← Back
BuildNYC
Two family frame
39 BELFIELD AVENUE
STATEN ISLAND · BIN 5175888
💬 Discuss this project
2023Year Built
2Stories
B2Building Class
R3XZoning
2,600 sfGross Floor Area
2Units
Two family frame · Owner of record: LLJ Realty · 4,000 sf lot · 0.65 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Roof1p · 1 filing · 20 docs
Floor 25p · 1 filing · 13 docs
Floor 16p · 3 filings · 20 docs
Cellar7p · 2 filings · 20 docs
Site & exterior4p · 1 filing · 13 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Scaglione Architects906/02/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
C P Design Consultants1003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Miranco ContractingGeneral Contractor403/21/2026
JB Buzco PlumbingPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SRA Planning & Expediting5677706/02/2023
Building Lifecycle
10/12/2023
Permit expired, never signed off — Foundation
The city's record still shows this permit as issued, with no sign-off on its filing
S00745320-I1-GC-CX
06/05/2023
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
WILLIAM MONTAGUE
06/05/2023
Special inspection requirement — Subgrade Inspections
WILLIAM MONTAGUE
06/05/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
WILLIAM MONTAGUE
06/05/2023
Special inspection requirement — Concrete - Cast-In-Place
WILLIAM MONTAGUE
50 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offMiranco Contracting04/04/2023
DOB NOWPlumbingSigned-offJB Buzco Plumbing10/14/2022
DOB NOWFoundationPermit IssuedMiranco Contracting10/12/2022
1 project · most recent 06/02/2023
Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScope
06/02/2023Permit IssuedMiranco ContractingAir Conditioning Systems, Heating Systems, Ventilation Systems
1 project · most recent 12/27/2022
General Wiring
FiledStatusContractorScope
12/27/2022CompleteRidge ElectricGeneral Wiring
1 project · most recent 06/02/2023
Wood
FiledStatusContractorScope
06/02/2023Permit IssuedMiranco ContractingWood
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
05/23/2023Pass-Final CND-Occupancy InspectionPassView ↗
05/10/2023Pass-Final Curb Cut Non-Directive 14PassView ↗
01/19/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
10/19/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
10/19/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 62
DateRequirementInspectorRole
06/05/2023Mechanical SystemsWILLIAM MONTAGUEspecial
06/05/2023Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationWILLIAM MONTAGUEspecial
06/05/2023Wood – Prefabricated I-JoistsWILLIAM MONTAGUEspecial
06/05/2023Fire-Resistant Penetrations and JointsWILLIAM MONTAGUEspecial
06/05/2023Concrete - Cast-In-PlaceWILLIAM MONTAGUEspecial
06/05/2023Subgrade InspectionsWILLIAM MONTAGUEspecial
06/05/2023Fire-Resistance Rated ConstructionWILLIAM MONTAGUEprogress
06/05/2023FinalWILLIAM MONTAGUEprogress
06/05/2023Structural Wood FrameWILLIAM MONTAGUEprogress
06/05/2023Energy Code Compliance InspectionsWILLIAM MONTAGUEprogress
06/05/2023Footing and FoundationWILLIAM MONTAGUEprogress
06/05/2023Fenestration areasWILLIAM MONTAGUEenergy_progress
06/05/2023Maintenance informationWILLIAM MONTAGUEenergy_progress
06/05/2023Insulation placement and R valuesWILLIAM MONTAGUEenergy_progress
06/05/2023HVAC-R and service water heating equipmentWILLIAM MONTAGUEenergy_progress
06/05/2023Fenestration and door U-factor and product ratingsWILLIAM MONTAGUEenergy_progress
06/05/2023Air barrier — testing WILLIAM MONTAGUEenergy_progress
06/05/2023Shutoff dampersWILLIAM MONTAGUEenergy_progress
06/05/2023Lighting in dwelling unitsWILLIAM MONTAGUEenergy_progress
06/05/2023HVAC-R and service water heating system controlsWILLIAM MONTAGUEenergy_progress
06/05/2023Air barrier - visual inspectionWILLIAM MONTAGUEenergy_progress
06/05/2023HVAC-R and service water piping design and insulationWILLIAM MONTAGUEenergy_progress
06/05/2023Fenestration air leakageWILLIAM MONTAGUEenergy_progress
06/02/2023Footing and FoundationWILLIAM MONTAGUEprogress
06/02/2023FinalWILLIAM MONTAGUEprogress
Latest 25 of 62.
105 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account