| Owner | Filings | Most Recent |
|---|---|---|
| HHLA VENTURE I | 28 | 07/08/2026 |
| METHOD GENERAL CONTRACTOR | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/24/2022 | $1.3M | — | THE PEOPLES COMMUNITY TEMPLE INC. → HHLA VENTURE I LLC | $432/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| A.S.III DESIGN STUDIO | 8 | 10/01/2024 |
| PAUL G. JONES, P.E. | 1 | 07/07/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| PROFESSIONAL SOLUTIONS | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| METHOD GENERAL CONTRACTOR | General Contractor | 8 | 07/08/2026 |
| CONSOLIDATED SCAFFOLDING | General Contractor | 2 | 04/09/2026 |
| METHOD ELECTRIC LLC | Electrical | 1 | 03/22/2026 |
| F.S. WORKS INC | Fire Protection | 1 | 07/08/2026 |
| CCS. CUSTOM CONSTRUCTION | General Contractor | 1 | 04/09/2026 |
| P.H. WORKS INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ENGINEERING CONSULTING SE | 2050 | 8 | 10/01/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | METHOD GENERAL CONTRACTOR | 02/23/2024 |
| DOB NOW | General Construction | Permit Issued | METHOD GENERAL CONTRACTOR | 02/20/2024 |
| DOB NOW | General Construction | Permit Issued | METHOD GENERAL CONTRACTOR | 02/08/2024 |
| DOB NOW | Plumbing | Signed-off | F.S. WORKS INC | 01/11/2024 |
| DOB NOW | Sprinklers | Signed-off | P.H. WORKS INC | 10/03/2023 |
| DOB NOW | Supported Scaffold | Signed-off | CONSOLIDATED SCAFFOLDING | 07/10/2023 |
| DOB NOW | Supported Scaffold | Signed-off | CONSOLIDATED SCAFFOLDING | 07/10/2023 |
| DOB NOW | Structural | Permit Issued | METHOD GENERAL CONTRACTOR | 05/16/2023 |
| DOB NOW | Structural | Signed-off | METHOD GENERAL CONTRACTOR | 02/27/2023 |
| DOB NOW | Structural | Signed-off | METHOD GENERAL CONTRACTOR | 12/08/2022 |
| DOB NOW | General Construction | Signed-off | CCS. CUSTOM CONSTRUCTION | 07/25/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/01/2024 | Permit Issued | METHOD GENERAL CONTRACTOR | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MLZ-KP09NA2 9,000 BTU · Fan Coil Indoor ×16 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/03/2024 | Complete | METHOD ELECTRIC LLC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/01/2024 | Permit Issued | METHOD GENERAL CONTRACTOR | Steel, Masonry, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/05/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/14/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/30/2024 | Pass-Final SP - Up to 9 Requested Floors | Pass | View ↗ |
| 08/16/2024 | Pass-Final SP - Up to 9 Requested Floors | Pass | View ↗ |
| 08/09/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/29/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/25/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/13/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| 11/13/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/27/2025 | Mechanical Systems | PAUL MARINO | special |
| 01/27/2025 | Energy Code Compliance Inspections | PAUL MARINO | progress |
| 01/27/2025 | Fire-Resistance Rated Construction | PAUL MARINO | progress |
| 01/27/2025 | HVAC-R and service water piping design and insulation | PAUL MARINO | energy_progress |
| 01/27/2025 | HVAC-R and service water heating equipment | PAUL MARINO | energy_progress |
| 01/27/2025 | Shutoff dampers | PAUL MARINO | energy_progress |
| 01/27/2025 | Structural Stability – Alterations of existing buildings | PAUL MARINO | special |
| 01/27/2025 | Structural Steel - Details | PAUL MARINO | special |
| 01/27/2025 | Construction Operations Influencing Adjacent Structures | PAUL MARINO | special |
| 01/27/2025 | Masonry | PAUL MARINO | special |
| 01/27/2025 | Fire-Resistant Penetrations and Joints | PAUL MARINO | special |
| 01/27/2025 | Final | ALBERT SMITH III | progress |
| 01/27/2025 | Exterior lighting power | PAUL MARINO | energy_progress |
| 01/27/2025 | Lighting controls | PAUL MARINO | energy_progress |
| 01/27/2025 | Maintenance information | PAUL MARINO | energy_progress |
| 01/27/2025 | Metering | PAUL MARINO | energy_progress |
| 01/27/2025 | Lighting in dwelling units | PAUL MARINO | energy_progress |
| 01/27/2025 | Vestibules | PAUL MARINO | energy_progress |
| 01/27/2025 | Insulation placement and R values | PAUL MARINO | energy_progress |
| 01/27/2025 | Fenestration and door U-factor and product ratings | PAUL MARINO | energy_progress |
| 01/27/2025 | Fenestration areas | PAUL MARINO | energy_progress |
| 01/27/2025 | Fenestration air leakage | PAUL MARINO | energy_progress |
| 01/27/2025 | HVAC-R and service water heating system controls | PAUL MARINO | energy_progress |
| 01/27/2025 | Duct leakage testing, insulation and design | PAUL MARINO | energy_progress |
| 01/27/2025 | Air barrier - visual inspection | PAUL MARINO | energy_progress |