| Owner | Filings | Most Recent |
|---|---|---|
| The Bridge | 4 | 10/20/2026 |
| DP Group GC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| James Stout Architect & Associates | 1 | 02/24/2026 |
| Loring Consulting Engineers | 10 | 01/27/2026 |
| Ashraf | 2 | 11/18/2025 |
| Gace | 2 | 07/15/2025 |
| Valjato Engineering | 2 | 07/02/2025 |
| Tohfaz Uddin PE | 1 | 06/25/2025 |
| Cityscape | 2 | 05/14/2025 |
| Age Engineering | 1 | 11/05/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| Eurocelt Expediting | 4 | 03/21/2026 |
| BMB Building Consulting | 2 | 03/21/2026 |
| Royal Expediting | 1 | 03/21/2026 |
| Select Type | 2 | 03/21/2026 |
| Core Consultants NYC | 13 | 03/21/2026 |
| Sunkeeper Solar Electric | 2 | 03/21/2026 |
| Sheikh Expediting | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RO-Sal Plumbing & Heating | Fire Protection | 10 | 10/20/2026 |
| D.P. Group General Contracting | General Contractor | 9 | 07/08/2026 |
| RO-Sal Plumbing & Heating | Plumbing | 6 | 10/14/2026 |
| Platinum Services NY | Scaffold | 4 | 06/17/2026 |
| All Purpose Electric | Electrical | 1 | 03/22/2026 |
| D.P. Group General Contracting | Scaffold | 1 | 07/08/2026 |
| K&E Builders | Scaffold | 1 | 04/09/2026 |
| Sunkeeper Solar Electric | specialty_contractor | 1 | 04/09/2026 |
| Sunkeeper Solar Electric | Electrical | 1 | 03/21/2026 |
| Tuxedo Electrical Contracting | Electrical | 1 | 03/21/2026 |
| Tuxedo Electrical Contracting | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| James J Stout Architects | 5913 | 1 | 02/24/2026 |
| Vibranalysis Inc., Dba VT | 6864 | 10 | 07/15/2025 |
| Valjato Engineering | 2486 | 2 | 07/02/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Standpipe | Permit Issued | RO-Sal Plumbing & Heating | 10/19/2026 |
| DOB NOW | Plumbing | Permit Issued | RO-Sal Plumbing & Heating | 10/13/2026 |
| DOB NOW | Standpipe | Permit Issued | RO-Sal Plumbing & Heating | 10/13/2026 |
| DOB NOW | Sprinklers | Permit Issued | RO-Sal Plumbing & Heating | 10/13/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Platinum Services NY | 06/15/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | D.P. Group General Contracting | 06/08/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | Qualified Construction | 04/29/2026 |
| DOB NOW | Solar | Permit Issued | Sunkeeper Solar Electric | 02/26/2026 |
| DOB NOW | Standpipe | Permit Issued | RO-Sal Plumbing & Heating | 11/05/2025 |
| DOB NOW | Standpipe | Permit Issued | RO-Sal Plumbing & Heating | 11/05/2025 |
| DOB NOW | Sprinklers | Permit Issued | RO-Sal Plumbing & Heating | 11/03/2025 |
| DOB NOW | Plumbing | Permit Issued | RO-Sal Plumbing & Heating | 11/03/2025 |
| DOB NOW | Suspended Scaffold | Signed-off | D and S Rest and Wtrprng | 10/27/2025 |
| DOB NOW | Standpipe | Permit Issued | RO-Sal Plumbing & Heating | 10/08/2025 |
| DOB NOW | Sprinklers | Permit Issued | RO-Sal Plumbing & Heating | 10/08/2025 |
| DOB NOW | Supported Scaffold | Signed-off | K&E Builders | 09/24/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | D.P. Group General Contracting | 09/16/2025 |
| DOB NOW | Standpipe | Permit Issued | RO-Sal Plumbing & Heating | 09/09/2025 |
| DOB NOW | Plumbing | Permit Issued | RO-Sal Plumbing & Heating | 09/08/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Platinum Services NY | 06/25/2025 |
| DOB NOW | Construction Fence | Permit Issued | D.P. Group General Contracting | 11/12/2024 |
| DOB NOW | Standpipe | Permit Issued | RO-Sal Plumbing & Heating | 10/16/2024 |
| DOB NOW | Sprinklers | Permit Issued | RO-Sal Plumbing & Heating | 10/16/2024 |
| DOB NOW | Structural | Signed-off | D.P. Group General Contracting | 10/09/2024 |
| DOB NOW | Support of Excavation | Signed-off | D.P. Group General Contracting | 10/09/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | D.P. Group General Contracting | 10/09/2024 |
| DOB NOW | Plumbing | Permit Issued | RO-Sal Plumbing & Heating | 10/02/2024 |
| DOB NOW | Standpipe | Permit Issued | RO-Sal Plumbing & Heating | 10/02/2024 |
| BIS | — | ISSUED | D.P. Group General Contracting | 03/27/2025 |
| BIS | — | ISSUED | D.P. Group General Contracting | 03/27/2025 |
| BIS | — | ISSUED | D.P. Group General Contracting | 12/13/2024 |
| BIS | — | ISSUED | D.P. Group General Contracting | 12/13/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/15/2025 | Permit Issued | D.P. Group General Contracting | Air Conditioning Systems, Associated Ducts and Piping, Generators, Heating and Air Conditioning Systems | Cooling Greenheck G-097-VG Exhaust Fan ×4 G-100HP-VG Exhaust Fan ×4 USF-24-B1 Exhaust Fan ×2 AX-41-160-0624 Exhaust Fan ×1 CSP-A1550 Exhaust Fan ×1 CSP-A390-VG Exhaust Fan ×1 Mitsubishi Electric PLFY-EP08NEMU-ER1 8,000 CFM · Vrf Indoor ×3 PEFY-24NEMU-E3 24,000 BTU · Vrf Indoor ×2 PEFY-24NEMAU-E3 24,000 CFM · Vrf Indoor ×1 PLFY-EP36NEMUI-ER1 36,000 BTU · Vrf Indoor ×1 PUHY-EP240TSNU-A 27,000 BTU · Vrf Outdoor ×1 PKA-AK24NL 24,000 BTU · Vrf Outdoor ×4 Ephoca SK92XDX0 8,100 BTU ×1 Ventilation Mitsubishi Electric PEFY-24NMAU-E3 24,000 BTU · Vrf Indoor ×1 PEFY-P18NMAU-E3 36,000 BTU · Vrf Indoor ×5 PKA-A36KA7 36,000 BTU · Split System ×1 PLFY-EP08NEMU-ER1 8,000 BTU · Vrf Indoor ×1 PLFY-EP36NEMU-ER1 36,000 BTU · Vrf Indoor ×1 PUY-A36KNA7 36,000 BTU · Split System ×1 Greenheck G-100HP-VG Exhaust Fan ×30 CP-A1550 ×1 CSP-A1550 Exhaust Fan ×1 G-097-VG Exhaust Fan ×1 SQ-98-VG/G-098-VG 350 CFM · Exhaust Fan ×16 G-100HP-VG/ SQ-99-VG/ 400 CFM · Exhaust Fan ×12 G-100-VG 700 CFM · Exhaust Fan ×8 AX-41-160-0624 6,000 CFM · Exhaust Fan ×4 AX-63-160-0622-A30 6,600 CFM · Exhaust Fan ×4 CSP-A390-VG 75 CFM · Exhaust Fan ×4 SQ-98-VG 250 CFM · Exhaust Fan ×4 SQ-99-VG 560 CFM · Exhaust Fan ×4 USF-24-B1 7,500 CFM · Exhaust Fan ×4 Lfs Systems TLF050 2,500 CFM ×4 Refrigeration Mitsubishi Electric PLFY-EP08NEMU-ER1 8,000 BTU · Vrf Indoor ×1 Generators Generac SG130 130 kW · Generator ×1 Ducts & Piping Mitsubishi Electric PLFY-EP08NEMU-ER1 8,000 BTU · Vrf Indoor ×1 PLFY-EP36NEMU-ER1 36,000 BTU · Vrf Indoor ×1 Heat / Cool Mitsubishi Electric TPLFYP018FM140B/TPLFYP018FM140B/TPEFYP018MA145A 18,000 BTU · Vrf Indoor ×12 TPLFYP008FM140B/TPLFYP008FM140B 8,000 BTU · Vrf Indoor ×8 TURYE0723AN41AN 72,000 BTU · Split System ×8 PCA-AK36NL 36,000 BTU · Vrf Indoor ×4 PEFY-L24NMAU-A 24,000 BTU · Vrf Indoor ×4 PLFY-L15NFMU-A 15,000 BTU · Vrf Indoor ×4 PUY-A36KNA7 36,000 BTU · Split System ×4 PUY-AH24NL 24,000 BTU · Split System ×4 PUZ-AK36NL 36,000 BTU · Split System ×4 TPEFYP054MA144A 54,000 BTU · Vrf Indoor ×4 TPLFYP012FM140B 12,000 BTU · Vrf Indoor ×4 Ephoca APK10N3H2 9,000 BTU · Ptac ×4 Greenheck RVE-40-30D-7A-1-A2 1,360 CFM · Erv ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/15/2025 | Permit Issued | RO-Sal Plumbing & Heating | 1 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/27/2026 | Permit Issued | RO-Sal Plumbing & Heating | Gas, Storm, Water/Sanitary |
| 07/15/2025 | Permit Issued | RO-Sal Plumbing & Heating | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/07/2026 | Permit Issued | Tuxedo Electrical Contracting | — |
| 11/19/2025 | Permit Issued | All Purpose Electric | — |
| 11/02/2025 | Permit Issued | Sunkeeper Solar | — |
| 06/30/2025 | Permit Issued | Richard Neu | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/24/2026 | Permit Issued | Sunkeeper Solar Electric | 67 panels, 35.5 kw, 6,700 roof_area_sqft |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/18/2025 | Signed-off | K&E Builders | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/13/2025 | Signed-off | Qualified Construction | Suspended Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/13/2025 | Signed-off | Qualified Construction | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/03/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/03/2026 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 11/26/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 10/08/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 08/13/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 04/03/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/27/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/14/2025 | Mechanical Systems | JUAN GOMEZ | special |
| 08/14/2025 | Shutoff dampers | JUAN GOMEZ | energy_progress |
| 08/14/2025 | HVAC-R and service water heating system controls | JUAN GOMEZ | energy_progress |
| 08/14/2025 | Maintenance information | JUAN GOMEZ | energy_progress |
| 08/14/2025 | HVAC-R and service water piping design and insulation | JUAN GOMEZ | energy_progress |
| 08/14/2025 | Final | JUAN GOMEZ | progress |
| 08/12/2025 | Post-installed Anchors | JUAN GOMEZ | special |
| 08/12/2025 | Final | JUAN GOMEZ | progress |
| 08/12/2025 | Structural Steel - Details | JUAN GOMEZ | special |
| 08/12/2025 | Structural Steel - High Strength Bolting | JUAN GOMEZ | special |
| 08/12/2025 | Concrete - Cast-In-Place | JUAN GOMEZ | special |
| 08/12/2025 | Structural Steel - Welding | JUAN GOMEZ | special |
| 07/31/2025 | Sprinkler Systems | JUAN GOMEZ | special |
| 07/31/2025 | Fire-Resistant Penetrations and Joints | JUAN GOMEZ | special |
| 07/31/2025 | Standpipe Systems | JUAN GOMEZ | special |
| 07/31/2025 | Post-installed Anchors | JUAN GOMEZ | special |
| 07/07/2025 | Standpipe Systems | JUAN GOMEZ | special |
| 07/07/2025 | Concrete - Cast-In-Place | JUAN GOMEZ | special |
| 07/07/2025 | Post-installed Anchors | JUAN GOMEZ | special |
| 07/07/2025 | Structural Steel - Details | JUAN GOMEZ | special |
| 07/07/2025 | Structural Steel - High Strength Bolting | JUAN GOMEZ | special |
| 07/07/2025 | Structural Steel - Welding | JUAN GOMEZ | special |
| 07/07/2025 | Final | JUAN GOMEZ | progress |
| 07/07/2025 | Mechanical Systems | JUAN GOMEZ | special |
| 07/07/2025 | Final | JUAN GOMEZ | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| The Bridge | Community Facility | Cellar, Floors 1–9, Roof | Project M01355661 Project M01300854 Project M01289523 Project M01238196 Project M00872065 Project M00569500 Project M00570917 Project M00570933 Project M00570944 |