| Owner | Filings | Most Recent |
|---|---|---|
| J B PRO CONTRACTING | 42 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| PAUL CHRISTAKOS ARCHITECTURE | 4 | 04/22/2023 |
| KCE CONSULTING ENGINEERING PLLC | 2 | 08/09/2022 |
| DOYUN KIM; RA | 1 | 02/18/2022 |
| LEVIN ENGINEERING PLLC | 2 | 10/20/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| KC EXPEDITING | 6 | 03/21/2026 |
| LEVIN ENGINEERING PLLC | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NICOLOSI BROS INC | General Contractor | 15 | 07/08/2026 |
| ALL PRO PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MARKANICS CORP | 4600 | 4 | 04/22/2023 |
| DOYUN KIM; RA | 7415 | 3 | 05/27/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | ALL PRO PLBG & HTG INC | 06/03/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | NICOLOSI BROS INC | 05/24/2024 |
| DOB NOW | General Construction | Permit Issued | NICOLOSI BROS INC | 05/01/2024 |
| DOB NOW | Construction Fence | Permit Issued | NICOLOSI BROS INC | 04/19/2024 |
| DOB NOW | General Construction | Permit Issued | NICOLOSI BROS INC | 08/11/2023 |
| DOB NOW | Structural | Permit Issued | NICOLOSI BROS INC | 08/11/2023 |
| DOB NOW | Plumbing | Permit Issued | ALL PRO PLBG & HTG INC | 05/18/2023 |
| DOB NOW | General Construction | Permit Issued | NICOLOSI BROS INC | 03/27/2023 |
| DOB NOW | Construction Fence | Permit Issued | NICOLOSI BROS INC | 01/20/2023 |
| DOB NOW | General Construction | Permit Issued | NICOLOSI BROS INC | 09/13/2022 |
| DOB NOW | Structural | Permit Issued | NICOLOSI BROS INC | 09/09/2022 |
| DOB NOW | Earth Work | Permit Issued | NICOLOSI BROS INC | 06/29/2022 |
| DOB NOW | Construction Fence | Permit Issued | NICOLOSI BROS INC | 06/15/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/20/2021 | Permit Issued | ALL PRO PLBG & HTG INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/13/2026 | Permit Issued | R.C.M. ELECTRIC CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2023 | Permit Issued | NICOLOSI BROS INC | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/17/2022 | Permit Issued | NICOLOSI BROS INC | Fence |
| 02/18/2022 | Permit Issued | NICOLOSI BROS INC | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2023 | Permit Issued | NICOLOSI BROS INC | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/28/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/27/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/24/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/24/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 11/24/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 11/24/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/24/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/24/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/17/2023 | Fire-Resistant Penetrations and Joints | Malcolm Barkan | special |
| 04/17/2023 | Energy Code Compliance Inspections | DOYUN KIM | progress |
| 04/17/2023 | Fire-Resistance Rated Construction | DOYUN KIM | progress |
| 04/17/2023 | Interior lighting power | DOYUN KIM | energy_progress |
| 04/17/2023 | Fenestration areas | DOYUN KIM | energy_progress |
| 04/17/2023 | Air barrier - visual inspection | DOYUN KIM | energy_progress |
| 04/17/2023 | Fenestration air leakage | DOYUN KIM | energy_progress |
| 04/17/2023 | Lighting controls | DOYUN KIM | energy_progress |
| 04/17/2023 | Insulation placement and R values | DOYUN KIM | energy_progress |
| 04/17/2023 | Exterior lighting power | DOYUN KIM | energy_progress |
| 04/17/2023 | Fenestration and door U-factor and product ratings | DOYUN KIM | energy_progress |
| 07/26/2022 | Concrete - Cast-In-Place | Malcolm Barkan | special |
| 07/26/2022 | Masonry | Malcolm Barkan | special |
| 07/26/2022 | Structural Steel - Details | Malcolm Barkan | special |
| 07/26/2022 | Structural Steel - High Strength Bolting | Malcolm Barkan | special |
| 07/26/2022 | Structural Steel - Welding | Malcolm Barkan | special |
| 07/26/2022 | Final | JEFFREY BELL | progress |
| 08/12/2021 | Mechanical Systems | DOYUN KIM | special |
| 08/12/2021 | Heating Systems | DOYUN KIM | special |
| 08/12/2021 | Final | JEFFREY BELL | progress |
| 08/12/2021 | HVAC-R and service water heating equipment | JEFFREY BELL | energy_progress |
| 08/12/2021 | HVAC-R and service water piping design and insulation | JEFFREY BELL | energy_progress |
| 08/12/2021 | Maintenance information | JEFFREY BELL | energy_progress |
| 08/12/2021 | HVAC-R and service water heating system controls | JEFFREY BELL | energy_progress |
| 08/12/2021 | Fire-Resistant Penetrations and Joints | DOYUN KIM | special |