICAL INC | Plumbing | 1 | 07/08/2026 |
| KLEINKNECHT ELEC. CO.,INC | Electrical | 1 | 03/22/2026 |
| STRIANO ELECTRIC CO., INC | Electrical | 1 | 03/22/2026 |
| SOH PAR SPRINKLER LLC | Fire Protection | 1 | 07/08/2026 |
| PJP INSTALLERS INC | General Contractor | 1 | 07/03/2026 |
| TISHMAN CONSTRUCTION CORP | General Contractor | 1 | 07/08/2026 |
| OLYMPIC PLBG & HTG SVC IN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ATLAS ATC ENGINEERING INC | 8011 | 14 | 06/22/2026 |
| MILROSE CONSULTANTS LLC | 2003 | 4 | 02/26/2026 |
| ATLANTIC ENGINEERINGLABOR | 1381 | 21 | 12/01/2025 |
| WAVIC ENGINEERING PLLC | 1733 | 1 | 03/24/2021 |
| GILSANZ MURRAY STEFICEK | 240 | 1 | 02/26/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | CROSS MANAGEMENT CORP | 08/26/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | CROSS MANAGEMENT CORP | 08/26/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | PJP INSTALLERS INC | 07/01/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | CROSS MANAGEMENT CORP | 09/16/2025 |
| DOB NOW | General Construction | Permit Issued | CROSS MANAGEMENT CORP | 08/20/2025 |
| DOB NOW | General Construction | Signed-off | CROSS MANAGEMENT CORP | 08/20/2025 |
| DOB NOW | Mechanical Systems | Signed-off | CROSS MANAGEMENT CORP | 08/13/2025 |
| DOB NOW | General Construction | Signed-off | CROSS MANAGEMENT CORP | 04/10/2025 |
| DOB NOW | General Construction | Permit Issued | JAMES E FITZGERALD INC | 12/09/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JAMES E FITZGERALD INC | 04/05/2024 |
| DOB NOW | General Construction | Signed-off | JAMES E FITZGERALD INC | 04/05/2024 |
| DOB NOW | Plumbing | Signed-off | PREFERRED MECHANICAL INC | 04/03/2024 |
| DOB NOW | Plumbing | Signed-off | PREFERRED SPKLR AND MECH | 04/03/2024 |
| DOB NOW | Sprinklers | Signed-off | SIRINA FIRE PROT CORP | 04/02/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JAMES E FITZGERALD INC | 02/09/2024 |
| DOB NOW | General Construction | Signed-off | JAMES E FITZGERALD INC | 02/01/2024 |
| DOB NOW | Mechanical Systems | Signed-off | JAMES E FITZGERALD INC | 12/14/2023 |
| DOB NOW | Sprinklers | Signed-off | PREFERRED SPKLR AND MECH | 12/14/2023 |
| DOB NOW | General Construction | Signed-off | JAMES E FITZGERALD INC | 12/12/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | JAMES E FITZGERALD INC | 09/26/2023 |
| DOB NOW | General Construction | Signed-off | JAMES E FITZGERALD INC | 09/25/2023 |
| DOB NOW | General Construction | Signed-off | CROSS MANAGEMENT CORP | 04/05/2023 |
| DOB NOW | Sprinklers | Signed-off | SIRINA FIRE PROT CORP | 03/17/2023 |
| DOB NOW | Mechanical Systems | Signed-off | JAMES E FITZGERALD INC | 03/09/2023 |
| DOB NOW | General Construction | Permit Issued | JAMES E FITZGERALD INC | 01/20/2023 |
| DOB NOW | Sprinklers | Signed-off | SOH PAR SPRINKLER LLC | 12/13/2022 |
| DOB NOW | Mechanical Systems | Signed-off | JRM CONSTRUCTION MGMT LLC | 12/12/2022 |
| DOB NOW | General Construction | Signed-off | JRM CONSTRUCTION MGMT LLC | 12/10/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SAFWAY ATLANTIC, LLC | 05/24/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | SAFWAY ATLANTIC, LLC | 05/23/2022 |
| DOB NOW | Sprinklers | Signed-off | ASHLAR MECHANICAL CORP | 01/19/2022 |
| DOB NOW | Mechanical Systems | Signed-off | TISHMAN INTERIORS CORP | 10/07/2021 |
| DOB NOW | General Construction | Signed-off | TISHMAN INTERIORS CORP | 10/05/2021 |
| DOB NOW | Structural | Signed-off | TISHMAN INTERIORS CORP | 10/01/2021 |
| DOB NOW | General Construction | Signed-off | TISHMAN INTERIORS CORP | 09/27/2021 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | TISHMAN CONSTRUCTION CORP | 08/06/2021 |
| DOB NOW | Standpipe | Signed-off | ASHLAR MECHANICAL CORP | 06/16/2021 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SAFWAY ATLANTIC, LLC | 06/16/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | SAFWAY ATLANTIC, LLC | 06/07/2021 |
| DOB NOW | Sprinklers | Signed-off | ASHLAR MECHANICAL CORP | 04/09/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/22/2026 | Signed-off | PREFERRED SPKLR AND MECH | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/25/2026 | Permit Issued | TOP SHELF ELECTRIC CORP | — |
| 10/21/2024 | Complete | NEAD ELECTRIC INC. | General Wiring |
| 12/07/2023 | Complete | KLEINKNECHT ELEC. CO.,INC | General Wiring |
| 09/27/2023 | Complete | UNITY ELECTRIC CO. INC | General Wiring |
| 09/01/2023 | Complete | UNITY ELECTRIC CO. INC | General Wiring |
| 07/13/2023 | Permit Issued | STRIANO ELECTRIC CO., INC | General Wiring |
| 03/02/2023 | Complete | UNITY ELECTRIC CO. INC | General Wiring |
| 12/13/2022 | Complete | DAL ELECTRICAL CORP. | General Wiring |
| 04/18/2022 | Complete | FOREST ELECTRIC CORP. | General Wiring |
| 02/03/2022 | Complete | DIFALZO ELECTRIC NY, INC | General Wiring |
| 08/05/2021 | Complete | NY ELECT MAINT & DATA COR | General Wiring |
| 06/14/2021 | Complete | NEAD ELECTRIC INC. | General Wiring |
| 06/07/2021 | Complete | CORPORATE ELEC. GROUP INC | — |
| 05/18/2021 | Complete | HUGH O'KANE ELEC. CO. INC | General Wiring |
| 04/12/2021 | Complete | HUGH O'KANE ELEC. CO. INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/01/2026 | Permit Issued | PJP INSTALLERS INC | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/04/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/06/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/03/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/19/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/14/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/23/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/23/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/04/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/26/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/26/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/17/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/12/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/12/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/05/2021 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 11/01/2021 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/22/2026 | Sprinkler Systems | RONALD GRAPIN | special |
| 06/11/2026 | Sprinkler Systems | RONALD GRAPIN | special |
| 04/03/2026 | Final | Christopher Drutjons | progress |
| 03/01/2026 | Sprayed fire-resistant materials | RONALD GRAPIN | special |
| 03/01/2026 | Fire-Resistant Penetrations and Joints | RONALD GRAPIN | special |
| 03/01/2026 | Final | Edward Bosco | progress |
| 02/26/2026 | Maintenance information | Christopher Drutjons | energy_progress |
| 02/26/2026 | Mechanical Systems | Christopher Drutjons | special |
| 02/26/2026 | Final | Christopher Drutjons | progress |
| 02/26/2026 | Energy Code Compliance Inspections | Christopher Drutjons | progress |
| 02/26/2026 | Duct leakage testing, insulation and design | Christopher Drutjons | energy_progress |
| 01/29/2026 | Mechanical Systems | Christopher Drutjons | special |
| 01/29/2026 | Energy Code Compliance Inspections | Christopher Drutjons | progress |
| 01/29/2026 | Final | Christopher Drutjons | progress |
| 01/29/2026 | Duct leakage testing, insulation and design | Christopher Drutjons | energy_progress |
| 01/29/2026 | Maintenance information | Christopher Drutjons | energy_progress |
| 11/28/2025 | HVAC-R and service water heating system controls | RONALD GRAPIN | energy_progress |
| 11/28/2025 | HVAC-R and service water piping design and insulation | RONALD GRAPIN | energy_progress |
| 11/28/2025 | Final | Edward Bosco | progress |
| 11/28/2025 | Mechanical Systems | RONALD GRAPIN | special |
| 11/28/2025 | HVAC-R and service water heating equipment | RONALD GRAPIN | energy_progress |
| 11/28/2025 | Duct leakage testing, insulation and design | RONALD GRAPIN | energy_progress |
| 11/28/2025 | Lighting controls | RONALD GRAPIN | energy_progress |
| 11/28/2025 | Post-installed Anchors | RONALD GRAPIN | special |
| 11/28/2025 | Fire-Resistant Penetrations and Joints | RONALD GRAPIN | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Citi | Other | Ground, Floors 1, 2, 5–7, 14, 38 | Project M01249773 Project M01213424 Project M01232726 Project M01076635 Project M00966699 Project M00954137 Project M00921608 Project M08054143 Project M00708240 Project M00708220 Project M00430337 Project M00430336 |
| Citibank | Office | Floor 8 | Project M08028897 |