← Back
Special condominium billing lot
390 MANHATTAN AVENUE
BROOKLYN · BIN 3430300
💬 Discuss this project
2024Year Built
1Stories
R0Building Class
R6BZoning
1,722 sfGross Floor Area
—Units
1 Open Violation 0 unresolved · 1 paperwork only ▸FDNY Report ↗
Special condominium billing lot · Owner of record: 390 MANHATTAN AVE LLC · 3,125 sf lot · 0.55 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionGeneral
Roof5p · 1 filing · 20 docs
Bulkhead9p · 1 filing · 20 docs
Floor 57p · 1 filing · 20 docs
Floor 45p · 1 filing · 20 docs
Floor 36p · 1 filing · 20 docs
Floor 213p · 1 filing · 20 docs
Floor 14p · 1 filing · 20 docs
Cellar14p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SALEH AND ASSOCIATES LLC709/24/2025
SIMON JIANG911/08/2024
SALEH & ASSOCIATES809/16/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
B2 CODE CONSULTANTS4803/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
G ENGINEERING PC77782009/24/2025
Building Lifecycle
All (139)Filed (24)Signed Off (1)Violation (4)Objection (80)Special Inspection (30)
09/24/2025
Filed — New Building
Installation of Plumbing and Sprinkler Fixture
B00794549-A8
05/29/2025
Filed — New Building
Installation of Plumbing and Sprinkler Fixture
B00794549-A7
05/29/2025
Special inspection requirement — Electrical motors and elevators
XIONGCAI GU
05/29/2025
Special inspection requirement — HVAC-R and service water heating system controls
XIONGCAI GU
05/29/2025
Special inspection requirement — Shutoff dampers
XIONGCAI GU
05/29/2025
Special inspection requirement — Air barrier - visual inspection
XIONGCAI GU
05/29/2025
Special inspection requirement — Final
XIONGCAI GU
05/29/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
XIONGCAI GU
05/29/2025
Special inspection requirement — Fenestration air leakage
XIONGCAI GU
05/29/2025
Special inspection requirement — Fenestration areas
XIONGCAI GU
05/29/2025
Special inspection requirement — Lighting in dwelling units
XIONGCAI GU
05/29/2025
Special inspection requirement — Protection of exposed foundation insulation
XIONGCAI GU
05/29/2025
Special inspection requirement — Exterior lighting power
XIONGCAI GU
05/29/2025
Special inspection requirement — Metering
XIONGCAI GU
05/29/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
XIONGCAI GU
05/29/2025
Special inspection requirement — Air barrier — testing
XIONGCAI GU
05/29/2025
Special inspection requirement — Maintenance information
XIONGCAI GU
05/29/2025
Special inspection requirement — Insulation placement and R values
XIONGCAI GU
05/29/2025
Special inspection requirement — Interior lighting power
XIONGCAI GU
05/29/2025
Special inspection requirement — Mechanical Systems
XIONGCAI GU
05/29/2025
Special inspection requirement — HVAC-R and service water heating equipment
XIONGCAI GU
05/29/2025
Special inspection requirement — Lighting controls
XIONGCAI GU
11/20/2024
Special inspection requirement — Concrete - Cast-In-Place
XIONGCAI GU
11/20/2024
Special inspection requirement — Subgrade Inspections
XIONGCAI GU
11/20/2024
Special inspection requirement — Footing and Foundation
XIONGCAI GU
11/20/2024
Special inspection requirement — Final
XIONGCAI GU
11/19/2024
Special inspection requirement — Concrete - Cast-In-Place
XIONGCAI GU
11/19/2024
Special inspection requirement — Structural Steel - Welding
XIONGCAI GU
11/19/2024
Special inspection requirement — Masonry
XIONGCAI GU
11/19/2024
Special inspection requirement — Structural Steel - Details
XIONGCAI GU
11/19/2024
Special inspection requirement — Structural Steel - High Strength Bolting
XIONGCAI GU
11/19/2024
Special inspection requirement — Sprayed fire-resistant materials
XIONGCAI GU
11/08/2024
Filed — New Building
Installation of Plumbing and Sprinkler Fixture
B00794549-A4
11/08/2024
Filed — New Building
Installation of Plumbing and Sprinkler Fixture
B00794549-A5
11/04/2024
Filed — New Building
Installation of Plumbing and Sprinkler Fixture
B00794549-A3
09/16/2024
Filed — New Building
Installation of Plumbing and Sprinkler Fixture
B00794549-A6
04/16/2024
Objection resolved — Addressed
04/15/2024
Objection raised — Other
04/05/2024
Filed — New Building
Installation of Plumbing and Sprinkler Fixture
B00794549-A2
04/05/2024
Filed — New Building
Installation of Plumbing and Sprinkler Fixture
B00794549-A1
03/26/2024
Objection resolved — Addressed
03/26/2024
Objection resolved — Addressed
03/26/2024
Objection resolved — Addressed
02/29/2024
Objection raised — Other
02/21/2024
Objection resolved — Addressed
02/15/2024
Violation issued (ECB, closed)
Construction
02/06/2024
Violation issued (ECB, closed)
Construction
02/06/2024
Violation issued (ECB, closed)
Construction
02/06/2024
Violation issued (ECB, open)
Construction
02/05/2024
Objection raised — Other
02/05/2024
Objection raised — Other
02/05/2024
Objection raised — Other
01/24/2024
Filed — New Building
Installation of Plumbing and Sprinkler Fixture
B00794549-P9
01/23/2024
Filed — New Building
Installation of Plumbing and Sprinkler Fixture
B00794549-P8
11/26/2023
Signed off — New Building
Installation of Plumbing and Sprinkler Fixture
B00794549-S4
10/31/2023
Objection resolved — Addressed
10/31/2023
Objection resolved — Addressed
10/31/2023
Objection resolved — Addressed
10/31/2023
Objection resolved — Addressed
10/31/2023
Objection resolved — Addressed
Latest 60 of 139 events.
Nothing on file for this building.
1 project · most recent 09/24/2025
Air Conditioning Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
09/24/2025Permit IssuedBROOKLYN AZ INCAir Conditioning Systems, Heating Systems
Cooling
Mitsubishi Electric MXZ-3C30NAHZ-U1 28,400 BTU · Heat Pump Outdoor ×6
MXZ-SM42NAMHZ-U1 48,000 BTU · Heat Pump Outdoor ×6
MXZ-SM36NAMHZ-U1 36,000 BTU · Heat Pump Outdoor ×3
PUZ-HA24NHA1 23,600 BTU · Heat Pump Outdoor ×3
Fujitsu AOU45RLXFZ 45,000 BTU · Heat Pump Outdoor ×4
AOUG15LZAS1 35,200 BTU · Heat Pump Outdoor ×4
AOU24RLXFZH 22,000 BTU · Heat Pump Outdoor ×2
AOU36RLXFZH 35,200 BTU · Heat Pump Outdoor ×2
Heating
Mitsubishi Electric MXZ-3C30NAHZ-U1 28,600 BTU · Heat Pump Outdoor ×6
MXZ-SM36NAMHZ-U1 45,000 BTU · Heat Pump Outdoor ×3
MXZ-SM42NAMHZ-U1 48,000 BTU · Heat Pump Outdoor ×3
PUZ-HA24NHA1 25,000 BTU · Heat Pump Outdoor ×3
Fujitsu AOU45RLXFZ 36,400 BTU · Heat Pump Outdoor ×8
AOU24RLXFZH 25,000 BTU · Heat Pump Outdoor ×2
AOU36RLXFZH 36,400 BTU · Heat Pump Outdoor ×2
1 project · most recent 09/24/2025
Sprinkler System
FiledStatusContractorScope
09/24/2025Signed-offPARAMOUNT SERVICES, LLCSprinkler System
1 project · most recent 09/24/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
09/24/2025Signed-offVILLAGE P & H NY INCGas, Storm, Water/Sanitary
1 project · most recent 09/24/2025
Steel Concrete Masonry
FiledStatusContractorScope
09/24/2025Signed-offVILLAGE P & H NY INCSteel, Concrete, Masonry
1 project · most recent 09/24/2025
Fence
FiledStatusContractorScope
09/24/2025Signed-offVILLAGE P & H NY INCFence
1 project · most recent 09/24/2025
Earthwork
FiledStatusContractorScope
09/24/2025Signed-offVILLAGE P & H NY INCEarthwork
▾Special Inspection Requirements (DOB NOW) — 94
DateRequirementInspectorRole
05/29/2025FinalXIONGCAI GUprogress
05/29/2025Protection of exposed foundation insulationXIONGCAI GUenergy_progress
05/29/2025Insulation placement and R valuesXIONGCAI GUenergy_progress
05/29/2025Interior lighting powerXIONGCAI GUenergy_progress
05/29/2025Mechanical SystemsXIONGCAI GUspecial
05/29/2025Fenestration and door U-factor and product ratingsXIONGCAI GUenergy_progress
05/29/2025Lighting in dwelling unitsXIONGCAI GUenergy_progress
05/29/2025Lighting controlsXIONGCAI GUenergy_progress
05/29/2025HVAC-R and service water heating system controlsXIONGCAI GUenergy_progress
05/29/2025HVAC-R and service water heating equipmentXIONGCAI GUenergy_progress
05/29/2025Shutoff dampersXIONGCAI GUenergy_progress
05/29/2025MeteringXIONGCAI GUenergy_progress
05/29/2025Exterior lighting powerXIONGCAI GUenergy_progress
05/29/2025Fenestration areasXIONGCAI GUenergy_progress
05/29/2025Fenestration air leakageXIONGCAI GUenergy_progress
05/29/2025HVAC-R and service water piping design and insulationXIONGCAI GUenergy_progress
05/29/2025Air barrier — testing XIONGCAI GUenergy_progress
05/29/2025Electrical motors and elevatorsXIONGCAI GUenergy_progress
05/29/2025Maintenance informationXIONGCAI GUenergy_progress
05/29/2025Air barrier - visual inspectionXIONGCAI GUenergy_progress
11/20/2024FinalXIONGCAI GUprogress
11/20/2024Footing and FoundationXIONGCAI GUprogress
11/20/2024Subgrade InspectionsXIONGCAI GUspecial
11/20/2024Concrete - Cast-In-PlaceXIONGCAI GUspecial
11/19/2024FinalXIONGCAI GUprogress
Latest 25 of 94.
▾Documents — 209 on file (BIS + DOB NOW)
▸Plans & Drawings24
▸DOB NOWPlans/Sketch24
08/25/2026B00794549-I1Request digital key ↗
08/25/2026B00794549-A7Request digital key ↗
08/25/2026B00794549-P7Request digital key ↗
Showing 3 of 24 on file for this type
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION3
06/18/2025340880256Open ↗
06/18/2025340880256Open ↗
05/17/2024322114298Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
01/11/2024340880256Open ↗
▸Zoning, Tax Lot & Property Records17
▸DOB NOWZD1: DOB Zoning Diagram6
08/13/2026B00794549-P2Open ↗
08/13/2026B00794549-A3Open ↗
08/13/2026B00794549-P8Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWZoning Exhibit form (1-5)6
08/13/2026B00794549-P8Open ↗
08/13/2026B00794549-A3Open ↗
08/13/2026B00794549-P2Open ↗
Showing 3 of 6 on file for this type
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED2
06/06/2024322114298Open ↗
12/29/2023340880256Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
06/06/2024322114298Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
06/06/2024322114298Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00794549-I1Open ↗
▸Seals & Professional Certifications112
▸DOB NOWProgress Inspector Seal & Signature56
09/02/2026B00794549-A4Open ↗
09/02/2026B00794549-A4Open ↗
09/02/2026B00794549-S1Open ↗
Showing 3 of 56 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature30
09/02/2026B00794549-A4Open ↗
09/02/2026B00794549-A4Open ↗
09/02/2026B00794549-S1Open ↗
Showing 3 of 30 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature24
08/25/2026B00794549-A7Open ↗
08/25/2026B00794549-P4Open ↗
08/25/2026B00794549-S3Open ↗
Showing 3 of 24 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
12/29/2023340880256Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
06/18/2025340880256Open ↗
▸Trade Schedules & Equipment6
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)6
08/13/2026B00794549-A3Open ↗
08/13/2026B00794549-A7Open ↗
08/13/2026B00794549-A8Open ↗
Showing 3 of 6 on file for this type
▸Safety & Tenant Protection12
▸DOB NOWStreet Tree Checklist6
08/25/2026B00794549-I1Open ↗
08/25/2026B00794549-A7Open ↗
08/25/2026B00794549-A3Open ↗
Showing 3 of 6 on file for this type
▸BISBPP: STREET TREES SITE PLAN1
12/29/2023340880256Open ↗
▸BISSTREET TREE CHECKLIST1
12/29/2023340880256Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
12/29/2023340880256Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026B00794549-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026B00794549-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00794549-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis1
08/25/2026B00794549-I1Open ↗
▸Approvals, Objections & Sign-offs4
▸BISLETTERS - SUPPORTING DOCUMENTATION4
06/06/2024322114298Open ↗
06/06/2024322114298Open ↗
06/06/2024322114298Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms4
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
12/29/2023340880256Open ↗
▸BISEFILING COVER SHEET1
05/17/2024322114298Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
12/29/2023340880256Open ↗
▸BISADDITIONAL INFORMATION1
12/29/2023340880256Open ↗
▸Other Documents25
▸DOB NOWSite Survey: Initial6
08/13/2026B00794549-P8Open ↗
08/13/2026B00794549-P2Open ↗
08/13/2026B00794549-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone6
08/13/2026B00794549-A3Open ↗
08/13/2026B00794549-P2Open ↗
08/13/2026B00794549-P8Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProperty Ownership Certification6
08/25/2026B00794549-I1Open ↗
08/25/2026B00794549-A7Open ↗
08/25/2026B00794549-A3Open ↗
Showing 3 of 6 on file for this type
▸BISBPP - SUPPORTING DOCUMENTATION2
12/29/2023340880256Open ↗
12/29/2023340880256Open ↗
▸DOB NOWAdjoining Owners Notification2
08/13/2026B00794549-S4Open ↗
08/13/2026B00794549-S2Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
06/06/2024322114298Open ↗
▸BISVERIFY DOB PLAN NAMING STANDARD IS MET1
06/06/2024322114298Open ↗
▸DOB NOWFinal Survey1
08/13/2026B00794549-I1Open ↗