| Owner | Filings | Most Recent |
|---|---|---|
| NYU Langone Health | 7 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Think Design Architecture | 3 | 04/25/2022 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Raise the Roof GC | General Contractor | 3 | 03/21/2026 |
| Rock Solid Landscape | specialty_contractor | 3 | 03/21/2026 |
| Capital Contracting P&H | Plumbing | 1 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | Raise the Roof GC | 12/09/2022 |
| DOB NOW | Plumbing | Signed-off | Capital Contracting P&H | 09/20/2021 |
| DOB NOW | General Construction | Signed-off | Rock Solid Landscape | 09/16/2021 |
| BIS | — | ISSUED | Francis Minunni | 08/04/2009 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/25/2022 | Energy Code Compliance Inspections | Frank Martarella III | progress |
| 04/25/2022 | Electrical motors and elevators | Frank Martarella III | energy_progress |
| 04/25/2022 | Maintenance information | Frank Martarella III | energy_progress |
| 04/20/2022 | Energy Code Compliance Inspections | Frank Martarella III | progress |
| 04/20/2022 | Electrical motors and elevators | Frank Martarella III | energy_progress |
| 04/20/2022 | Maintenance information | Frank Martarella III | energy_progress |