| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/06/2026 | Permit Issued | MILLENIUM CENT CONTR CORP | Ventilation Systems | Ventilation |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/06/2026 | Signed-off | 2M MECHANICAL LLC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/23/2025 | Complete | LIMITLESS ELECT RESOURCES | — |
| 01/28/2025 | Complete | GMJ ELECTRIC CORP | General Wiring |
| 11/27/2023 | Complete | VERTEX ELECTRIC CORP. | General Wiring |
| 10/05/2021 | Complete | MEGA ELEC'L CONTR'G, INC | — |
| Owner | Filings | Most Recent |
|---|---|---|
| BELL REALTY HOLDINGS | 35 | 07/08/2026 |
| COMPLETE MAINTENANCE GROUP | 3 | 07/08/2026 |
| BRAXI REALTY LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/03/2016 | $1.4M | — | — → — | $530/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| P GEORGOPOULOS ARCHITECT PC | 5 | 08/06/2026 |
| RDDNY DESIGN BUILD CORP | 8 | 06/06/2025 |
| LEON SKVIRSKY PE | 1 | 05/15/2025 |
| RAS PE CONSULTING ENGINEERS | 1 | 12/08/2021 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 10/13/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| BUILDING BROTHERS | 2 | 03/21/2026 |
| RDDNY DESIGN BUILD | 8 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| STATIC CONSTRUCTION INC | General Contractor | 6 | 03/21/2026 |
| MILLENIUM CENT CONTR CORP | General Contractor | 3 | 03/21/2026 |
| RDDNY DESIGN BUILD CORP | General Contractor | 3 | 07/08/2026 |
| EMPIRE NY INSTALLATIONS INC | General Contractor | 1 | 07/08/2026 |
| DPH PLUMBING & HTG CORP | Plumbing | 1 | 07/08/2026 |
| JUST PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| PAUL SIGNS | Scaffold | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| P GEORGOPOULOS ARCHITECT | 889 | 4 | 08/06/2026 |
| SD TESTING & INSPECTION S | 7010 | 6 | 06/06/2025 |
| ABDUS SALAM C. ENGINEERS | 484 | 1 | 12/08/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sign | Signed-off | PAUL SIGNS, INC | 05/21/2025 |
| DOB NOW | Mechanical Systems | Signed-off | RDDNY DESIGN BUILD CORP | 02/11/2025 |
| DOB NOW | Plumbing | Signed-off | DPH PLUMBING & HTG CORP | 01/22/2025 |
| DOB NOW | General Construction | Signed-off | RDDNY DESIGN BUILD CORP | 01/10/2025 |
| DOB NOW | Construction Fence | Signed-off | RDDNY DESIGN BUILD CORP | 01/06/2025 |
| DOB NOW | Plumbing | Signed-off | MOHAMED ABDELRAZEK | 12/11/2023 |
| DOB NOW | General Construction | Permit Issued | MILLENIUM CENT CONTR CORP | 11/09/2023 |
| DOB NOW | General Construction | Signed-off | STATIC CONSTRUCTION INC | 04/14/2022 |
| DOB NOW | Structural | Signed-off | STATIC CONSTRUCTION INC | 12/13/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | EMPIRE NY INSTALLATIONS I | 10/13/2021 |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/25/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/09/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/19/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/27/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/08/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 05/22/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 03/25/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 02/27/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/27/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/14/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/06/2026 | HVAC-R and service water piping design and insulation | Vasilios Georgopoulos | energy_progress |
| 08/06/2026 | Mechanical Systems | Vasilios Georgopoulos | special |
| 08/06/2026 | Final | Vasilios Georgopoulos | progress |
| 08/06/2026 | HVAC-R and service water heating system controls | Vasilios Georgopoulos | energy_progress |
| 08/06/2026 | HVAC-R and service water heating equipment | Vasilios Georgopoulos | energy_progress |
| 03/03/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 03/03/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 03/03/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 03/03/2026 | Mechanical Systems | Vasilios Georgopoulos | special |
| 03/03/2026 | Final | Vasilios Georgopoulos | progress |
| 09/22/2025 | HVAC-R and service water heating system controls | — | energy_progress |
| 09/22/2025 | HVAC-R and service water heating equipment | — | energy_progress |
| 09/22/2025 | Final | Vasilios Georgopoulos | progress |
| 09/22/2025 | Mechanical Systems | Vasilios Georgopoulos | special |
| 09/22/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 06/06/2025 | Tenant Protection Plan Compliance | XIUCHENG LI | special |
| 06/06/2025 | Final | ROMAN STRAZHKO | progress |
| 06/06/2025 | Fire-Resistant Penetrations and Joints | XIUCHENG LI | special |
| 06/03/2025 | Final | ROMAN STRAZHKO | progress |
| 06/03/2025 | Tenant Protection Plan Compliance | XIUCHENG LI | special |
| 06/03/2025 | Fire-Resistant Penetrations and Joints | XIUCHENG LI | special |
| 05/28/2025 | Mechanical Systems | XIUCHENG LI | special |
| 05/28/2025 | Tenant Protection Plan Compliance | XIUCHENG LI | special |
| 05/28/2025 | Fire-Resistant Penetrations and Joints | XIUCHENG LI | special |
| 05/28/2025 | Energy Code Compliance Inspections | ROMAN STRAZHKO | progress |