| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/14/2021 | $1000K | — | Private party → Private party | $1,050/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| RMF BRYANT ARCHITECTS | 7 | 05/28/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| FORECAST DESIGN CONST INC | General Contractor | 4 | 07/08/2026 |
| WASOFF PLBG & UTILITY CO | Plumbing | 2 | 07/08/2026 |
| L&J PLG & HTG CO OF NY IN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DEMERARA ENGINEERING, PLL | 4248 | 2 | 07/07/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | FORECAST DESIGN CONST INC | 09/27/2024 |
| DOB NOW | Plumbing | Signed-off | WASOFF PLBG & UTILITY CO | 07/24/2023 |
| DOB NOW | Plumbing | Signed-off | WASOFF PLBG & UTILITY CO | 09/13/2022 |
| DOB NOW | Plumbing | Signed-off | L&J PLG & HTG CO OF NY IN | 12/15/2021 |
| DOB NOW | General Construction | Signed-off | FORECAST DESIGN CONST INC | 12/06/2021 |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/07/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/02/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 01/24/2022 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| 01/03/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/03/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/23/2024 | Energy Code Compliance Inspections | Robyn Fleming | progress |
| 03/03/2023 | Energy Code Compliance Inspections | Robyn Fleming | progress |
| 07/08/2022 | Mechanical Systems | Oscar Walters Jr | special |
| 07/08/2022 | Final | Robyn Fleming | progress |
| 07/08/2022 | Fire-Resistance Rated Construction | Robyn Fleming | progress |
| 07/08/2022 | Energy Code Compliance Inspections | Robyn Fleming | progress |
| 07/08/2022 | Interior lighting power | Robyn Fleming | energy_progress |
| 07/08/2022 | Fenestration and door U-factor and product ratings | Robyn Fleming | energy_progress |
| 07/08/2022 | Lighting in dwelling units | Robyn Fleming | energy_progress |
| 07/05/2022 | Energy Code Compliance Inspections | Robyn Fleming | progress |
| 07/05/2022 | Fire-Resistance Rated Construction | Robyn Fleming | progress |
| 07/05/2022 | Lighting in dwelling units | Robyn Fleming | energy_progress |
| 07/05/2022 | Interior lighting power | Robyn Fleming | energy_progress |
| 07/05/2022 | Fenestration and door U-factor and product ratings | Robyn Fleming | energy_progress |
| 07/05/2022 | Final | Robyn Fleming | progress |
| 07/05/2022 | Mechanical Systems | Oscar Walters Jr | special |