← Back
BuildNYC
Unlicensed parking lot
4-44 BEACH 67TH STREET
QUEENS · BIN 4595335
💬 Discuss this project
0Year Built
—Stories
G7Building Class
R6Zoning
0 sfGross Floor Area
0Units
7 Active Violations ▸FDNY Report ↗
Unlicensed parking lot · Owner of record: God's Battalion of Prayer Properties · 4,000 sf lot · 0 FAR built · Flood zone AE
Locations of Work
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Whole building & multi-floor projectsDlac Senior Residence1 filing
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Martin H. Kapell207/19/2025
Wexler Associates303/28/2023
Skyline303/24/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
KM Associates of New York803/21/2026
K & M Associates803/21/2026
Building Lifecycle
All (107)Filed (8)Violation (7)Objection (62)Special Inspection (30)
06/23/2026
Objection resolved — Resolved
03/26/2026
Special inspection requirement — Sprayed fire-resistant materials
03/26/2026
Special inspection requirement — Lighting in dwelling units
03/26/2026
Special inspection requirement — HVAC-R and service water heating system controls
03/26/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
03/26/2026
Special inspection requirement — Maintenance information
03/26/2026
Special inspection requirement — Air barrier - visual inspection
03/26/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
03/26/2026
Special inspection requirement — Fenestration areas
03/26/2026
Special inspection requirement — Metering
03/26/2026
Special inspection requirement — Insulation placement and R values
03/26/2026
Special inspection requirement — Fireplaces
03/26/2026
Special inspection requirement — Permanent certificate
03/26/2026
Special inspection requirement — Air barrier continuity plan testing
03/26/2026
Special inspection requirement — Interior lighting power
03/26/2026
Special inspection requirement — HVAC-R and service water heating equipment
03/26/2026
Special inspection requirement — Protection of exposed foundation insulation
03/26/2026
Special inspection requirement — Lighting controls
03/26/2026
Special inspection requirement — Duct leakage testing, insulation and design
03/26/2026
Special inspection requirement — Electrical motors and elevators
03/26/2026
Special inspection requirement — Vestibules
03/26/2026
Special inspection requirement — Exterior lighting power
03/26/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
03/26/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
03/26/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
03/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
03/26/2026
Special inspection requirement — Masonry
03/26/2026
Special inspection requirement — Mastic and Intumescent Fire-resistant Coatings
03/26/2026
Special inspection requirement — Subgrade Inspections
03/26/2026
Special inspection requirement — Underpinning
03/26/2026
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
02/09/2026
Objection raised — Other
02/02/2026
Objection resolved — Resolved
12/23/2025
Objection resolved — Resolved
11/06/2025
Objection resolved — Resolved
11/06/2025
Objection resolved — Resolved
11/06/2025
Objection resolved — Resolved
09/08/2025
Objection resolved — Addressed
09/08/2025
Objection resolved — Addressed
09/08/2025
Objection resolved — Addressed
08/05/2025
Objection raised — Other
07/19/2025
Filed — New Building
Mechanical application filed in conjunction with an NB
Q00761543-Z1
05/09/2025
Objection resolved — Resolved
05/09/2025
Objection resolved — Resolved
05/09/2025
Objection resolved — Resolved
05/09/2025
Objection resolved — Addressed
05/09/2025
Objection resolved — Addressed
05/09/2025
Objection resolved — Resolved
05/09/2025
Objection resolved — Resolved
05/09/2025
Objection resolved — Addressed
05/09/2025
Objection resolved — Resolved
07/18/2023
Objection raised — Other
06/26/2023
Objection resolved — Addressed
05/30/2023
Objection resolved — Addressed
05/12/2023
Objection resolved — Addressed
04/21/2023
Objection resolved — Addressed
04/03/2023
Objection raised — Energy
04/03/2023
Objection raised — Scope
04/03/2023
Objection raised — Inspections
04/03/2023
Objection raised — Admin
Latest 60 of 107 events.
Nothing on file for this building.
1 project · most recent 07/19/2025
Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
07/19/2025——Air Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Lg ×4
Heating
Neotherm LLARS NEOTHERM LC NTH 1200 193 tons · Boiler ×2
Ventilation
Greenheck Greenheck G-098-VG 120 CFM · Exhaust Fan ×8
Greenheck G-097-VG 120 CFM · Exhaust Fan ×5
Lg LG ARNU36B8A4 40,600 BTU · Vrf Indoor ×2
LG ARNU183SKA4 21,500 BTU · Vrf Indoor ×1
LG ARNU18B8A4 19,100 BTU · Vrf Indoor ×1
LG ARNU18BHA4 21,500 BTU · Vrf Indoor ×1
LG ARNU24BHA4 27,300 BTU · Vrf Indoor ×1
LG ARNU24SKA4 25,600 BTU · Vrf Indoor ×1
LG ARNU42B8A4 42,200 BTU · Vrf Indoor ×1
__Junk__ AX-72-190-0617-A50 209 CFM · Exhaust Fan ×2
SS1-12-432-D 120 CFM · Exhaust Fan ×1
1 project · most recent 07/19/2025
Sprinkler System
FiledStatusContractorScope
07/19/2025——Sprinkler System
1 project · most recent 07/19/2025
Steel Concrete Masonry
FiledStatusContractorScope
07/19/2025——Steel, Concrete, Masonry
▾Special Inspection Requirements (DOB NOW) — 51
DateRequirementInspectorRole
03/26/2026Sprayed fire-resistant materials—special
03/26/2026Lighting in dwelling units—energy_progress
03/26/2026HVAC-R and service water heating system controls—energy_progress
03/26/2026Fenestration and door U-factor and product ratings—energy_progress
03/26/2026Maintenance information—energy_progress
03/26/2026Air barrier - visual inspection—energy_progress
03/26/2026HVAC-R and service water piping design and insulation—energy_progress
03/26/2026Fenestration areas—energy_progress
03/26/2026Metering—energy_progress
03/26/2026Insulation placement and R values—energy_progress
03/26/2026Fireplaces—energy_progress
03/26/2026Permanent certificate—energy_progress
03/26/2026Air barrier continuity plan testing—energy_progress
03/26/2026Interior lighting power—energy_progress
03/26/2026HVAC-R and service water heating equipment—energy_progress
03/26/2026Protection of exposed foundation insulation—energy_progress
03/26/2026Lighting controls—energy_progress
03/26/2026Duct leakage testing, insulation and design—energy_progress
03/26/2026Electrical motors and elevators—energy_progress
03/26/2026Vestibules—energy_progress
03/26/2026Exterior lighting power—energy_progress
03/26/2026Alternative Materials - OTCR Buildings Bulletin Number—special
03/26/2026Excavations - Sheeting, Shoring, and Bracing—special
03/26/2026Exterior Insulation and Finish Systems (EIFS)—special
03/26/2026Fire-Resistant Penetrations and Joints—special
Latest 25 of 51.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Dlac Senior ResidenceResidentialCellar, Floors 1–9
Project Q00761543 New Building · Objections · 09/20/2022
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 36 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/25/2026Q00761543-Z1Request digital key ↗
08/15/2026Q00761543-I1Request digital key ↗
08/15/2026Q00761543-S1Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits2
▸BISBPP-5 - Authorization to the Department of Transportation1
11/12/2025440824226Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
11/12/2025440824226Open ↗
▸Zoning, Tax Lot & Property Records3
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
11/12/2025440824226Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/15/2026Q00761543-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/15/2026Q00761543-I1Open ↗
▸Seals & Professional Certifications10
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/25/2026Q00761543-S4Open ↗
08/25/2026Q00761543-I1Open ↗
08/25/2026Q00761543-S1Open ↗
Showing 3 of 8 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
11/12/2025440824226Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
11/12/2025440824226Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/15/2026Q00761543-I1Open ↗
▸Inspections & Test Reports1
▸DOB NOWSOIL REPORT1
08/15/2026Q00761543-S1Open ↗
▸Approvals, Objections & Sign-offs8
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter8
08/25/2026Q00761543-Z1Open ↗
08/15/2026Q00761543-I1Open ↗
08/15/2026Q00761543-S1Open ↗
Showing 3 of 8 on file for this type
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
11/12/2025440824226Open ↗
▸Other Documents2
▸DOB NOWSite Survey: Initial1
08/15/2026Q00761543-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/15/2026Q00761543-I1Open ↗