Two family converted from one family
389 JEFFERSON AVENUE
BROOKLYN · BIN 3052095
💬 Discuss this project
1915Year Built
3Stories
B3Building Class
R6BZoning
3,797 sfGross Floor Area
2Units
Rent Stabilized12 Open Violations ▸FDNY Report ↗
Two family converted from one family · 2,000 sf lot · 1.9 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Permit Issued — active, not yet Signed-off
Roof11p · 2 filings · 20 docs
Floor 338p · 3 filings · 20 docs
Floor 238p · 3 filings · 20 docs
Floor 142p · 3 filings · 20 docs
CellarUnder Construction41p · 4 filings · 20 docs
Basement1p · 1 filing · 18 docs
Sub-Basement34p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CRISTOM CONSTRUCTION SERVICES403/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/28/2021$1.6M—DEVITO PROPERTIES 389 INC → Private party$419/sf building
10/02/2019$1.4M—— → —$374/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CES ENGINEERING LLC1210/11/2024
TELYK NYC604/28/2023
CANDACE S MENDEZ, RA109/05/2019
JOHN STACOM ARCHITECTURAL DESIGN109/05/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
M W EXPEDITING1603/21/2026
JOHN STACOM ARCHITECTURAL DESIGN203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NO LIMIT CONTRACTING INCGeneral Contractor608/08/2026
ATTIC TO BASEMENT HOMEGeneral Contractor407/08/2026
ARCO PLBG AND HTG INCPlumbing307/08/2026
ARCO PLBG AND HTG INCFire Protection207/08/2026
WCK ELECTRIC CORP 002413General Contractor203/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CES ENGINEERING LLC12771210/11/2024
MICHAEL PATINO ARCHITECTU8170204/28/2023
ASE ENGINEERING PLLC5785403/17/2022
NS ENGINEERING & CONSULTI3652109/05/2019
Building Lifecycle
All (100)Filed (20)Permit Issued (7)Signed Off (1)Violation (23)Inspection (9)Objection (10)Special Inspection (30)
08/07/2026
Permit issued — Mechanical Systems
B00546592-I1-MS
03/17/2026
Permit issued — General Construction
B00570662-I1-GC-CX
02/05/2026
Permit issued — General Construction
B00570662-I1-GC-CX
12/29/2025
Signed off — Alteration
B00570630-I1
11/24/2025
Violation issued (HPD, open)
I
12/04/2024
Violation issued (HPD, open)
I
11/13/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/15/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Delbert Smith
10/15/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Delbert Smith
10/15/2024
Special inspection requirement — Energy Code Compliance Inspections
Delbert Smith
10/11/2024
Filed — Alteration
Changes: Change "garden" floor to "cellar" floor- p100 & pd100; change schedules for pumps water, water haters, exp. tank- p002; slight fixt. layout changes- p101; show etr house traps- p300; water heater details- p301
B00546601-P5
09/09/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Delbert Smith
09/09/2024
Special inspection requirement — Energy Code Compliance Inspections
Delbert Smith
09/09/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Delbert Smith
06/05/2024
Special inspection requirement — Final
Delbert Smith
06/05/2024
Special inspection requirement — Ventilation and air distribution system
Delbert Smith
06/05/2024
Special inspection requirement — Mechanical Systems
Delbert Smith
06/03/2024
Filed — Alteration
Install AC Split system Throughout. No change to egress, occupancy or use.
B00546592-P3
06/03/2024
Filed — Alteration
Changes: Change "garden" floor to "cellar" floor- p100 & pd100; change schedules for pumps water, water haters, exp. tank- p002; slight fixt. layout changes- p101; show etr house traps- p300; water heater details- p301
B00546601-P4
05/24/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
05/22/2024
Special inspection requirement — Ventilation and air distribution system
Delbert Smith
05/22/2024
Special inspection requirement — Final
Delbert Smith
05/22/2024
Special inspection requirement — Mechanical Systems
Delbert Smith
05/16/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
05/15/2024
Permit issued — Plumbing
B00546587-I1-EW-SP
04/18/2024
Objection resolved — Addressed
04/16/2024
Objection raised — Scope
04/10/2024
Filed — Alteration
Changes: Change "garden" floor to "cellar" floor- p100 & pd100; change schedules for pumps water, water haters, exp. tank- p002; slight fixt. layout changes- p101; show etr house traps- p300; water heater details- p301
B00546601-P3
03/28/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/22/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/01/2024
Objection resolved — Addressed
01/29/2024
Objection resolved — Addressed
01/19/2024
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
01/19/2024
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
01/19/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/19/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
01/17/2024
Objection resolved — Addressed
12/22/2023
Objection resolved — Addressed
12/18/2023
Objection raised — Scope
12/15/2023
Objection raised — Admin
12/15/2023
Objection raised — Zoning
12/15/2023
Objection raised — Scope
12/13/2023
Filed — Alteration
Install AC Split system Throughout. No change to egress, occupancy or use.
B00546592-P2
12/13/2023
Filed — Alteration
Changes: Change "garden" floor to "cellar" floor- p100 & pd100; change schedules for pumps water, water haters, exp. tank- p002; slight fixt. layout changes- p101; show etr house traps- p300; water heater details- p301
B00546601-P2
11/28/2023
Violation issued (HPD, open)
I
11/03/2023
Special inspection requirement — Energy Code Compliance Inspections
Delbert Smith
11/03/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
Delbert Smith
11/03/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Delbert Smith
09/13/2023
Permit issued — Plumbing
B00546601-I1-PL
09/08/2023
Permit issued — Sprinklers
B00546587-I1-EW-SP
05/08/2023
Special inspection requirement — Structural Cold-Formed Steel
Michael Patino
05/08/2023
Special inspection requirement — Structural Steel - Details
Michael Patino
05/08/2023
Special inspection requirement — Final
KYLE TWITCHELL
05/08/2023
Special inspection requirement — Structural Steel - Welding
Michael Patino
05/08/2023
Special inspection requirement — Post-installed Anchors
Michael Patino
05/08/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Michael Patino
05/08/2023
Special inspection requirement — Structural Steel - High Strength Bolting
Michael Patino
04/28/2023
Filed — Alteration
B00570630-P2
04/17/2023
Special inspection requirement — Structural Steel - Welding
Michael Patino
04/17/2023
Special inspection requirement — Final
KYLE TWITCHELL
Latest 60 of 100 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offNO LIMIT CONTRACTING INC08/07/2026
DOB NOWGeneral ConstructionPermit IssuedNO LIMIT CONTRACTING INC03/17/2026
DOB NOWGeneral ConstructionPermit IssuedATTIC TO BASEMENT HOME02/05/2026
DOB NOWPlumbingPermit IssuedARCO PLBG AND HTG INC05/15/2024
DOB NOWPlumbingPermit IssuedARCO PLBG AND HTG INC09/13/2023
DOB NOWSprinklersPermit IssuedARCO PLBG AND HTG INC09/08/2023
DOB NOWStructuralSigned-offATTIC TO BASEMENT HOME12/02/2021
BIS—ISSUEDNO LIMIT CONTRACTING INC04/16/2024
BIS—ISSUEDNO LIMIT CONTRACTING INC10/23/2023
BIS—ISSUEDNO LIMIT CONTRACTING INC10/28/2022
BIS—ISSUEDNO LIMIT CONTRACTING INC10/07/2022
BIS—ISSUEDATTIC TO BASEMENT HOME11/01/2021
BIS—ISSUEDCRISTOM CONSTRUC SERV INC10/16/2019
1 project · most recent 06/03/2024
Air Conditioning Systems Associated Ducts and Piping
FiledStatusContractorScopeMake / Model / Capacity
06/03/2024Signed-offNO LIMIT CONTRACTING INCAir Conditioning Systems, Associated Ducts and Piping
Cooling
Mitsubishi Electric MXZ-SM48NAMHZ-U1 46,500 BTU · Heat Pump Outdoor ×3
MXZ=SM36NAMHZ-U1 35,900 BTU · Vrf Outdoor ×3
Ducts & Piping
N/A n/a ×3
1 project · most recent 10/28/2021
FiledStatusContractorScope
10/28/2021Permit IssuedARCO PLBG AND HTG INC48 heads
2 projects · most recent 10/11/2024
Water/Sanitary Gas Storm
FiledStatusContractorScope
10/11/2024Permit IssuedARCO PLBG AND HTG INCGas, Storm, Water/Sanitary
10/28/2021——Water/Sanitary
1 project · most recent 08/18/2024
General Wiring
FiledStatusContractorScope
08/18/2024CompleteWCK ELECTRIC CORP.General Wiring
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
11/13/2024Pass-Final CND-Occupancy InspectionPassView ↗
05/24/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/16/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/28/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/22/2024Pass-Final CND-Occupancy InspectionPassView ↗
01/19/2024Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
01/19/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
01/19/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/19/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 57
DateRequirementInspectorRole
10/15/2024Fire-Resistant Penetrations and JointsDelbert Smithspecial
10/15/2024HVAC-R and service water piping design and insulationDelbert Smithenergy_progress
10/15/2024Energy Code Compliance InspectionsDelbert Smithprogress
09/09/2024HVAC-R and service water piping design and insulationDelbert Smithenergy_progress
09/09/2024Energy Code Compliance InspectionsDelbert Smithprogress
09/09/2024Fire-Resistant Penetrations and JointsDelbert Smithspecial
06/05/2024FinalDelbert Smithprogress
06/05/2024Ventilation and air distribution systemDelbert Smithenergy_progress
06/05/2024Mechanical SystemsDelbert Smithspecial
05/22/2024Ventilation and air distribution systemDelbert Smithenergy_progress
05/22/2024FinalDelbert Smithprogress
05/22/2024Mechanical SystemsDelbert Smithspecial
11/03/2023Energy Code Compliance InspectionsDelbert Smithprogress
11/03/2023HVAC-R and service water piping design and insulationDelbert Smithenergy_progress
11/03/2023Fire-Resistant Penetrations and JointsDelbert Smithspecial
05/08/2023Structural Cold-Formed SteelMichael Patinospecial
05/08/2023Structural Steel - DetailsMichael Patinospecial
05/08/2023FinalKYLE TWITCHELLprogress
05/08/2023Structural Steel - WeldingMichael Patinospecial
05/08/2023Post-installed AnchorsMichael Patinospecial
05/08/2023Structural Stability – Alterations of existing buildingsMichael Patinospecial
05/08/2023Structural Steel - High Strength BoltingMichael Patinospecial
04/17/2023Structural Steel - WeldingMichael Patinospecial
04/17/2023FinalKYLE TWITCHELLprogress
04/17/2023Post-installed AnchorsMichael Patinospecial
Latest 25 of 57.
▾Documents — 173 on file (BIS + DOB NOW)
▸Plans & Drawings19
▸DOB NOWPlans/Sketch18
09/01/2026B00546592-P1Request digital key ↗
09/01/2026B00546592-I1Request digital key ↗
09/01/2026B00546592-P3Request digital key ↗
Showing 3 of 18 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/02/2026B00200489-I1Request digital key ↗
▸Applications & Permits20
▸BISPLAN / WORK APPROVAL APPLICATION13
09/12/2025321793207Open ↗
11/13/2023321793207Open ↗
03/04/2022321793207Open ↗
Showing 3 of 13 on file for this type
▸BISWORK PERMIT APPLICATION6
10/11/2022321793207Open ↗
11/02/2021321793207Open ↗
09/16/2021321793207Open ↗
Showing 3 of 6 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
09/13/2023321793207Open ↗
▸Zoning, Tax Lot & Property Records2
▸BISZONING DIAGRAM2
08/23/2021321793207Open ↗
09/30/2019321793207Open ↗
▸Seals & Professional Certifications59
▸DOB NOWDPL-1: Design Professional Seal & Signature21
09/02/2026B00200489-I1Open ↗
09/01/2026B00546592-P3Open ↗
09/01/2026B00546592-I1Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWProgress Inspector Seal & Signature19
09/02/2026B00570630-P2Open ↗
09/02/2026B00546601-P2Open ↗
09/02/2026B00546601-P2Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature17
09/02/2026B00570630-P2Open ↗
09/02/2026B00570630-P2Open ↗
09/02/2026B00570630-P2Open ↗
Showing 3 of 17 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
09/16/2021321793207Open ↗
08/29/2019321793207Open ↗
▸Safety & Tenant Protection4
▸BISTenant Protection Plan and Notes2
10/03/2019321793207Open ↗
08/29/2019321793207Open ↗
▸BISSTREET TREE CHECKLIST2
10/03/2019321793207Open ↗
08/29/2019321793207Open ↗
▸Environmental & Asbestos21
▸DOB NOWDEP ACP-5: Asbestos Assessment Report20
09/01/2026B00546592-I1Open ↗
09/01/2026B00546592-P1Open ↗
09/01/2026B00546592-P3Open ↗
Showing 3 of 20 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
10/03/2019321793207Open ↗
▸Energy Compliance14
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
09/16/2021321793207Open ↗
10/04/2019321793207Open ↗
10/03/2019321793207Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
08/05/2021321793207Open ↗
06/24/2021321793207Open ↗
▸DOB NOWEN2: As Built Energy Analysis.2
09/01/2026B00546592-I1Open ↗
08/13/2026B00546601-I1Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
07/29/2025321793207Open ↗
▸BISFENESTRATION AREAS1
07/29/2025321793207Open ↗
▸BISFENESTRATION AIR LEAKAGE1
07/29/2025321793207Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
07/29/2025321793207Open ↗
▸BISINTERIOR LIGHTING POWER1
07/29/2025321793207Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
07/29/2025321793207Open ↗
▸Inspections & Test Reports11
▸DOB NOWSOIL REPORT3
08/13/2026B00570662-I1Open ↗
08/13/2026B00570662-P2Open ↗
08/13/2026B00570662-P1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY2
08/05/2021321793207Open ↗
06/24/2021321793207Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
07/29/2025321793207Open ↗
▸BISFOOTING AND FOUNDATION INSPECTION1
07/29/2025321793207Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
07/29/2025321793207Open ↗
▸BISSTRUCTURAL STABILITY - ALTERATIONS OF EXISTING BUILDINGS1
07/29/2025321793207Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
07/29/2025321793207Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026B00570662-I1Open ↗
▸Approvals, Objections & Sign-offs9
▸BISSCHEDULE A - OCCUPANCY / USE7
08/10/2021321793207Open ↗
08/05/2021321793207Open ↗
08/04/2021321793207Open ↗
Showing 3 of 7 on file for this type
▸BISSUPERSEDING LETTER2
08/24/2022321793207Open ↗
09/16/2021321793207Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
10/04/2019321793207Open ↗
08/29/2019321793207Open ↗
▸Filing & Intake Forms8
▸BISADDITIONAL INFORMATION5
09/15/2025321793207Open ↗
07/22/2025321793207Open ↗
12/15/2023321793207Open ↗
Showing 3 of 5 on file for this type
▸BISBOROUGH INTAKE FORM2
04/19/2021321793207Open ↗
04/19/2021321793207Open ↗
▸BISEFILING COVER SHEET1
08/29/2019321793207Open ↗
▸Other Documents4
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION2
08/05/2021321793207Open ↗
08/05/2021321793207Open ↗
▸BISFIREPLACES1
07/16/2025321793207Open ↗
▸DOB NOWWaiver Document1
09/02/2026B00200489-I1Open ↗